Crabb v. Welden Bros.

65 F. Supp. 369, 1946 U.S. Dist. LEXIS 2764
CourtDistrict Court, S.D. Iowa
DecidedMarch 12, 1946
Docket374, 479, 503
StatusPublished
Cited by11 cases

This text of 65 F. Supp. 369 (Crabb v. Welden Bros.) is published on Counsel Stack Legal Research, covering District Court, S.D. Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Crabb v. Welden Bros., 65 F. Supp. 369, 1946 U.S. Dist. LEXIS 2764 (S.D. Iowa 1946).

Opinion

DEWEY, District Judge.

Suits were instituted in this court by four salaried employees to recover overtime compensation under the provisions of the Fair Labor Standards Act, 29 U.S.C.A. § 201 et seq., against certain independent contractors who had engaged in the construction of the Alcan Highway.

The cases were consolidated for trial to the court.

In the spring of 1942 the United States of America was contemplating the con *371 struction of an international vehicular highway from Ft. St. John in Canada to a point in Alaska subsequently determined to be at Big Delta to join with an existing highway that continued to Fairbanks.

The highway was to follow a line of airports then existing in Canada and Alaska: Ft. St. John, Ft. Nelson, Watson Lake, Whitehorse, Boundary, Big Delta, and the respective termini of the existing roads in Canada and Alaska. It was to be called the Alcan Highway and was about 1,400 to 1,500 miles in length, about 300 miles of it in Alaska. (Distances are given for descriptive purposes and not intended to be accurate).

The project was delegated to the Public Roads Administration and that agency in turn employed the C. F. Lytle Company and the Green Construction Company as ‘‘project managers’’’ for that part of the construction work in Alaska. And in 1942 there was procured and employed in such construction fourteen contractors who are designated as “affiliated contractors.” These affiliated contractors and the project managers were authorized to and did enter into written contracts with individuals of different classifications to do the work.

The Army was working upon a supply road along the proposed route, and the project managers with the affiliated contractors took charge as soon as they could get their organization and the Government could transport those organizations and equipment to Alaska.

The only work that could be accomplished during the year 1942 was to build a supply trail or road. They did in that year with the use of heavy • equipment knock down and push to one side of the trail or road the trees encountered. The roots did not extend very far into the ground because it did not thaw more than two or three feet below the surface. One reason the ground did not thaw any more in the short summer season was a deposit which covered the surface of the ground known as tundra or muskeg, some two or three feet in depth which served as an insulation.

The several project managers and the Public Roads Administration were able to and did finish a temporary road or trail in 1942 along the general route indicated. Besides removing the trees they removed the tundra and ditched the sides of the road to some extent, but it was not a finished road and, in fact, in the year 1943 they found it more difficult to use in some places than if the tundra had not been removed, as the summer thaw without the tundra soon made a morass of mud and mire that in many places prevented the use of trucks and equipment. Especially was this true in Canada from Whitehorse to the boundary line of Alaska, a distance of at least 50 miles.

Temporary bridges were constructed which washed out during the winter and spring of 1942-1943.

The Public Roads Administration in the spring of 1943 completed and published its surveys, location and plans and specifications for the permanent road and bridges. While the location of the permanent road was not influenced by the location of the supply trail or road, they were both built or to be built along the same proposed route which brought them more or less together or adjacent to each other.

In the year 1943 the project managers allocated the different portions of the work in Alaska to seventeen associated contractors, and the work was diligently prosecuted and completed, with the possible exception of a permanent bridge or two, by the middle of October in 1943. It was on this work in 1943 that these plaintiffs were employed.

The Public Roads Administration paid all the expenses of the project. It maintained offices in Seattle and perhaps at other points in the United States; bought and shipped the goods necessary for the feeding, housing and comfort of the men and for doing the work. These goods were sent to Alaska in convoyed ships and were unloaded on docks at the port of Valdez in southern Alaska. The goods were unloaded by Army personnel and first assembled at Valdez and later taken to warehouses and distributing points at different locations, by employees of contractors working under the direction of the project managers and the Public Roads Administration. Some of it was stored during the preceding winter in Fairbanks, Alaska. Later in the summer other storehouses were prepared and used on the highway and especially at a point known as Tok where a managerial headquarters had been constructed on the Alcan Highway.

The above method of procuring and delivering the goods did not include the gas and oil requirements. The Standard Oil Company of California maintained a gasoline storage plant at Valdez and sold and *372 delivered in Alaska the gasoline and oil products, directly to the Public Roads Administration. Gasoline and oil products constituted more than half of all the supplies that were used by the contractors in building the road in Alaska. However, this does not mean that large quantities of goods were not brought in and distributed to the affiliated contractors, as it took a tremendous amount of goods to furnish the men with food, housing facilities and supplies, and the contractors with construction materials and equipment. One of the associated contractors was the Hoak Transportation Company which undertook to and did transport the goods, first, to the distributing points and later from those points to the contractors, although the associated contractors often hauled a part of their own supplies. One witness gave as a rough estimate the number of men employed on the project during the summer of 1943 at 5,000 and some 500 trucks being used in the transportation of supplies.

The general direction of the Alcan Highway from Ft. St. John in Canada to Big Delta and ultimately to Fairbanks, Alaska, fan in a northwesterly direction, but for our purposes we will consider it as running east and west.

When the project was started in 1942 there was a vehicular road known as the Richardson Highway from the port of Valdez extending in a northerly direction to Fairbanks. While this road was not an A-1 highway it was good enough for scheduled bus service. At a point about 75 miles north of Valdez on this road was a place called Gulkana, which was a managerial headquarters in 1942 and in the early part of 1943.

In order to facilitate the movement of the supplies to the main highway — as it was a roundabout route to go through Fairbanks —there was a cut-off extended in 1942 on what was known as the Slana Road or trail from Gulkana to a point on the Alcan Highway about midway between Big Delta and the Alaskan border. This point or place was first known as TanaCross, and was used as a storage depot and headquarters for some time but later they were moved a short distance east to Tok. The distance from Valdez to Tok by this supply route was about 150 miles. And Gulkana was about half way between Valdez and Tok.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Weinberger v. New York Stock Exchange
335 F. Supp. 139 (S.D. New York, 1971)
Martinez v. Killian-House Co.
255 S.W.2d 227 (Court of Appeals of Texas, 1953)
McComb v. Trimmer
85 F. Supp. 565 (D. New Jersey, 1949)
Filardo v. Foley Bros.
78 N.E.2d 480 (New York Court of Appeals, 1948)
Young v. Kellex Corporation
82 F. Supp. 953 (E.D. Tennessee, 1948)
Crabb v. Welden Bros.
164 F.2d 797 (Eighth Circuit, 1947)
Kasper v. National Electric Products Corp.
70 F. Supp. 927 (W.D. Pennsylvania, 1947)
Adams v. Long Turner Const. Co.
202 S.W.2d 112 (Missouri Court of Appeals, 1947)
Harrington v. Empire Const. Co.
71 F. Supp. 324 (D. Maryland, 1947)
Harlan-Wallins Coal Corporation v. David
196 S.W.2d 881 (Court of Appeals of Kentucky (pre-1976), 1946)
Maitrejean v. Metcalfe Const. Co.
72 F. Supp. 109 (D. Minnesota, 1946)

Cite This Page — Counsel Stack

Bluebook (online)
65 F. Supp. 369, 1946 U.S. Dist. LEXIS 2764, Counsel Stack Legal Research, https://law.counselstack.com/opinion/crabb-v-welden-bros-iasd-1946.