Cr Humphreys General Contractor, Inc. v. Tangipahoa Parish School System

973 So. 2d 178, 2007 La.App. 1 Cir. 0993, 2007 La. App. Unpub. LEXIS 343, 2007 WL 4896246
CourtLouisiana Court of Appeal
DecidedDecember 21, 2007
Docket2007 CA 0993
StatusPublished
Cited by1 cases

This text of 973 So. 2d 178 (Cr Humphreys General Contractor, Inc. v. Tangipahoa Parish School System) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cr Humphreys General Contractor, Inc. v. Tangipahoa Parish School System, 973 So. 2d 178, 2007 La.App. 1 Cir. 0993, 2007 La. App. Unpub. LEXIS 343, 2007 WL 4896246 (La. Ct. App. 2007).

Opinion

C. R. HUMPHREYS GENERAL CONTRACTOR, INC.
v.
TANGIPAHOA PARISH SCHOOL SYSTEM AND GOSSEN-GASAWAY-HOLLOWAY, LTD.

No. 2007 CA 0993.

Court of Appeal of Louisiana, First Circuit.

December 21, 2007.
NOT DESIGNATED FOR PUBLICATION.

KEVIN P. LANDRENEAU, Counsel for Plaintiff/Appellant, C. R. Humphreys General Contractor

ALTON B. LEWIS, Counsel for Defendants/Appellees, Tangipahoa Parish School System and Gossen-Gasaway-Holloway, Ltd.

Before WHIPPLE, GUIDRY and HUGHES, JJ.

WHIPPLE, J.

This matter is before us on appeal by a general contractor seeking sums allegedly due under a public works contract. Plaintiff, C. R. Humphreys General Contractor, Inc. ("C. R. Humphreys") appeals from a trial court judgment, dismissing with prejudice its claims to recover $11,505.18 for a requested change order, $11,600.00 withheld for punch-list items allegedly not completed, and damages allegedly caused by delays, interest, costs, and attorney's fees. For the following reasons, we affirm in part, reverse in part, and render.

FACTS AND PROCEDURAL HISTORY

On July 30, 2001, C. R. Humphreys and the Tangipahoa Parish School System ("the School System") entered into a contract for the construction of a shop building for Crystal Street Academy in Hammond, Louisiana.[1] The contract provided that C.R. Humphreys was to be paid $114,800.000 for performance of the contract and that the project was to be completed within 120 days from the date of the notice to proceed.

Prior to the issuance of the notice to proceed, the parties discovered that C. R. Humphreys could not obtain a building permit from the City of Hammond because the proposed location of the building as set forth in the plans was in a flood plain. Thereafter, Andrew Gasaway of Gossen-Gasaway-Holloway, Ltd., the project architect, revised the plans three times, each time attempting to relocate the building to a suitable location that would be most cost effective. Eventually, the School System agreed to the third relocation, and Gasaway thereafter issued the notice to proceed on November 14, 2001.

As a result of the plan revisions relocating the building site three times, C. R. Humphreys submitted to Gasaway a request for a change order for estimating time, field service work, additional underground electrical work, overhead, and profit. However, Gasaway disputed the request, stating that he believed it was "exorbitant," and, in a written response, cited C. R. Humphreys to article 7.3.10.6 of the specifications for proper itemization of the request.[2] C. R. Humphreys did not thereafter submit any itemization of the requested charges; consequently, Gasaway did not approve the request or issue a change order.

C. R. Humphreys proceeded with the work, after informing Gasaway in writing that by proceeding with the work, it was not waiving its right to a change order. In March 2002, C. R. Humphreys requested a certificate of substantial completion and a final punch list. Gasaway and Bernie Shontell, a representative of the School System, then inspected the building on March 6, March 20, and March 26, 2002.[3] The fire marshal also inspected the building on March 26, 2002, and he generated a list of items that needed correction, but nonetheless allowed for temporary occupancy of the building.

As a result of these inspections, Gasaway generated punch lists, setting forth items that needed to be completed or corrected, and he also directed C. R. Humphreys to complete all previous punch-list items and all items on the fire marshal's inspection report. The School System then issued a certificate of substantial completion on March 26, 2002

Thereafter, disputes arose between the parties as to C. R. Humphreys's responsibility for certain punch-list items and as to whether other items were corrected satisfactorily. Gasaway contended that various punch-list items were never properly completed, and he recommended withholding $11,600.00 from the contract price for outstanding punch-list items.

The dispute over C. R. Humphreys's request for a change order also continued. C. R. Humphreys again submitted a change-order request with the final payment application, seeking the additional sum of $11,505.18 for estimating time, labor, equipment, lost wages allegedly caused by the delay in issuing the notice to proceed, and profit and overhead attributed to the three revisions to the plans and additional work allegedly resulting from errors in the plans and specifications. In the change-order request, C. R. Humphreys also included a deduction for work and materials deleted by the architect in the plan changes and during the course of the project. However, Gasaway refused to approve a change order based on his assertion that the request for a change order was never submitted with the proper itemization. Thus, when final payment was made on the contract, the sum of $11,600.00 was withheld for outstanding punch-list items, and no amount was approved or paid toward the $11,505.18 change-order request. C. R. Humphreys then instituted this suit seeking to recoup these amounts, together with attorney's fees, interest, and court costs.

Following a bench trial, the trial court concluded that C. R. Humphreys did not complete the punch-list items and that it did not produce the required documentation to support a change order. Accordingly, the trial court rendered judgment, dismissing C. R. Humphreys's claims with prejudice. From this judgment, C. R. Humphreys appeals, listing seven assigmnents of error.

CHANGE-ORDER REQUEST (Assignments of Error Nos. 1, 4 & 5)

On appeal, C. R. Humphreys avers that the trial court erred in failing to find that Gasaway should have approved the change-order request that resulted from the errors in the design and plans. It also contends that the trial court made various erroneous factual findings relating to this issue.[4]

According to C. R. Humphreys, because the building was originally designed to be built in a flood plain, the plans were revised by the architect three times, causing C. R. Humphreys to incur additional expenses in estimating time, labor, field service work, and equipment and to suffer loss of income because of delays caused by the redrafting of the plans. C. R. Humphreys also contends that it was entitled to be paid for removing louvers and installing other material in their place because the School System and Gasaway decided that they did not want the louvers as originally designed. C. R. Humphreys further contends that it is entitled to the cost of constructing concrete landings in front of the two exterior doors because the landings were not in the plans and specifications.

According to C. R. Humphreys, it also subtracted $3,288.65 in its change-order request for deductions related to reduced electrical work and heating units, for a total change-order request of $11,505.18. C. R. Humphreys submits on appeal that defendants presented no evidence to refute the amount otherwise requested, and that the trial court accordingly erred in failing to award it this sum.

Contracts have the effect of law upon the parties, and the courts are bound to give legal effect to all contracts according to the common intent of the parties. This intent is determined by the words of the contract when they are clear and explicit and lead to no absurd consequences. LSA-C.C. arts. 1983, 2045 and 2046; O & M Construction, Inc. v. State, Division of Administration, 576 So. 2d 1030, 1034 (La. App. 1st Cir.), writ denied, 581 So. 2d 691 (La. 1991).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
973 So. 2d 178, 2007 La.App. 1 Cir. 0993, 2007 La. App. Unpub. LEXIS 343, 2007 WL 4896246, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cr-humphreys-general-contractor-inc-v-tangipahoa-p-lactapp-2007.