Cross Timbers Oil Co. v. Exxon Corp.

22 S.W.3d 24, 2000 WL 332951
CourtCourt of Appeals of Texas
DecidedMay 1, 2000
Docket07-99-0138-CV
StatusPublished
Cited by142 cases

This text of 22 S.W.3d 24 (Cross Timbers Oil Co. v. Exxon Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cross Timbers Oil Co. v. Exxon Corp., 22 S.W.3d 24, 2000 WL 332951 (Tex. Ct. App. 2000).

Opinion

BRIAN QUINN, Justice.

Cross Timbers Oil Company (Cross Timbers) appeals from a final summary judgment entered in favor of Exxon Corporation, d/b/a Exxon Company, U.S.A. (Exxon). Through that judgment, the trial court purportedly denied Cross Timbers all relief against Exxon. 1 On appeal, Cross Timbers asserts five issues which effectively attack the trial court’s decision to grant Exxon’s motion for summary judgment while denying its own. We affirm.

Background

Both Cross Timbers and Exxon were successors in interest to two agreements involving the production of oil and gas. The first consisted of an accord unitizing various oil and gas interests in the San Andreas pay zone in Yoakum County (the Unit Agreement) while the second concerned the operation of the unitized interests (Operating Agreement). The two were executed in February of 1965. As previously mentioned, neither Cross Timbers nor Exxon were original parties to the agreements. Both eventually came to own a working interest and, thereafter, Exxon also assumed the role of operator *26 under the Operating Agreement. Moreover, the dispute before us arose from Exxon’s position as operator.

In late 1997, Cross Timbers sought to replace Exxon as the operator. It did so by invoking various sections of the Operating Agreement. The sections allegedly vested the working interest owners with authority to exercise “overall control and supervision of all matters pertaining to Unit operations” and to so supervise the operations through the vote of the working interest owners. 2 So, pursuant to those sections, Cross Timbers informed the working interest owners of its intent, solicited the approval of the requisite number of working interest owners and garnered sufficient vote. When Exxon was informed of this and told to relinquish its post, it refused to step down. Subsequently, Cross Timbers sued Exxon for breach of contract, contending that the latter violated the agreement by failing to capitulate. Both parties moved for summary judgment. The trial court granted that of Exxon but did not specify the particular ground upon which it relied.

Standard of Review

The standard of review applicable when considering orders granting summary judgment is well known and need not be repeated. We find it sufficient to simply refer the litigants to Science Spectrum, Inc. v. Martinez, 941 S.W.2d 910 (Tex.1997) and Nixon v. Mr. Property Management Co. Inc., 690 S.W.2d 546 (Tex.1985).

Next, resolution of this dispute entails interpretation of the contracts involved. In doing so, we again apply various settled rules of law. The first mandates that construing an unambiguous contract involves a question of law. Borders v. KRLB, Inc., 727 S.W.2d 357, 359 (Tex.App.—Amarillo 1987, writ refd n.r.e.). Thus, we need not defer to any interpretation afforded by the trial court. Second, when interpreting an instrument, we strive to give effect to its parties’ intent. Id. Furthermore, that intent is garnered from the language of the contract, which language is considered in its entirety. Id. That is, we peruse the complete document to understand, harmonize, and effectuate all its provisions. Questa Energy Corp. v. Vantage Point Energy, Inc., 887 S.W.2d 217, 221 (Tex.App.—Amarillo 1994, writ denied). So too must we afford the words contained in the agreement their plain, ordinary, and generally accepted meaning, unless the instrument requires otherwise. Sun Operating, Ltd. v. Holt, 984 S.W.2d 277, 285 (Tex.App.—Amarillo 1998, pet. denied); Phillips Petroleum Co. v. Gillman, 593 S.W.2d 152, 154 (Tex.Civ.App.—Amarillo 1980, writ refd. n.r.e.).

Finally, in applying the foregoing rules we may not rewrite the agreement to mean something it did not. Borders v. KRLB, Inc., 727 S.W.2d at 359. Simply put, we cannot change the contract merely because we or one of the parties comes to dislike its provisions or thinks that something else is needed in it. HECI Explor. Co. v. Neel, 982 S.W.2d 881, 888-89 (Tex.1998). This is so because parties to the contract are considered masters of their own choices. They are entitled to select what terms and provisions to include in a contract before executing it. And, in so choosing, each is entitled to rely upon the words selected to demarcate their respective obligations and rights. In short, the parties strike the deal they choose to strike and, thus, voluntarily bind themselves in the manner they choose. And, that is why parties are bound by their agreement as written. Emmer v. Phillips Petroleum Co., 668 S.W.2d 487, 490 (Tex.App.—Amarillo 1984, no writ). For a court to change the parties’ agreement merely because the Court did not like the *27 agreement, or because one of the parties subsequently found it distasteful, would be to undermine not only the sanctity afforded the contract but also the expectations of those who created and relied upon it.

With the foregoing said, we now turn to the first and second issues raised by Cross Timbers.

Points One and Two

Through points one and two, Cross Timbers asserts that the trial court erred in granting its opponent a summary judgment. This is so because specific provisions of the Operating Agreement and the Unit Agreement allegedly permitted the working interest owners to remove Exxon by the vote of the working interest owners. 3 We disagree and overrule the two points. The sections of the two agreements which purportedly create the right in dispute follow. The first, found in the Operating Agreement, states:

3.1 Overall Supervision. Working Interest Owners shall exercise overall supervision and control of all matters pertaining to Unit Operations pursuant to this agreement and the Unit Agreement....

The second, found in the Unit Agreement, reads:

4.3 Change of Operating Methods. Nothing herein shall prevent Working Interest Owners from discontinuing or changing in whole or in part any method of operation which, in their opinion, is no longer in accord with good engineering or production practices.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ETC Texas Pipeline, Ltd. v. XTO Energy Inc.
Court of Appeals of Texas, 2024
Michael Damien Dunn v. Pamela Sue Dunn
Court of Appeals of Texas, 2023
Commissioner of the General Land Office v. Sandridge Energy, Inc.
454 S.W.3d 603 (Court of Appeals of Texas, 2014)
FPL Energy, LLC v. TXU Portfolio Management Co.
426 S.W.3d 59 (Texas Supreme Court, 2014)
in Re W.L.W.
370 S.W.3d 799 (Court of Appeals of Texas, 2012)
In Re Gdh
366 S.W.3d 766 (Court of Appeals of Texas, 2012)
in the Interest of G.D.H., a Child
366 S.W.3d 766 (Court of Appeals of Texas, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
22 S.W.3d 24, 2000 WL 332951, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cross-timbers-oil-co-v-exxon-corp-texapp-2000.