Crosswell v. Arten Construction Co.

262 S.E.2d 522, 152 Ga. App. 162, 1979 Ga. App. LEXIS 2851
CourtCourt of Appeals of Georgia
DecidedOctober 31, 1979
Docket58732
StatusPublished
Cited by12 cases

This text of 262 S.E.2d 522 (Crosswell v. Arten Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crosswell v. Arten Construction Co., 262 S.E.2d 522, 152 Ga. App. 162, 1979 Ga. App. LEXIS 2851 (Ga. Ct. App. 1979).

Opinion

McMurray, Presiding Judge.

This is an action for a breach of a construction contract predicated upon a June 26, 1976, agreement whereby Arten Construction Company agreed to construct a building for Crosswell (Brandon Hall faculty residence building). The contract made time of the essence and provided that the project be commenced on or before August 15, 1976, and be completed 100 days after commencement. However, Crosswell instructed Arten not to begin construction and considerable delay ensued. When Crosswell became ready to commence the project, Arten declined to construct the building at the original contract price due to cost increases.

Crosswell eventually contracted with another construction company for the erection of the building, whereupon Arten Construction Company brought this lawsuit.

The complaint alleges damages of $19,643.50 with interest and costs. A trial was held and the jury returned a verdict in this amount. The judgment followed the verdict. Defendant appeals. Held :

1. The first enumeration of error is concerned with the denial of a motion to require the plaintiff to produce documents. Prior to trial defendant had served on the plaintiff notice for production and permission to inspect and copy the plaintiff’s federal income tax returns and profit and loss statements for the years 1974, 1975, and 1976. The plaintiff objected to this request, and defendant’s motion that the trial court require plaintiff to produce and allow defendant to inspect and copy these documents was denied. Defendant then served on plaintiff *163 a motion to produce these documents at trial. At trial, plaintiff again opposed allowing defendant access to these documents. After an in camera inspection of these documents the trial court determined there might be information in these documents which would be relevant and material to this case. The court allowed defendant’s counsel to examine these documents for 15 minutes prior to trial.

This action was instituted to recover damages allegedly sustained by virtue of the breach of the construction contract. The measure of damages for such breach is usually the contract price less what it would have cost the contractor to perform, that is, the profits. See Code §§ 20-1406, 20-1407, 20-1414; Murphey v. Northeastern Const. Co., 31 Ga. App. 715 (121 SE 848); Campbell & Co. v. Mion Brothers, 6 Ga. App. 134 (3) (64 SE 571); Murray v. Americare-Medical Designs, Inc., 123 Ga. App. 557, 559 (3) (181 SE2d 871). Under the circumstances it is not very clear as to how the plaintiffs federal income tax returns and profit and loss statements would be admissible in evidence in this case. It could be, however, that for the purposes of discovery with reference to mitigation of the damages that the defendant might have been able to investigate and determine that the plaintiff suffered no loss by reason of the failure to perform this construction contract. It therefore would have been discretionary with the court to allow the production of these documents for discovery purposes. At trial when the defendant again requested under a notice to produce to examine these documents he was given approximately 15 minutes to do so. Thereafter counsel did not request and made no motion to continue or postpone the case in order to investigate further anything counsel found in the documents which would assist defendant in the preparation of the case. Without conceding, however, that the trial court erred in denying defendant’s motion to require plaintiff to produce the documents for inspection, we believe that if there were error it was indeed harmless for defendant was later given the opportunity to inspect the profit and loss statements for the fiscal years ending August 31, 1974, and August 31, 1975, and to introduce them into evidence. Had the defendant needed further *164 discovery, the proper action on his part would have been a motion to postpone or to continue. Consequently, we find no merit in this complaint.

