Criswell v. Seaman Body Corp.

290 N.W. 177, 233 Wis. 606, 1940 Wisc. LEXIS 49
CourtWisconsin Supreme Court
DecidedJanuary 17, 1940
StatusPublished
Cited by27 cases

This text of 290 N.W. 177 (Criswell v. Seaman Body Corp.) is published on Counsel Stack Legal Research, covering Wisconsin Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Criswell v. Seaman Body Corp., 290 N.W. 177, 233 Wis. 606, 1940 Wisc. LEXIS 49 (Wis. 1940).

Opinion

Fritz, J.

The plaintiff, Criswell, sued the defendant and appellant, Seaman, and the Electric Company to recover damages for injuries sustained by him upon receiving an electric shock on September 28, 1936, while working as one of a *611 crew employed by Worden in erecting structural steel as a subcontractor under Permanent, which as the general contractor was constructing a crane-runway building for Seaman on premises owned and used by it as a manufacturing plant in which it employed many men. Criswell received the shock when a metal cable, which extended from the boom of a derrick used by Worden’s crew in erecting an iron column for the building either came in coiltact with one of the uninsulated wires of a power line, or an arc formed between the wire and the cable as Criswell’s hand touched the column while he stood on the ground performing his duties in connection with erecting the column on a concrete footing constructed theretofore by Permanent. Plaintiff’s action is predicated upon alleged violations of the safe-place statute and negligence on the part of Seaman and the Electric Company in the installation and maintenance of the wires upon Seaman’s premises. Upon the trial the court directed a verdict in favor of the Electric Company, and submitted questions to the jury for a special verdict in relation to alleged causal violations by Seaman of the safe-place statute, contributory negligence on the part of Criswell, comparative negligence, and the-assessment of Criswell’s damages for loss of earnings and pain and suffering.

The jury found that Seaman failed to maintain the place where Worden’s employees were erecting the column as free from danger to the life and safety of the employees as the nature of their employment and their place of employment would reasonably permit; that Seaman by the exercise of reasonable diligence ought to have known before the accident and in time to take adequate steps to prevent the same that the equipment used by Worden might probably be used by its employees in erecting that column, and used by them in such a manner as to make it likely that some part of the equipment would come in contact with or dangerously close to the electric-power wires; that Seaman failed prior to the accident to adopt and use methods or measures reasonably *612 adequate to render the place where Worden’s employees were engaging in erecting the column as free from danger as the nature of their employment and place of employment would reasonably permit, and such failure was an efficient cause of plaintiff’s injury; that plaintiff was not negligent in directing .the boom operator as to the movement of the boom, or in coming in contact with the column at a time when the cable holding the column came dangerously close to the electric wiring; and that his damages were $2,250 for loss of earnings and $2,200 for pain and suffering. In passing upon the motions after verdict, the court approved these findings. They are challenged on Seaman’s appeal, particularly in so far as the jury found that there was no' contributory negligence on Criswell’s part and that his damages amounted to $2,250 for loss of earnings and $2,200 for pain and suffering. However, upon reviewing the record we find that the evidence warranted the court’s approval of the jury’s findings. The material facts in support thereof and which the evidence fairly admits finding will be hereinafter stated in so far as necessary to pass upon Seaman’s other contentions on this appeal.

Seaman’s principal contention is that it is not liable under the safe-place statute because (a) it did not own, maintain, or have any right of control over the electric-power line and had called in and consulted representatives of the Electric Company, which was the owner thereof and the only party in the vicinity equipped or competent to take care of high-tension lines; (b) Seaman was not engaged in or equipped for the construction trade, and therefore let to Permanent, a general construction contractor, the contract for the construction of the addition to its factory; (c) and Seaman did not own, control, or select the equipment used by Permanent or its subcontractor Worden, and it had no right of control over the operations of either of them or of the details of the work, excepting to have the completed build *613 ing delivered in accordance with the plans and specifications, and have Tinker, who was its only representative, check to see whether the building was erected in accordance therewith. In passing upon the contention which is based on these grounds, there must be taken into consideration the following additional facts, which can reasonably be deemed established by the evidence.

