Crescent City Marine, Inc. And Central Boat Rentals, Inc. v. M/v Nunki, Her Engines, Tackle, Etc., in Rem.

20 F.3d 665
CourtCourt of Appeals for the Fifth Circuit
DecidedJune 15, 1994
Docket93-3194
StatusPublished
Cited by16 cases

This text of 20 F.3d 665 (Crescent City Marine, Inc. And Central Boat Rentals, Inc. v. M/v Nunki, Her Engines, Tackle, Etc., in Rem.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crescent City Marine, Inc. And Central Boat Rentals, Inc. v. M/v Nunki, Her Engines, Tackle, Etc., in Rem., 20 F.3d 665 (5th Cir. 1994).

Opinion

REYNALDO G. GARZA, Circuit Judge:

Crescent City Marine, Inc. and Central Boat Rentals, Inc. appeal the district court’s finding that they were not entitled to a maritime lien. Finding no error, we AFFIRM.

I. FACTS

The M/V NUNKI (“NUNKI”) was owned by Impressa Transporti Maritimi SRL, and under the time charter of Scanports Shipping, Ltd. (“Scanports”). Scanports entered into a voyage charter with Energy Transport, LTD., a subsidiary of Cabot Corporation, Scanports, as the “disponet owner” of the NUNKI, appointed Global Steamship Agencies, Inc. (“Global”), to act as local, husbanding agent for the charterers after Global had been nominated by the voyage charterer. Acting on instructions from the voyage charterers, Global arranged to have the “slops” 1 removed from the NUNKI, and disposed ashore by Emerald Refining, Inc. (“Emer- *667 aid”), an independent Louisiana service company. The voyage charterers agreed to pay Emerald $1 per barrel both to remove and dispose of the slops, plus the opportunity to sell any salvageable crude oil removed from the vessel. After the slops had been removed from the NUNKI, Emerald sent an invoice to the voyage charterers totalling $27,644.64, which was paid in full.

Although Emerald agreed with the voyage charterers to remove and dispose of the “slops” for a flat per-barrel charge, Emerald hired appellants Crescent City Marine and Central Boat Rentals’ tugs and barges on a per-day basis. After the “slops” had been removed from the ship, Emerald encountered difficulties in disposing of the material. This resulted in Crescent City Marine and Central Boat Rentals’ equipment being tied up much longer than had been anticipated by Emerald. Work that was supposed to be completed in two to three days actually required approximately twelve days to finish. The appellants incurred additional transportation costs of $80,768.66.

The appellants were never paid for their services and instituted this action by seizing the vessel claiming a maritime lien. The district court found that the appellants were not entitled to a maritime lien and vacated their seizure of the vessel. The appellants timely appealed to this court.

II. DISCUSSION

The appellants claim the district court erred in: (1) finding that the appellants did not perform the work at the request of a person authorized to act for the vessel; (2) finding that the contract priee to remove the slops was $1 per barrel; (3) finding that the charges of the appellants were incurred solely because of delays Emerald encountered in disposing of the slops; and (4) failing to hold that a maritime lien attaches when necessaries are ordered by or supplied to a charterer unless the supplier has notice that the person who ordered the necessaries lacked authority to do so.

We find that the district court did not err in any of its findings. Therefore, the judgment of the district court is affirmed.

A. Did the appellants perform the work at the request of a person authorized to act for the vessel?

The appellants claim that they have met all of the requirements for a maritime lien, and that the trial court erred in holding that they were not entitled to a maritime lien. The appellants also claim that the district court erred in holding that Emerald was the only contractor hired by the vessel to perform the work, and only it could have acquired a maritime lien. The Federal Maritime Commercial Instruments and Lien Acts provides that:

[A] person providing necessaries to a vessel on the order of the owner or a person authorized by the owner—
(1) has a maritime lien on the vessel;
(2) may bring a civil action in rem to enforce the lien; and
(3) is not required to allege or prove in the action that credit was given to the vessel.

46 U.S.C. § 31342(a).

Appellants assert that the district court erred in holding that they were subcontractors and that by definition, they did not perform the work at the request of a person authorized to act for the vessel. They claim that the “restrictive repair contractor” line of cases relied on by the district court does not apply to this case. See, Bonanni Ship Supply, Inc. v. United States, 959 F.2d 1558 (11th Cir.1992); Farwest Steel Corp. v. Barge SEA-SPAN 241, 828 F.2d 522 (9th Cir.1987), cert. denied, 485 U.S. 1034, 108 S.Ct. 1594, 99 L.Ed.2d 909 (1988). Rather, they claim that the “agent/broker” or “middle-man” line of cases is more consistent with the facts presented in this case. See, Marine Fuel Supply and Towing v. M/V KEN LUCKY, 869 F.2d 473, 475 (9th Cir.1988); Belcher Co. of Alabama, Inc. v. M/V MARATHA MARINER, 724 F.2d 1161 (5th Cir.1984). In the “agent/broker” or “middle-man” cases there were as many as five layers between the owner of the vessel and the service provider, yet the service provider was still permitted a lien against the vessel.

Appellants contend that the Federal Maritime Commercial Instruments and Liens Act *668 broadly defines persons authorized by the owner to procure necessaries for a vessel. Although 46 U.S.C. §§ 31341, et seq. lists those persons presumed to have authority, that presumption is not conclusive. Gulf Oil Trading Co., a Div. of Gulf Oil Co. v. M/V CARIBE MAR, 767 F.2d 743, 748-49 (5th Cir.1985). Appellants assert that persons falling outside the class presumed to have authority might still have authority to procure necessaries; there is merely no presumption of authority. Appellants further assert that it is axiomatic in this court that authorization, either actual, implied or fairly presumed, given prior to, during performance of the services, or ratified subsequent to the performance will suffice. Atlantic & Gulf Stevedores, Inc. v. M/V GRAND LOYALTY, 608 F.2d 197, 202 (6th Cir.1979).

Appellants assert that Steven Long, the President of Emerald, testified that Nick Kandiliotis, President of Global, was informed during their negotiations that:

(1) Emerald did not own the necessary tug boats and tank barges absolutely required to properly remove, transport and dispose of the NUNKI’s slops; and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
20 F.3d 665, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crescent-city-marine-inc-and-central-boat-rentals-inc-v-mv-nunki-her-ca5-1994.