Crown Builders, Inc. v. STOWE ENGINEERING CORP.

8 F. Supp. 2d 483, 39 V.I. 249, 1998 WL 318218
CourtDistrict Court, Virgin Islands
DecidedJune 10, 1998
DocketCiv.1997-176
StatusPublished
Cited by3 cases

This text of 8 F. Supp. 2d 483 (Crown Builders, Inc. v. STOWE ENGINEERING CORP.) is published on Counsel Stack Legal Research, covering District Court, Virgin Islands primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crown Builders, Inc. v. STOWE ENGINEERING CORP., 8 F. Supp. 2d 483, 39 V.I. 249, 1998 WL 318218 (vid 1998).

Opinion

MEMORANDUM

Moore, Chief Judge.

Plaintiff's motion for a preliminary injunction DENIED; and plaintiff's motion for attachment DENIED WITHOUT PREJUDICE.

*250 INTRODUCTION

The Court is here presented with a request to reconsider its ten-year old precedent holding the Virgin Islands statute providing for prejudgment attachment "unconstitutional on its face for its total failure to safeguard the defendant's due process rights." Walsh v. Edward J. Gerrits, Inc., 24 V.I. 118 (D.V.I. 1988). 1 The statute is found at V.I. Code Ann. tit. 5, §§ 251-73 (1997) ["Attachment Statute"]. The Walsh decision, which was not appealed, is only one paragraph of nine or ten lines in length. The opinion contains no analysis. It simply cites four Supreme Court cases and states that "due process requires that the defendant be afforded notice and opportunity for a hearing and participation of a judicial officer, when his property is seized. Our local statue completely ignores fourteenth amendment principles of due process," 2 The four cases are: North Georgia Finishing, Inc. v. Di-Chem, Inc., 419 U.S. 601, 606, 42 L. Ed. 2d 751, 95 S. Ct. 719 (1975); Mitchell v. W.T. Grant Co., 416 U.S. 600, 628, 40 L. Ed. 2d 406, 94 S. Ct. 1895 (1974); Fuentes v. Shevin, 407 U.S. 67, 32 L. Ed. 2d 556, 92 S. Ct. 1983 (1972); and Sniadach v. Family Finance Corporation of Bay View, 395 U.S. 337, 23 L. Ed. 2d 349, 89 S. Ct. 1820 (1969).

This issue arises in the context of a dispute between a contractor, Stowe Engineering Corporation ["Stowe"], and one of its subcontractors, Crown Builders, Inc. ["Crown"], regarding Stowe's alleged failure to pay Crown for work done on a heat recovery steam generator project at the St. Thomas facility of the Virgin Islands Water and Power Authority ["WAPA"]. Crown, the subcontractor, filed a complaint alleging that the general contractor, Stowe, is indebted to it for work done and that WAPA, as the owner of the property, owes and is about to pay Stowe for work on the project. Because the property of WAPA is exempt from all liens *251 and execution, 3 Crown was denied the usual protection of a construction lien 4 against the land and property of the owner whose property is improved by the subcontractor's efforts.

Giving notice to Stowe and requesting a hearing, Crown moved for a prejudgment attachment against Stowe to ensure that Crown would be paid when WAPA pays Stowe. 5 In support of its motion, Crown submitted the affidavit of its president. Stowe opposed the motion and filed the affidavit of its president. At the hearing on the motion, the parties agreed to maintain the status quo pending a ruling, and the Court gave them time to brief whether the Court should reconsider Walsh and uphold the constitutionality of the Virgin Islands Attachment Statute. Since the hearing, the parties have stipulated to stay all aspects of this action, save this motion for prejudgment attachment, pending arbitration. The briefs of the parties have been filed and the Court here issues its ruling.

CONSTITUTIONAL REQUIREMENTS

Of the four cases relied on in Walsh, the statutory scheme most closely resembling our Attachment Statute was the Louisiana ex parte procedure upheld by the Supreme Court which allowed a lienholder to have disputed goods sequestered without prior notice and hearing. Mitchell v. W.T. Grant Co., 416 U.S. 600, 40 L. Ed. 2d 406, 94 S. Ct. 1895. Mitchell followed by two years the Supreme Court decision finding a due process violation in Florida replevin provisions which permitted vendors to have goods seized simply by an ex parte application to a court clerk and the posting of a bond without notice and hearing. Fuentes v. Shevin, 407 U.S. at 80. The Court found sufficient differences in the factual and legal backgrounds between Mitchell and Fuentes to be able to uphold the *252 Louisiana sequestration statute. As noted in Connecticut v. Doehr, 501 U.S. 1, 115 L. Ed. 2d 1, 111 S. Ct. 2105 (1991), these differences included

Louisiana's provision of an immediate postdeprivation hearing along with the option of damages; the requirement that a judge rather than a clerk determine that there is a clear showing of entitlement to the writ; the necessity for a detailed affidavit; and an emphasis on the lienholder's interest in preventing waste or alienation of the encumbered property.

Id. at 10 (citing Mitchell, 416 U.S. at 615-18). Even though the writ could be obtained by ex parte application with no advance notice or opportunity to be heard given to the debtor, these differences, plus the plaintiff's vendor's lien in the property and the uncomplicated nature of the issues at stake, which were susceptible of documentary proof, served to "minimize the risk that the writ [would] be wrongfully issued by a judge." Mitchell, 416 U.S. at 609-610.

In addition to Fuentes, the Supreme Court found due process violations in the two other decisions relied on in Walsh. I.e., North Georgia Finishing, Inc. v. Di-Chem, Inc., 419 U.S. 601, 42 L. Ed. 2d 751, 95 S. Ct. 719 (ex parte garnishment remedy failed to require prior notice and hearing, posting of a bond, detailed affidavit stating the claim, neutral judicial officer, or prompt postdeprivation hearing); Sniadach v. Family Finance Corp., 395 U.S. 337, 342, 23 L. Ed. 2d 349, 89 S. Ct. 1820 (prejudgment garnishment of wages violated due process without requiring prior notice and hearing).

Then, in 1991, some three years after this Court's decision in Walsh, the Supreme Court provided guidance for determining whether a prejudgment attachment scheme meets the minimum requirements of Due Process in Connecticut v. Doehr. 6 The Court *253

Free access — add to your briefcase to read the full text and ask questions with AI

Related

People v. Simmonds
48 V.I. 320 (Superior Court of The Virgin Islands, 2007)
People v. Brathwaite
48 V.I. 207 (Superior Court of The Virgin Islands, 2007)
Government of the Virgin Islands
47 V.I. 178 (Superior Court of The Virgin Islands, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
8 F. Supp. 2d 483, 39 V.I. 249, 1998 WL 318218, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crown-builders-inc-v-stowe-engineering-corp-vid-1998.