Gardiner v. Curtis

CourtUnited States Bankruptcy Court, D. Idaho
DecidedJanuary 27, 2025
Docket21-06015
StatusUnknown

This text of Gardiner v. Curtis (Gardiner v. Curtis) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, D. Idaho primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gardiner v. Curtis, (Idaho 2025).

Opinion

UNITED STATES DISTRICT COURT

FOR THE DISTRICT OF IDAHO

In re: Case No. 1:23-cv-00200-DCN SCOTT ETHAN CURTIS and MEAGAN RAE CURTIS, Adv. Case No. 21-06015-NGH Bankr. Case No. 21-00521-NGH Debtors. MEMORANDUM DECISION AND WILLIAM GARDINER and SHANNON ORDER ON APPEAL GARDINER,

Appellants,

v.

SCOTT ETHAN CURTIS and MEAGAN RAE CURTIS,

Appellees.

I. INTRODUCTION This matter comes before the Court on Appellants William and Shannon Gardiner’s appeal of the final Memorandum Decision and Judgment entered by the United States Bankruptcy Court for the District of Idaho in Gardiner v. Curtis (In re Curtis), Adv. Case No. 21-06015-NGH. The appeal has been fully briefed and is ripe for the Court’s review. Having reviewed the record, the Court finds the parties have adequately presented the facts and legal arguments in their briefs. Accordingly, in the interest of avoiding further delay, and because it finds the decisional process would not be significantly aided by oral argument, the Court decides this appeal on the record and without oral argument. Dist. Idaho Loc. Civ. R. 7.1(d)(1)(B). For the reasons set forth below, the Bankruptcy Court is AFFIRMED. II. BACKGROUND

The general factual background underlying this dispute is set forth in the Bankruptcy Court’s Memorandum Decision. Dkt. 7, at 6–11.1 To the extent not outlined below, the background set forth by the Bankruptcy Court is incorporated by reference. Id. In April of 2020, Appellants William and Shannon Gardiner (collectively, the “Gardiners”) hired BFH Idaho, LLC (“BFH”)—a company created by Appellees Scott and

Meagan Curtis (collectively, the “Curtises”)—to construct a log cabin near High Valley, Idaho. Id. at 7. The construction contract between the Gardiners and BFH2 provided the total cost for the cabin would be $722,341.00. Id. at 8. To fund construction, the Gardiners obtained a loan from Idaho Central Credit Union (“ICCU”). Id. The Curtises could access the Gardiners’ loan funds through draw

requests—submitted through ICCU’s “getbuilt.com” system—for construction expenses. Id. To make a draw request, Meagan Curtis submitted the amount necessary to pay various vendors and suppliers, as well as supporting documents and invoices as requested by ICCU, through the getbuilt.com system. Id. ICCU also retained professional independent inspectors who periodically inspected the cabin site and submitted written reports, with

1 Unless otherwise referenced, citations are to the CM/ECF-generated page number in the instant civil case.

2 While the construction contract was between BFH and the Gardiners, the Bankruptcy Court explained all of the Gardiners’ dealings with BFH went through the Curtises, and that the Gardiners’ allegations in the adversary proceeding involved only actions taken by the Curtises. Dkt. 7, at 11–12. As such, the Bankruptcy Court held the Curtises could be held personally liable to the extent they actively participated in, or were responsible for, the alleged wrongdoing of BFH. The Curtises have not appealed this holding. photographs showing the progress of the job, to ICCU. Dkt. 8, at 7. These reports were also available in the getbuilt.com system. Compare Dkt. 7-3, at 118, ¶ 21 with Dkt. 7-3, at 191, ¶ 21.

When the Curtises submitted a draw request, the Gardiners received a notification and would have to approve the request before loan funds were released. Dkt. 7, at 8. Once a draw request was approved, the funds were paid by ICCU to a title company, which then transferred the money into BFH’s bank account. Id.; Dkt. 6, at 11. During the bench trial in the underlying adversary proceeding, the Curtises testified they believed the Gardiners

had access to the getbuilt.com system and could see the full details of the draw requests and supporting documentation. Dkt. 7, at 8. However, the Gardiners maintained they were unable to view the getbuilt.com system until they later requested access to the system in approximately November of 2020. Id. at 8–9; Dkt. 6, at 11. In total during the cabin construction, the Curtises submitted 11 draws—each of which was approved by the