2. The next enumeration of error was to the allowance in evidence of a business document of the plaintiff with reference to a written estimate of the cost of construction by which the plaintiff determined the contract sum to be $103,939. The witness who identified this document was the company president who had previously testified to the increased cost which would have resulted in the delay of performance of the contract when plaintiff was not allowed to proceed in constructing it. He then testified as to how the job estimate was prepared from a quantity survey of all materials and labor and subcontract items, a normal procedure in the construction industry and such estimates are prepared as a basis for bidding or quoting prices for doing jobs. During the examination of this witness as to the cost involved in the job he was not allowed to refresh and assist his memory by the use of the document upon objection of counsel for the defendant that the document speaks for itself and the witness should not be allowed to testify as to what is in the document. It is generally held that a memorandum has no present evidentiary value since it is not the memorandum that is the evidence but the recollection of the witness. Stansall v. Columbian Nat. Life Ins. Co., 32 Ga. App. 87, 91-92 (122 SE 733); State Hwy. Dept. v. Godfrey, 118 Ga. App. 560, 561 (1) (164 SE2d 340).

But, on cross examination this witness testified that the contract price (as prepared from the estimate) was $103,939, the cost of which would be $84,767, leaving "a locked-in profit of . . . $19,173.” Thereafter when the estimate was offered in evidence as an instrument prepared in the regular course of business as a normal and customary record in the construction industry to prepare such estimates of jobs it was allowed in evidence under the Business Records Rule over the objection that it had no probative value, was highly prejudicial, and contained hearsay. Any writing or record made as a memorandum or record of any act, transaction, occurrence, or event shall be admissible in evidence as proof of said act, transaction, *165 occurrence, or event if the trial judge shall find that it was made in the regular course of any business and that it was the regular course of such business to make such memorandum or record at the time of such act, transaction, occurrence, or event or within any reasonable time thereafter. Code Ann. § 38-711 (Ga. L. 1952, p. 177). Consequently, there was evidence before the court that such estimates are indeed business records of building contractors. However, in such cases as Knudsen v. Duffee-Freeman, Inc., 95 Ga. App. 872, 877-880 (99 SE2d 370); Yarbrough v. Cantex Mfg. Co., 97 Ga. App. 438, 441 (2) (103 SE2d 138); Camp v. Camp, 213 Ga. 65 (97 SE2d 125); and Martin v. Baldwin, 215 Ga. 293 (2), 297-300 (110 SE2d 344), opinions of medical experts (whose qualifications are not first proved) are not allowed as a part of business records.

The common knowledge of the writer is that in such estimates percentages for overbid, labor increases, other imponderables, and profit are indeed items which the estimators and contractors add to such estimates which involve expert opinion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Excavation +, Inc. v. Candler
433 S.E.2d 340 (Court of Appeals of Georgia, 1993)
Armstrong v. Vallion
370 S.E.2d 215 (Court of Appeals of Georgia, 1988)
Spicewood, Inc. v. Dykes Paving & Construction Co.
364 S.E.2d 298 (Court of Appeals of Georgia, 1987)
Franklin v. Demico, Inc.
347 S.E.2d 718 (Court of Appeals of Georgia, 1986)
Atlanta Foot & Leg Clinics, P.A. v. Patton
335 S.E.2d 141 (Court of Appeals of Georgia, 1985)
Thico Plan, Inc. v. Ashkouti
320 S.E.2d 604 (Court of Appeals of Georgia, 1984)
Department of Transportation v. Lowery
291 S.E.2d 573 (Court of Appeals of Georgia, 1982)
Raybestos-Manhattan, Inc. v. Friedman
275 S.E.2d 817 (Court of Appeals of Georgia, 1981)
Williams v. State
267 S.E.2d 305 (Court of Appeals of Georgia, 1980)
Atlanta Recycled Fiber Co. v. Tri-Cities Steel Co.
262 S.E.2d 554 (Court of Appeals of Georgia, 1979)

Cite This Page — Counsel Stack

Bluebook (online)
262 S.E.2d 522, 152 Ga. App. 162, 1979 Ga. App. LEXIS 2851, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crosswell-v-arten-construction-co-gactapp-1979.