Crowder v. Aurora Co-Operative Elevator Co.

393 N.W.2d 250, 223 Neb. 704, 2 U.C.C. Rep. Serv. 2d (West) 1292, 59 A.L.R. 4th 949, 1986 Neb. LEXIS 1050
CourtNebraska Supreme Court
DecidedSeptember 5, 1986
Docket85-307
StatusPublished
Cited by47 cases

This text of 393 N.W.2d 250 (Crowder v. Aurora Co-Operative Elevator Co.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crowder v. Aurora Co-Operative Elevator Co., 393 N.W.2d 250, 223 Neb. 704, 2 U.C.C. Rep. Serv. 2d (West) 1292, 59 A.L.R. 4th 949, 1986 Neb. LEXIS 1050 (Neb. 1986).

Opinion

Shanahan, J.

James E. Crowder sued Aurora Co-operative Elevator Company for breach of a written contract for sale of Crowder’s corn, and for damages. From a judgment for $6,833 Co-op appeals and Crowder cross-appeals. We reverse and remand for a new trial.

We review the pleadings, before our examination of the facts. In his petition Crowder alleged four causes of action concerning his written contract for sale of 26,000 bushels of corn to Co-op. As alleged in his first cause of action, Crowder delivered 9,729 bushels of the contracted corn before Co-op repudiated the contract. When Co-op deducted $6,833 as the cost of its “buy-in” to cover the 16,271 bushels not delivered, Crowder brought the action to recover the $6,833 deducted from proceeds for the 9,729 bushels. Crowder’s three remaining *706 causes of action sought a judgment for Co-op’s other deductions from sale proceeds — damaged corn as nonconforming goods and incidental damages (storage costs). See Neb. U.C.C. § 2-710 (Reissue 1980). In its answer Co-op admitted the contract with Crowder but, as a defense, asserted Crowder’s breach of the contract in failing to deliver 16,271 bushels of corn as contracted. Also, Co-op sought a setoff of $6,833 as the cost of the “buy-in” or “cover” regarding Co-op’s purchase of 16,271 bushels of corn substituted for that not delivered by Crowder. See Neb. U.C.C. § 2-712 (Reissue 1980).

On February 24, 1983, Crowder and Co-op signed their “Future Delivery Grain Purchase Contract,” requiring Crowder to deliver 26,000 bushels of No. 2 yellow corn during September 1983 at the Co-op’s elevator in Murphy or Aurora. The contract specified a price of $2.72 per bushel for the corn delivered to Co-op and granted Co-op an “option to extend delivery date,” without prescribing a procedure for extension of the delivery date. The contracted corn was stored in Crowder’s bins on his farm near Aurora.

According to Crowder’s evidence, in August 1983 Crowder “inquired” whether he could deliver contracted corn to the co-op. Crowder telephoned the co-op daily to ascertain whether corn deliveries were being accepted. As explained by Crowder: “I didn’t want to load the truck up and haul it up there and haul it home.” Also, in early September Crowder, on half a dozen occasions, “dropped by and saw someone” concerning corn deliveries at Co-op’s Aurora elevator. On September 14 Co-op told Crowder to begin delivering corn on September 15. To deliver his corn to Co-op, Crowder used two trucks — one with an approximate capacity of 400 bushels, the other with an estimated capacity of 325 bushels. Crowder delivered 9,729 bushels of corn to the Aurora elevator between September 15 and 27. During that span, Co-op periodically “shut off” deliveries, limiting the amount of corn Crowder could deliver. On September 27, when Crowder brought a truckload of corn to the elevator, the co-op informed Crowder: “[Co-op was not] going to be able to take any more corn after that one load. . . . [They talked like] they was getting ready for the new crop coming in.” Crowder made no delivery of corn after September *707 27 and explained: “[Co-op] refused to take my corn.... [T]hey wouldn’t take it, couldn’t receive it.” After Co-op had refused any further delivery, Crowder sold the balance of the contracted corn — 16,271 bushels — to another elevator at a price of $3.14 per bushel.

Co-op presented countervailing evidence. In August Crowder never inquired about corn delivery and asked about delivery on two occasions in September. The co-op’s manager testified, “[Crowder] stopped by the afternoon of the 14th and he said, T am getting ready to haul corn,’ ” to which the manager responded, “Fine.” The frequency of Crowder’s deliveries to Co-op decreased when an auger broke and delayed loading corn at Crowder’s farm. Crowder delivered “damaged” corn to Co-op, which never turned away a full truck of corn, even if the elevator was filled to capacity.

