Cripe v. Mathis (In Re Mathis)

360 B.R. 662, 2006 Bankr. LEXIS 3346, 2006 WL 3512109
CourtUnited States Bankruptcy Court, C.D. Illinois
DecidedDecember 6, 2006
Docket19-09005
StatusPublished
Cited by16 cases

This text of 360 B.R. 662 (Cripe v. Mathis (In Re Mathis)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, C.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cripe v. Mathis (In Re Mathis), 360 B.R. 662, 2006 Bankr. LEXIS 3346, 2006 WL 3512109 (Ill. 2006).

Opinion

OPINION

MARY P. GORMAN, Bankruptcy Judge.

The issue before the Court is whether a debt arising out of the Debtor’s contract to build a house for the Plaintiffs is nondis-chargeable because of alleged fraud and embezzlement. Although Plaintiffs obtained an $88,000 state court judgment against the Debtor before this case was filed, the Plaintiffs have failed to present proof here that their complaints are anything more than contract disputes which are dischargeable.

The Debtor, Darrel Mathis, has been in the construction business most of his adult life. On June 5, 2002, Mr. Mathis entered into a Construction Contract with the Plaintiffs, Jerry Cripe and Nancy Lewis, wherein he agreed to construct a 2,468 square-foot house in the East Bluff subdivision in Petersburg, Illinois. This was the third new construction home which the Plaintiffs had built for themselves.

The Construction Contract was a “cost plus” contract. The estimated cost of construction was $169,525, but was subject to change based on the actual costs of labor and materials. The contractor’s profit— the “plus” — was set at 10% and estimated to be $16,952, resulting in the total estimated construction cost of $186,477. The Construction Contract provided for the contractor’s profit to be paid $1,695.20 upon signing, with three additional payments of $3,814.20, for a total of $13,137.80. A final payment was to be calculated at 10% of the actual project cost minus the $13,137.80 previously paid.

The Plaintiffs took out a construction loan to build the house. The parties set up a procedure whereby Mr. Mathis would submit draw requests to Mr. Cripe which set forth the names of entities who had provided materials and labor for the pro *665 ject and how much was owed to them. The draw requests also purported to show a running total of amounts paid and amounts still due to complete the project. Funds from the construction loan were disbursed to Mr. Mathis’ business account at Town & Country Bank. Mr. Mathis paid the bills out of this account. Mr. Mathis paid himself by transferring money from the Town & Country account to his personal account at Bank One.

The draw requests were made on a form entitled SWORN STATEMENT FOR CONTRACTOR AND SUBCONTRACTOR TO OWNER. Four written draw requests were made by Mr. Mathis. The first draw is undated and shows that, after various extras and credits, the new estimated total cost of the project was $202,000.73. This first draw request was for $43,107.32, and included a request for $3,814 for Mr. Mathis. Mr. Cripe approved this draw request.

The second draw request is also undated and requested a disbursement of $63,818.99. The second draw request shows proposed payments to Mr. Mathis for the regular $3,814.20 contract profit payment along with $7,650 for framing and $2,000 for additional work on the basement. Mr. Cripe approved the second draw request.

The third draw request is dated November 2, 2002, and requests $50,015.25. It also requested the regular $3,814.20 profit payment for Mr. Mathis. Mr. Mathis admitted that he was aware at the time of the third draw request that the original contract price would not cover the cost of the house. Mr. Cripe testified that, at the time of the third request, Mr. Mathis assured him that the project was on budget and that drywall and electrical work for the basement could be added to the project without going over the original budget. Mr. Mathis denies making that statement and asserts that the parties agreed to add the drywall and electrical work for an additional cost.

The fourth draw request is dated January 16, 2003, and requests $66,674.10. Both parties testified that when they met to discuss draw request number four, they were both aware that the project was over budget and the funds from the original construction loan would be inadequate to pay to complete the home. The fourth request has the total contract and extras at $225,310.86. Mr. Mathis did not sign draw request number four, but Mr. Cripe approved the request and told Mr. Mathis to take it to the title company, which was disbursing the funds, and get whatever funds were left from the original loan. Both parties agree that Mr. Cripe generally told Mr. Mathis to pay bills with the money, but both also agree that no specific bills were discussed.

