Crowder Construction v. Dwight Holland

CourtCourt of Appeals of Tennessee
DecidedJuly 10, 2003
DocketM2002-01840-COA-R3-CV
StatusPublished

This text of Crowder Construction v. Dwight Holland (Crowder Construction v. Dwight Holland) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crowder Construction v. Dwight Holland, (Tenn. Ct. App. 2003).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE July 10, 2003 Session

CROWDER CONSTRUCTION GROUP, LLC v. DWIGHT HOLLAND, ET AL.

Direct Appeal from the Chancery Court for Davidson County No. 00-172-1 Irvin H. Kilcrease, Jr., Chancellor

No. M2002-01840-COA-R3-CV - Filed September 18, 2003

The trial court determined that a construction contract between the parties had been modified orally and awarded judgment to plaintiff contractor. We affirm in part and remand.

Tenn. R. App. P. 3 Appal as of Right; Judgment of the Chancery Court Affirmed in part; and Remanded

DAVID R. FARMER , J., delivered the opinion of the court, in which HOLLY M. KIRBY, J. and WILLIAM H. INMAN , SP . J., joined.

Alan Mark Turk, Brentwood, Tennessee, for the appellants, Dwight Holland and Betty Klein Holland.

Gary S. Rubenstein, Nashville, Tennessee, for the appellee, Crowder Construction Group, LLC.

MEMORANDUM OPINION1

This dispute arises from a mechanics’ and materialmens’ lien filed by Crowder Construction Group, LLC (“Crowder”) to recover amounts due for the construction of a sewer line in a subdivision owned by the appellants (collectively, “Holland”). In October 1998, Crowder submitted a written base bid of $69,000 for construction of a sanitary sewer line in a subdivision owned by Holland on New Hope Road in Nashville. The bid was based on plans and specs provided by engineering associates employed by Holland. It included necessary clearing, driveway repair, road patching, 12-

1 Rule 10 o f the Rules of the C ourt of App eals of T ennessee provid es:

This Court, with the concurrence of all judges participating in the case, may affirm, reverse o r modify the actions of the trial court by memorandum opinion when a formal opinion would have no precedential value. When a case is decided by memorandum opinion it shall be designated "MEMORANDUM OPIN ION", shall not be published, and shall not be cited or relied on for any reaso n in any un related case. inch stone at the sewer, and backfill with excavated material. The plans required a number of easements over neighboring properties through which the sewer line was to pass. Holland submits he told Crowder that he needed to keep the costs of the project as low as possible.

The parties do not dispute that several revisions were made to the project, two of which were made in October 1998 and December 1999 and presented to Crowder at a preconstruction meeting in April 1999. At the April meeting, Holland informed Crowder that he had not yet secured the necessary easements, but that they had been promised. The parties began work on the project prior to securing the easements. Holland submits that blasting by Crowder caused rock and debris to be displaced onto a neighbor’s property, resulting in loss of that easement. Holland therefore purchased the property. The plans were further revised when Crowder discovered a kicker in a water line, causing a work stoppage from June 2-23, during which rented equipment remained on the job-site.

In August 1999, Crowder submitted an invoice for $42,000 in equipment rental and for its own services of $150,000 or $160,000. Crowder demanded immediate payment of $100,000. Crowder accepted $15,000 and the parties agreed to resolve the dispute. Crowder left the job site and on August 30, Holland demanded by letter that Crowder complete work. Crowder failed to resume and Holland hired Southwork Engineering to finish the project. Holland contends he incurred additional expenses of $22,106.

In January 2000, Crowder filed a complaint in the Chancery Court for Davidson County, seeking enforcement of a mechanics’ and materialmens’ lien against Holland’s property. 2 Crowder sought judgment of $146,983.45, plus interest, attachment of the property to secure payment, sale of the property to satisfy the debt, and costs. Holland counter-claimed, seeking damages for breach of contract and tort. The trial court determined the agreement orally had been modified to a cost plus fifteen percent contract, adopted findings and facts and conclusions of law submitted by Crowder, dismissed Holland’s counter-complaint, and entered judgment for Crowder in the amount of $138,433.45. The trial court taxed costs to Holland and ordered the property subject to lien sold, if necessary, to satisfy judgment. Holland appeals the judgment.

Issues Presented

The issues presented for our review, as we re-state them are:

(1) Whether the trial court erred by finding the contract had been modified to a cost plus fifteen percent basis.

(2) Whether the court erred in determining the amount of damages.

2 Crowder also named Clyde Paul Ho lland, Trustee, and Neff Rental, Inc., as defendants. Th e trial court dismissed N eff Rental and Mr. Ho lland p rior to trial.

-2- (3) Whether the court erred by dismissing with prejudice Holland’s counter- claim.

Standard of Review

Holland argues that because the trial court adopted Crowder’s findings of fact, the presumption of correctness for findings of fact of the trial court is inapplicable. We disagree. Although we do not encourage this procedure, it does not negate the presumption of correctness prescribed by Tenn. R. App. P. 13(d) where there is no showing that the party-prepared findings are not in accordance with the trial court’s own views. Airline Const. Inc. v. Barr, 807 S.W.2d 247, 254 (Tenn. Ct. App. 1990). Additionally, if Holland was dissatisfied with these findings, Holland could have moved the court to amend its findings or make additional findings pursuant to Tenn. R. Civ. P. 52.02. See id. Holland made no such motion and there is no justification here for disregarding the presumption of correctness. See id.

Contract Modification

The general contract to which Holland refers is a brief, one-page base bid of $69,860 for construction of a sewer based on plans provided by Holland. The parties do not dispute that the plans were altered a number of times, or that they agreed Crowder would perform additional work. The issue raised by Holland, as we perceive it, is not whether the contract had been modified, but the nature of the modification.

The trial court determined that the agreement had been modified orally to a cost plus fifteen percent basis. This finding is based on the testimony of John Crowder (Mr. Crowder), the majority owner of Crowder Construction, LLC. Mr. Crowder testified that on June 3, 1999, he and Dwight Holland (Mr. Holland) agreed that the on-going sewer project and additional work being performed at Mr. Holland’s home, lot 37, would continue at a cost plus fifteen percent basis. Mr. Crowder testified, “I did discuss with him that it would be better to keep up and for us to bill him. It would be less expensive for him for us to bill him the invoice amounts plus the fifteen percent. We had so many things going on. We had numerous changes and it was hard to delineate which costs were going to what job function.” When asked whether the “job functions” were the sewer project and work at lot 37, Mr. Crowder stated, “Right.” He further testified that the most effective use of the equipment sometimes meant combining uses for both jobs, and that, essentially, the two projects were treated as one.

Mr. Holland denies the contract was converted to a cost-plus basis. He testified at trial, “No. I would never have done that. I never have and I couldn’t vision [sic] a cost-plus basis because I was very skeptical, didn’t understand sewer anyway.” Mr. Holland also submits that the invoices sent by Crowder support his position because, with one exception, they do not reflect a cost plus agreement.

-3- Upon review of the record, we find the documentary evidence ambiguous.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Airline Construction, Inc. v. Barr
807 S.W.2d 247 (Court of Appeals of Tennessee, 1990)
Beaty v. McGraw
15 S.W.3d 819 (Court of Appeals of Tennessee, 1998)
Wells v. Tennessee Board of Regents
9 S.W.3d 779 (Tennessee Supreme Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
Crowder Construction v. Dwight Holland, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crowder-construction-v-dwight-holland-tennctapp-2003.