Gardiners—for a total of $549,251.99. Dkt. 7, at 9. From its inception, construction of the cabin was plagued by various problems, including multiple mistakes by subcontractors and suppliers, unsafe road conditions caused by severe winter weather, and several accidents involving vehicles and construction equipment at the building site. Id. at 9–10. In addition, building costs skyrocketed due to

material and labor shortages caused by the COVID-19 pandemic. Dkt. 7, at 132:5–14, 181:1–23, 194:3–25, 524:8–23. During trial, Scott Curtis and others testified that building costs escalated as much as 200 percent during construction of the Gardiners’ cabin.3 Id. As a result of escalating costs and the many issues with the project, the Curtises maintain they spent more than $43,000.00 of their own money—above and beyond the total amount they

withdrew from the Gardiners’ ICCU loan—on the Gardiners’ cabin. Dkt. 8, at 14. By contrast, the Gardiners argue the Curtises had trouble with accounting and available funds throughout the project. Dkt. 6, at 11. As a result, the Gardiners highlight the Curtises ultimately sought and obtained a short-term cash loan from National Funding, requiring immediate and daily repayment. Id. The Gardiners maintain these “daily

payments to National Funding began in mid-October 2020, and quickly served to dissipate the funds available to the Curtises.” Id. In November of 2020, the parties exchanged emails regarding the progress of construction, remaining loan funds, and the next steps for the project. The Gardiners contend it became clear by late November 2020 that, “based on the actual work that had been done, the loan funds were fast being depleted with significant

work still to be completed.” Id. at 12. Due to winter weather and unsafe conditions, work on the cabin stalled in December 2020. Dkt. 7, at 10. On December 14, 2020, the parties met to discuss the status of the project. Id. The Curtises testified they told the Gardiners during this meeting that they would not be able to finish the cabin within budget and would need approximately

$120,000.00 in additional funds to complete construction. Id. On December 15, 2020, the Gardiners sent the Curtises an email seeking the

3 The Gardiners did not rebut such testimony. See generally, Dkt. 7, at 187:21–236:3, 526:24–530:1. collection of $13,681.38, which the Gardiners maintained the Curtises had received loan funds for, but had not yet paid to suppliers or subcontractors. Id. Shortly thereafter, the Curtises hired an attorney, and the Gardiners hired another contractor to complete the

construction of their cabin. Id. at 10–11. The Gardiners ultimately spent over $120,000.00 in additional funds to complete their project. Id. at 11. On August 10, 2021, the Curtises filed a voluntary petition for relief under Chapter 7 of the Bankruptcy Code. Id. On November 8, 2021, the Gardiners initiated an adversary proceeding against the Curtises pursuant to 11 U.S.C. § 523(a)(2)(A), (a)(2)(B), (a)(4), and

(a)(6).4 Dkt. 7, at 11. The Gardiners ultimately sought a nondischargeable judgment against the Curtises for $41,782.475 in construction loan funds the Curtises received, but purportedly did not use for the Gardiners’ project.6 See, e.g., Id. at 18; Dkt. 6, at 13–15. The Gardiners argued such funds should be nondischargeable because they were obtained through the Curtises’ false representations, embezzlement, and conversion. Dkt. 7, at 14–

24.

4 The Gardiners abandoned their 11 U.S.C. § 523

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ghomeshi v. Sabban
600 F.3d 1219 (Ninth Circuit, 2010)
Grogan v. Garner
498 U.S. 279 (Supreme Court, 1991)
Kawaauhau v. Geiger
523 U.S. 57 (Supreme Court, 1998)
Cohen v. De La Cruz
523 U.S. 213 (Supreme Court, 1998)
In Re Littleton
942 F.2d 551 (Ninth Circuit, 1991)
In Re: Thomas M. Banks, Debtor
263 F.3d 862 (Ninth Circuit, 2001)
Luzar v. Western Surety Co.
692 P.2d 337 (Idaho Supreme Court, 1984)
United States v. Hinkson
585 F.3d 1247 (Ninth Circuit, 2009)
Peasley Transfer & Storage Co. v. Smith
979 P.2d 605 (Idaho Supreme Court, 1999)
Khaligh v. Hadaegh (In Re Khaligh)
338 B.R. 817 (Ninth Circuit, 2006)
McCrary v. Barrack (In Re Barrack)
217 B.R. 598 (Ninth Circuit, 1998)
Cripe v. Mathis (In Re Mathis)
360 B.R. 662 (C.D. Illinois, 2006)
King v. Lough (In Re Lough)
422 B.R. 727 (D. Idaho, 2010)
Applegate v. Shuler (In Re Shuler)
21 B.R. 643 (D. Idaho, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
Gardiner v. Curtis, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gardiner-v-curtis-idb-2025.