Mr. Cripe took over the project from Mr. Mathis after this discussion about the fourth draw request. Mr. Cripe was upset that the project was far over budget. He was also unhappy with the workmanship of Mr. Mathis.

At the time of his dismissal in January, 2003, Mr. Mathis obtained the final draw authorized by Mr. Cripe and received about $28,000, which was all that was left of the original construction loan funds. Mr. Mathis held the money in the Town & Country account for awhile because he wanted to make sure that the subcontractors were paid. He knew that contractors who failed to pay subcontractors did not stay in business very long. Once he learned that Mr. Cripe was paying the subcontractors, Mr. Mathis paid himself out of the funds in the account. He withdrew $7,930.05 on March 10, 2003, $2,069.95 on March 22, 2003, and $9,000 on April 18, 2003. Mr. Mathis claims that he was owed more than he was actually paid. *666 Mr. Mathis calculated that he was owed profit of $20,000 based on the $225,000 cost of the house as of January 16, 2003, plus at least $27,000 for work which he did on the home. 1

Mr. Cripe has still not finished the house. He says that he does not have the money needed to finish the project. He does not dispute that $225,000 was put into the house while Mr. Mathis was involved in the construction.

The Plaintiffs subsequently sued Mr. Mathis in state court and obtained a default judgment in the amount of $88,334.53 plus costs. The state court suit was based on breach of contract and consisted mainly of breach of warranty claims. When Mr. Mathis filed his petition in bankruptcy, the Plaintiffs commenced this adversary proceeding to determine the dischargeability of Mr. Mathis’ debt to them.

Count I of the Plaintiffs Amended Complaint is based on 11 U.S.C. § 523(a)(2)(A), which provides as follows:

(a) A discharge under section 727, 1141, 1228(a), 1228(b), or 1328(b) of this title does not discharge an individual debtor from any debt—
(2) for money, property, services, or an extension, renewal, or refinancing of credit, to the extent obtained by—
(A) false pretenses, a false representation, or actual fraud(.)

11 U.S.C. § 523(a)(2)(A).

Courts have historically required a creditor to establish the following elements by a preponderance of the evidence: (1) the debtor made a representation to the creditor; (2) the debtor’s representation was false; (3) the debtor possessed scienter, i.e. an intent to deceive; (4) the creditor relied on the debtor’s misrepresentation, resulting in a loss to the creditor, and (5) the creditor’s reliance was justifiable. Field v. Mans,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gardiner v. Curtis
D. Idaho, 2025
Rable v. Childers
N.D. Ohio, 2023
In re: Stanley Herbert Brody
Ninth Circuit, 2017
Americash Loans, LLC v. Marquardt (In re Marquardt)
561 B.R. 715 (C.D. Illinois, 2016)
Yust v. Henkel (In re Henkel)
490 B.R. 759 (S.D. Ohio, 2013)
Joyce v. Wish (In re Wish)
472 B.R. 763 (N.D. Illinois, 2012)
Zamora v. Jacobs (In Re Jacobs)
448 B.R. 453 (N.D. Illinois, 2011)
6050 Grant, LLC v. Hanson (In Re Hanson)
437 B.R. 322 (N.D. Illinois, 2010)
Deady v. Hanson (In Re Hanson)
432 B.R. 758 (N.D. Illinois, 2010)
Baermann v. Ryan (In Re Ryan)
408 B.R. 143 (N.D. Illinois, 2009)
Goldberg v. Ojeda (In Re Ojeda)
397 B.R. 67 (N.D. Illinois, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
360 B.R. 662, 2006 Bankr. LEXIS 3346, 2006 WL 3512109, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cripe-v-mathis-in-re-mathis-ilcb-2006.