Creppel v. United States Army Corps of Engineers

500 F. Supp. 1108, 14 ERC 1972, 14 ERC (BNA) 1972, 1980 U.S. Dist. LEXIS 17741
CourtDistrict Court, E.D. Louisiana
DecidedAugust 8, 1980
DocketCiv. A. 77-25
StatusPublished
Cited by8 cases

This text of 500 F. Supp. 1108 (Creppel v. United States Army Corps of Engineers) is published on Counsel Stack Legal Research, covering District Court, E.D. Louisiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Creppel v. United States Army Corps of Engineers, 500 F. Supp. 1108, 14 ERC 1972, 14 ERC (BNA) 1972, 1980 U.S. Dist. LEXIS 17741 (E.D. La. 1980).

Opinion

REASONS FOR RULING

MITCHELL, District Judge.

The parties herein have filed cross motions for summary judgment. Plaintiff landowners are seeking to have the Court *1112 set aside the agency order of Brigadier General Drake Wilson of November 16, 1976 as invalid and ordering the defendant United States Army Corps of Engineers to authorize the immediate construction of the Harvey Canal-Bayou Barataría Project as originally proposed in 1963. The federal defendants are seeking to have the Court uphold the Wilson order. An amicus curiae brief was filed by several conservation, environmental, recreational and civic organizations supporting the affirmation of the Wilson order.

The Harvey Canal-Bayou Barataria Levee Project (hereinafter the “Project”) was approved as a small flood control project pursuant to Section 205 of the Flood Control Act of 1948, as amended, Public Law 87-874, 33 U.S.C. § 701s, by the United States Army Corps of Engineers (hereinafter the “Corps”) on January 22, 1964. The Corps is authorized, under the small flood control statute, to spend up to one million dollars ($1,000,000) on authorized works. All costs above that amount are required to be assumed and guaranteed by the local governing body, Jefferson Parish (hereinafter the “Parish”).

This Project involved an 11,700-acre tract located near the headwaters of the Barataría Bay system. This area was unleveed and undrained prior to the initiation of the Project. Part of this area is a 3,700-acre tract in which the plaintiffs have an interest and which is predominately a freshwater system consisting mainly of swamp and some marsh. This 3,700-acre tract is the area which is at issue herein. The Corps found the tract was subject to flooding from normal high, storm and hurricane tides of the Gulf of Mexico through Barataría Bay, Barataría Bay Waterway and the Gulf Intracoastal Waterway. See “Review of Reports, Harvey Canal-Bayou Barataría Levee, La., Sept. 20, 1963.”

The Project was planned to be constructed in two phases. Phase I entailed excavation of material from the bottom of the Harvey Canal and Bayou Barataría, and placement of the material along the bank to form the levee system. Phase I construction was begun on September 22, 1971 and was completed on November 24, 1973. The authorized federal expenditure of one million dollars was exhausted in the construction of Phase I.

Phase II of the Project consisted of adding additional embankment material where needed and of shaping the first lift embankment material to form the final levee section. It also provided for the closure of Bayou Aux Carpes, Bayou Des Families and the Natural Gas Pipeline Canal and for the construction of a pumping station at Bayou Aux Carpes which would drain the swamp and marsh land located behind the levees.

It was initially contemplated that the Project would provide flood protection and land reclamation benefits in the area. The land reclamation would be achieved through the drainage of wetlands by the Bayou Aux Carpes pumping station.

The Corps was required to obtain the following local assurances of cooperation from Jefferson Parish prior to commencement of the Project:

(a) Provide without cost to the United States all land, easements and rights-of-way necessary for construction of the Project, including necessary modifications and/or relocation of existing facilities;
(b) Hold and save the United States free from damages due to construction works;
(c) Construct an additional pumping station with an initial capacity of not less than 154 c.f.s. as provided in the plan of improvement and future extensions to pumping capacities as may be necessary for development of the area; and
(d) Maintain and operate all works after completion in accordance with the regulations prescribed by the Secretary of the Army.

Jefferson Parish executed the formal act of assurances, furnishing to the Corps the required agreements, on July 20, 1967. The Parish obtained the necessary rights-of-way and servitudes for the purpose of constructing, maintaining and operating the Project.

*1113 An Environmental Impact Statement was prepared and filed with the Council on Environmental Quality on November 14, 1970.

During Phase I construction Congress passed the Federal Water Pollution Control Act Amendments of 1972, Section 301 of which provides that the discharge of dredged or fill material into navigable waterways without obtaining a permit under Section 404 of the Act is unlawful. The Corps promulgated regulations implementing Section 404 on July 22, 1974.

Commencement of Phase II of the Project was authorized in March, 1974. The closure of Bayou Aux Carpes was completed in July, 1974 and on August 10,1974 the Parish let a contract for the construction of the pumping station to Southbend Contractors, Inc. However, the Corps requested that the Parish cease further construction to allow the Corps to conduct a Section 404 review of the remaining “fill” portions of the Project.

A public hearing was conducted by the Corps on January 7, 1975 to provide interested parties the opportunity to present their views on the remaining work to be done. It was the first Section 404 hearing conducted in the New Orleans area and both positive and negative comments were received. The parties owning land in the area supported the land reclamation aspects of the Project. Many environmental and civic groups opposed the construction of the pumping station since it would result in the destruction of the wetlands in the area.

Colonel E. R. Heiberg, the New Orleans District Engineer, conducted the hearing and issued a Statement of Findings (SOF) on March 26, 1975. He found the principal adverse environmental effects would occur with the closure of Bayou Aux Carpes and the construction of the pumping station which, in combination with the levee system, would result in the loss of the wetland fish and wildlife habitat within the Project area. Colonel Heiberg determined, however, that the comments made in opposition to the Project were directed to the Project as a whole rather than specifically to the dredge and fill work remaining to be done. He concluded that despite the adverse environmental effects, the total public interest would be served by the construction of the Project.

The Environmental Protection Agency (hereinafter “EPA”), in a letter dated April 25,1975, objected to the Project as originally designed after reviewing the proposal and Heiberg’s SOF. The EPA found that the permanent blockage of the bayous and the drainage of the interior would result in the irretrievable loss of valuable wetlands, having an unacceptable adverse impact on wildlife and recreational areas and would not be in the public interest. The EPA suggested that if a pumping station was required to augment natural drainage, it should be maintained so as to preserve the integrity of the wetlands. In light of the EPA objections the matter was forwarded to the Division Engineer for further evaluation and discussions. EPA continued to object to the destruction of the wetlands.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Creppel v. United States
33 Fed. Cl. 590 (Federal Claims, 1995)
Bensch v. Metropolitan Dade County
798 F. Supp. 678 (S.D. Florida, 1992)
Bensch v. Metropolitan Dade County
541 So. 2d 1329 (District Court of Appeal of Florida, 1989)
Bayou Des Familles Development Corp. v. United States Corp.
541 F. Supp. 1025 (E.D. Louisiana, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
500 F. Supp. 1108, 14 ERC 1972, 14 ERC (BNA) 1972, 1980 U.S. Dist. LEXIS 17741, Counsel Stack Legal Research, https://law.counselstack.com/opinion/creppel-v-united-states-army-corps-of-engineers-laed-1980.