Cravotta v. Deggingers' Foundry, Inc.

215 P.3d 636, 42 Kan. App. 2d 700, 2009 Kan. App. LEXIS 828
CourtCourt of Appeals of Kansas
DecidedSeptember 11, 2009
Docket101,050
StatusPublished
Cited by3 cases

This text of 215 P.3d 636 (Cravotta v. Deggingers' Foundry, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cravotta v. Deggingers' Foundry, Inc., 215 P.3d 636, 42 Kan. App. 2d 700, 2009 Kan. App. LEXIS 828 (kanctapp 2009).

Opinion

Hill, J.:

In this case, Deggingers’ Foundry, Inc., of Topeka, promised in' a settlement agreement to manufacture and deliver *701 some chandeliers and other items to the plaintiff, Mark Cravotta, in Dallas, Texas, by a certain date. The foundry failed to do so. During the trial of this matter, when Tim Degginger claimed Cravotta’s failure to forward important electrical system information stopped the foundry from making a timely delivery, the district court ruled the Uniform Commercial Code’s statute of frauds barred Degginger from successfully raising such a defense. We must reverse and remand this case because the trial court failed to consider the contract in the commercial context from which it arose, as the Code requires. By relying only on the statute of frauds and not considering the parol evidence statute in the Code, the court erred.

We note the case history.

Cravotta engaged the Deggingers’ Foundry to make some chandeliers, sconces, and lanterns for installation in a mansion in Texas in April 2003. Cravotta wanted the foundry to make 3 nickel-bronze chandeliers, 8 nickel-wall sconces, and 16 silicone-bronze lanterns. The cost for these items was $106,000, and the parties anticipated a production time of 90 days.

The parties signed a concise two-page contract drawn on Deg-gingers’ letterhead. The essence of their agreement provided a 10-step list of how the parties intended to complete the project:

“By way of outline this contract shall be implemented by:
“1. Contract.
“2. Final shop drawings prepared by Degginger’s Foundiy, Inc.
“3. Final engineering review of the shop drawings.
“4. Patterns.
“5. Prototypes.
“6. Owner Approval.
“7. Aesthetic sample submittals.
“8. Production.
“9. Product approval.
“10. Shipping to job site.”

The rest of the agreement contained terms concerning method of payment and other matters not pertinent to this appeal.

Matters did not go smoothly for the parties, and on June 20, 2005, Cravotta filed a breach of contract lawsuit against Degginger *702 in Shawnee County. Cravotta alleged he had already paid $79,500 under the contract and Degginger had breached their contract by failing to manufacture the products. Cravotta sought $79,500 in damages plus interest. In response, Degginger admitted it made the contract with Cravotta but alleged the original contract had been modified by a series of subsequent communications and acknowledgments from both sides.

Despite the lawsuit, the parties were still working toward a common goal. For example, Degginger delivered the 16 lanterns to Cravotta even after Cravotta filed the petition. But, we note those lanterns had no wiring or glass. Tension between the parties apparently eased since, instead of going forward with the breach-of-contract case, Cravotta and Degginger reached an agreement to settle the lawsuit and complete the project.

The parties recite their settlement agreement into the record in district court.

On February 3,2006, the district court held a hearing so a record could be made of the parties’ agreement. Cravotta appeared at the hearing, but only counsel was present on behalf of Degginger. Cravotta’s attorney stated the parties had agreed that Degginger currently owed $62,478.22 to Cravotta under the April 7, 2003, contract. Degginger agreed to complete the eight sconces and three chandeliers. These items would be completed in a manner satisfactory to Cravotta and delivered to him by April 15, 2006. Once the items were completed and delivered to Cravotta, Degginger would be credited $62,478.22 and, for completing the work, Cravotta would pay Degginger tire remaining balance owed to the foundry under the contract. Finally, Degginger agreed to pay Cravotta $6,000 for legal fees.

Unfortunately, Degginger did not deliver the sconces and chandeliers to Cravotta. by April 15, 2006. Therefore, on May 12, 2006, Degginger filed several motions alleging Cravotta had prevented the foundry from completing the sconces and chandeliers on time because Cravotta failed to provide vital information needed to complete the wiring of the items. Thus, Degginger asked the district court to find that Cravotta had breached the settlement agree *703 ment and asked the court to order Cravotta to pay $27,000 to Deg-ginger for completing at least part of the contract. In turn, Cravotta denied the allegations and asked for judgment against Degginger. The question then became which party first breached their settlement agreement.

The district court tried the dispute in April 2008. Tim Degginger, President of Deggingers’ Foundry, Inc., testified about all of the work the foundry had completed in compliance with the contract. Because Cravotta could not provide acceptable models or patterns, the foundry had to hand-sculpt some patterns and machine-sculpt the remaining patterns used to create the chandeliers and sconces. After months of discussions and submissions of many drawings, the parties finally agreed on a design that was acceptable to the owner of the house in Texas. Degginger pointed out that for 1 chandelier, the foundry made 33 parts from lost-wax castings, each hand sculpted. The remaining 53 other parts were sand-cast, meaning they were hand carved as well. He said the chandeliers and sconces are at the foundiy, essentially complete. The only remaining work to be done on them is wiring and the final polishing. According to Degginger, wiring is the problem.

From the start of the project until the trial to the court, Deg-ginger sought information from Cravotta about the “stepdown transformers” inside the house where the items were going to be placed. According to Degginger, Cravotta never provided this information. In the foundry’s view, this information was crucial in order to ensure that the sconces and chandeliers were properly wired and safe to use inside the house. Degginger stated the house in Texas has a veiy unusual electrical system for a residence — 480-volt, three-phase power, and current at 600 watts. He pointed out that the foundiy uses a similar electrical system to melt bronze, 300 pounds in 15 minutes. Such electrical power is very dangerous, potentially lethal. The stepdown transformers lower the current to 220 or 110 volts, single phase. Therefore, wiring of the chandeliers and sconces required expert design assistance, what Degginger referred to as an electrical engineer’s stamp of approval on the wiring plans.

*704 In support, the foundry introduced as an example of the parties ongoing communication, a February 28, 2005, e-mail to Cravotta from Janet Zoble, who was hired by Degginger to work with Cravotta in designing the items to be created. It stated:

“Electrical drawings are nearly complete on the chandelier. Detailing will require input from the electrical engineer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Core Cashless v. Kansas Dept. of Labor
Court of Appeals of Kansas, 2018
James Colborn Revocable Trust v. Hummon Corp.
Court of Appeals of Kansas, 2017
Robl Construction, Inc. v. Andrew Homoly
781 F.3d 1029 (Eighth Circuit, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
215 P.3d 636, 42 Kan. App. 2d 700, 2009 Kan. App. LEXIS 828, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cravotta-v-deggingers-foundry-inc-kanctapp-2009.