At Seaman’s request the new building was designed for it by Permanent, which -was awarded the general contract for the construction thereof on Seaman’s land on which it had its manufacturing plant, and with its knowledge, Permanent sublet to Worden the erection of the structural steel. At the crest of the roof of the new building it was to be approximately forty-two and one-half feet above the ground, and the construction of the steel frame thereof required the erection by Worden, along the lines of its north and south walls, of two parallel rows, fifty-five feet apart, of seven iron columns twenty-eight and one-half feet long, the base of which had to be placed at the ground level upon concrete footings theretofore installed by Permanent. On the top of the columns Worden had to install triangular iron roof trusses with the apex thereof forty-two and one-half feet above the ground level, and also install iron crossbeams, braces, etc., between each pair of trusses. Consequently, in order to hoist the structural steel and have the clearance necessary for moving it into place at the highest points, Worden had to use hoisting apparatus of sufficient size to- allow the necessary clearance over the apex of an installed truss. For that purpose Worden provided and its crew used, in erecting the structural steel on several days prior to the accident in question, a derrick with a forty-feet boom, the base of which was on a truck at a height of five and one-half feet above the normal pavement.

The south wall of the new building was to be on a line on which there was a wooden pole carrying the power line *614 erected by the Electric Company on Seaman’s land pursuant to a contract between them for the furnishing of electric current to- Seaman. It had in its employment one Tinker, as its plant-maintenance engineer to look after the physical condition of its premises, and under his jurisdiction it employed Frank J. Effland, as its director of maintenance and purchases, and Wm. W. Janzer, as its safety director. Before the construction of the south wall was commenced, Effland, as 'Seaman’s representative, notified the Electric Company of the projected building by speaking to the latter’s sales engineer, Aimer Skretting. He had Peter Urfer, a practicing electrical engineer for the Electric Company, accompany him to the Seaman plant on September 3d, where they conferred with Effland or Tinker. Urfer proposed using a pole forty-five feet long which had to be set into the ground, but Seaman’s representative thought a higher pole should be used. Thereupon Urfer had a fifty-feet pole put in on September 5th, and on September 9th Skretting checked the change to see that it was done satisfactorily.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barry v. Employers Mutual Casualty Co.
2001 WI 101 (Wisconsin Supreme Court, 2001)
Ladwig v. Ermanco Inc.
504 F. Supp. 1229 (E.D. Wisconsin, 1981)
Dykstra v. Arthur G. McKee & Co.
284 N.W.2d 692 (Court of Appeals of Wisconsin, 1979)
Walsh v. Wild Masonry Co., Inc.
241 N.W.2d 416 (Wisconsin Supreme Court, 1976)
Barthel v. Wisconsin Electric Power Co.
230 N.W.2d 863 (Wisconsin Supreme Court, 1975)
Sampson v. Laskin
224 N.W.2d 594 (Wisconsin Supreme Court, 1975)
Knutter v. Bakalarski
191 N.W.2d 235 (Wisconsin Supreme Court, 1971)
Young v. Anaconda American Brass Co.
168 N.W.2d 112 (Wisconsin Supreme Court, 1969)
Carter v. Fraser Construction Co.
219 F. Supp. 650 (W.D. Arkansas, 1963)
Mustas v. INLAND CONSTRUCTION, INC.
19 Wis. 2d 194 (Wisconsin Supreme Court, 1963)
Globig v. Greene & Gust Co.
201 F. Supp. 945 (E.D. Wisconsin, 1962)
Schwenn v. Loraine Hotel Co.
111 N.W.2d 495 (Wisconsin Supreme Court, 1961)
Krause v. Menzner Lumber & Supply Co.
95 N.W.2d 374 (Wisconsin Supreme Court, 1959)
Hrabak v. Madison Gas Electric Company
240 F.2d 472 (Third Circuit, 1957)
Hrabak v. Madison Gas & Electric Co.
240 F.2d 472 (Seventh Circuit, 1957)
Potter v. City of Kenosha
68 N.W.2d 4 (Wisconsin Supreme Court, 1955)
Umnus v. Wisconsin Public Service Corp.
51 N.W.2d 42 (Wisconsin Supreme Court, 1952)
Trimyer v. Norfolk Tallow Co.
66 S.E.2d 441 (Supreme Court of Virginia, 1951)
Pappas v. Evans
48 N.W.2d 298 (Supreme Court of Iowa, 1951)
Saxhaug v. Forsyth Leather Co.
31 N.W.2d 589 (Wisconsin Supreme Court, 1948)

Cite This Page — Counsel Stack

Bluebook (online)
290 N.W. 177, 233 Wis. 606, 1940 Wisc. LEXIS 49, Counsel Stack Legal Research, https://law.counselstack.com/opinion/criswell-v-seaman-body-corp-wis-1940.