On November 10 Crowder requested payment for the 9,729 bushels delivered to Co-op in September. On November 11 Co-op informed Crowder that his delivery date had been extended to November 30 and that, on his failure to deliver, the co-op would purchase other corn to fill the contract, with “buy-in” costs charged to Crowder. The contract provided for a buy-in on 10 days’ notice to Crowder. Between November 17 and 23, Crowder delivered corn to a Cargill elevator. On November 30, when Crowder did not deliver the remainder of the corn specified in the February 24 contract, Co-op purchased 16,271 bushels at $3.14 per bushel. The $0.42 per bushel difference between the contracted price and the buy-in price resulted in a “cover” cost of $6,833, which Co-op deducted from the proceeds payable to Crowder for his 9,729 bushels delivered in September. See § 2-712 (“cover”; buyer’s procurement of substitute goods).

Over Crowder’s objection, the court admitted into evidence three Co-op exhibits.

The first exhibit was a November 10 handwritten “interoffice memo” from Don Comer, Co-op’s manager, to Co-op’s general manager. The contents of the memorandum, handwritten on stationery supplied by “Stine Seed Farm, Inc., ” included:

Jim Crowder in office today 10th of Nov 83.

*708 1. Said he will not deliver balance of his contract.
2. Harvested his 83 crop and took it to another elevator.
3. He did not try to deliver any corn prior to 15th of Sept. “Tried to let him haul even when others were shut off” he was broke down from 16th till 21st then hauled from 21st to 26th then did not try to haul again.

Although Comer verified that he had written the memo “shortly after” Crowder came to the elevator on November 10, there was no evidence that the memorandum was a document regularly prepared and kept in the course of Co-op’s day-to-day business involving sales of corn. Apart from Comer, no Co-op personnel testified regarding the preparation or maintenance of any memorandum similar to that written by Comer, as a part of Co-op’s records. Crowder objected that Comer’s November 10 memorandum did not qualify as a business record.

The second Co-op exhibit was a written summary of scale tickets for each corn delivery at the elevator during September, October, and November 1983. Co-op’s three-page summary was set out in columnar form, showing the date, total bushels of corn received daily at the co-op, the time of day of each receipt, and the price for corn on the day of receipt. Comer testified the document was prepared in his office, under his supervision, and reflected “thousands” of scale tickets for corn delivered to the co-op. The co-op received 543,000 bushels of corn in September, 559,000 in October, and 19,000 during the first 10 days of November.

Co-op’s third exhibit was a written summary of 61 contracts between 44 farmers and the co-op for delivery of corn during August and September 1983. The two-page summary, also in columnar form, showed the name of each farmer-seller who had contracted to deliver corn to the co-op, the total bushels under each contract, the number of bushels delivered, and the quantity of any undelivered corn under each contract. Comer testified that the summary-exhibit, prepared under his supervision, was based on original contracts and settlement sheets in Co-op’s possession.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

132 Ventures v. Active Spine Physical Therapy
318 Neb. 64 (Nebraska Supreme Court, 2024)
BCL Properties v. Boyle
992 N.W.2d 440 (Nebraska Supreme Court, 2023)
State v. Figures
308 Neb. 801 (Nebraska Supreme Court, 2021)
Blue Creek Farm, Inc. v. Aurora Cooperative Elevator Co.
614 N.W.2d 310 (Nebraska Supreme Court, 2000)
McFadden v. Winters and Merchant, Inc.
603 N.W.2d 31 (Nebraska Court of Appeals, 1999)
Baker v. Dec International
580 N.W.2d 894 (Michigan Supreme Court, 1998)
State v. Engleman
560 N.W.2d 851 (Nebraska Court of Appeals, 1997)
Kusek v. Burlington Northern Railroad
552 N.W.2d 778 (Nebraska Court of Appeals, 1996)
Misle v. Misle
529 N.W.2d 54 (Nebraska Supreme Court, 1995)
Trinidad Bean and Elevator Co. v. Frosh
494 N.W.2d 347 (Nebraska Court of Appeals, 1992)
Hunt v. Methodist Hospital
485 N.W.2d 737 (Nebraska Supreme Court, 1992)
State v. Wright
436 N.W.2d 205 (Nebraska Supreme Court, 1989)
Hansen v. Lien Termite & Pest Control Co.
428 N.W.2d 195 (Nebraska Supreme Court, 1988)
State v. Oliva
422 N.W.2d 53 (Nebraska Supreme Court, 1988)
Ford v. First Municipal Leasing Corporation
838 F.2d 994 (First Circuit, 1988)
Ford v. First Municipal Leasing Corp.
838 F.2d 994 (Eighth Circuit, 1988)
State v. Wilson
406 N.W.2d 123 (Nebraska Supreme Court, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
393 N.W.2d 250, 223 Neb. 704, 2 U.C.C. Rep. Serv. 2d (West) 1292, 59 A.L.R. 4th 949, 1986 Neb. LEXIS 1050, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crowder-v-aurora-co-operative-elevator-co-neb-1986.