Abraham v. Greater Baton Rouge Consolidated Sewerage District

159 So. 2d 525, 1963 La. App. LEXIS 2226
CourtLouisiana Court of Appeal
DecidedDecember 16, 1963
DocketNo. 5995
StatusPublished
Cited by2 cases

This text of 159 So. 2d 525 (Abraham v. Greater Baton Rouge Consolidated Sewerage District) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Abraham v. Greater Baton Rouge Consolidated Sewerage District, 159 So. 2d 525, 1963 La. App. LEXIS 2226 (La. Ct. App. 1963).

Opinion

ELLIS, Judge.

The defendant, Greater Baton Rouge Consolidated Sewerage District, is a governmental unit established and managed by the City-Parish government of the Parish of East Baton Rouge and the City of Baton Rouge to facilitate the construction and operation of sanitary sewerage facilities, [526]*526and will be hereinafter referred to as the “District.” The plaintiff is the contractor who was engaged in the construction of a sewerage trunk line along Sherwood Forest Boulevard and Engineer Depot Road, and will be hereinafter referred to as the “Contractor.” Continental Insurance Company is a third party defendant, and is the insurer of the consulting engineers, Parsons Brinckerhoff, Quade and Douglas.

The subject of this litigation arises out of that project, which appropriately bears contract number S-13. The Contractor’s demands may be divided into two claims for extra work, as follows:1

Claim for $9,000.80 for extra work consisting of compacting soil along Engineer Depot Road to 95% density.
Claim for $20,968.50 representing money spent by the contractor in an unsuccessful attempt to meet the specified infiltration test, which test was later waived. '

The record in this case contains over five hundred pages of testimony and a total of eighty-four documentary exhibits. This court is indebted to all counsel for very excellent briefs which have been of material assistance in the determination of this case.

This court will first consider the claim for $9,000.80 for additional compaction along Engineer Depot Road. The trial court gave judgment in favor of the Contractor on this demand.

The written contract between the District and the Contractor provided trenches in highways and streets were to be backfilled and compacted to a density of not less than 95% of a specified standard. The term “compaction” refers to the pressing and compression of the loose earth as it is replaced in the trench. The greater the compaction, the less settling the replaced fill will do at a later date. Ninety-five per cent compaction is accomplished by tamping- or beating the loose earth either manually or with air tamps in layers of about six inches until the top of the trench is reached. Normal compaction is achieved in the same-way except the layers of earth replaced may be up to twelve inches in thickness.

The contract further provided trenches, not in streets were to be compacted in the normal manner without regard to the percentage of compaction.

Subsequent to the awarding of the S-13'. contract, it was determined by the Department of Public Works for the City-Parish government that trenches located in street right-of-ways but not on the improved' street itself ought to be compacted to 95% of density, as anything less might endanger the life of the street and require extensive-repairs at an early date. As the contract was thought to be ambiguous with regard to the percent of compaction required of trenches in rights-of-way, a price of $1.60 per linear foot for additional compaction along Sherwood Forest Boulevard and Engineer Depot Road was negotiated with the Contractor. The work along Sherwood. Forest Boulevard was then in progress and: the additional compaction there was performed and paid for as the work progressed..

Prior to the time the pipe laying operation-reached Engineer Depot Road, the District determined to move the proposed trench-located over an additional seven feet from-the edge of Engineer Depot Road, making-a total of seventeen feet between the trench and the pavement, so additional compaction would not be necessary along this road.

This information was communicated by-Mr. C. W. Hair, project engineer employed: by the Department of Public Works for [527]*527the City-Parish, to Mr. James Best, then employed’ by the Contractor as job superintendent. Mr. Best denies receiving this information and stated even if he had received it, he would have disregarded it because Mr. Hair was only the project engineer and not the consulting engineer, and was therefore without any authority to order such a change.

Mr. Hair’s testimony, however, is supported by an entry in his diary for August 11th, 1960. It is likewise supported by two important facts: That no written work order was ever issued for the additional compaction along Engineer Depot Road and that the trench along that road was actually cut seventeen feet from the edge of the pavement as specified by Mr. Hair.

In addition, whether or not Mr. Hair had authority to make such a decision is immaterial. Certainly, the Contractor would have proceeded at his own peril after having been duly informed by the project engineer of a decision of this magnitude. If Mr. Best doubted Mr. Hair, he had only to call Mr. Hardin, the representative of Parsons, Brinckerhoff, Quade & Douglas in charge of the Baton Rouge office maintained by the consulting engineers.

Therefore, the Contractor cannot recover for the additional compaction along Engineer Depot Road, having been specifically ordered not to do the work which was never formally ordered, but which was certainly contemplated and discussed.

There is a second reason why the contractor cannot recover for additional compaction along Engineer Depot Road. A letter dated September 1, 1961 from Mr. Frank J. McConnell, President Pro Tempore of the Consolidated Sewerage District, introduced by the Contractor as exhibit Number P-38, discloses an agreement worked out as between the District and the Contractor. The actual agreement was supported by various testimony also.

The agreement, entered into because there may have been some confusion as to whether or not the additional compaction work should have been performed along Engineer Depot Road, provided the Contractor should be paid $1.60 per linear foot for compaction along Engineer Depot Road if in fact the additional work had been performed. In order to determine if the work had been done, it was agreed that soil borings would be made and tests conducted to determine the actual compaction as of the present time. It was thought these results would indicate whether or not the original compaction was actually 95%, though it was agreed they would not accurately show the actual compaction at the time the trenches were filled. The soil testing work was evidently to be done by Pittsburgh-Laboratories, but there is no indication as to who was to arrange for the tests or who was to bear the expenses.

On the trial of the case, the Contractor introduced a report of Shilstone Testing Laboratory which indicated that on August 1, 1961 at several points along the two sewer lines in question, the percentage of proctor, which we understand to be another way to express compaction, varied from 79% to 105.8%. These tests were made only to a depth of six inches, however, and the trenches had been cut to depths of up to twenty feet, with an average depth of about fifteen feet. These tests, according to the testimony of Mr. Traylor and Mr. Mahan, employees from the testing laboratory, are of absolutely no value in determining the compaction below twelve inches, but that deeper tests could have been made. Nor are the tests indicative of the initial compaction of the top six inches as this is the part that would be most affected by climatic conditions.

The burden of proof is upon the Contractor (plaintiff) to establish by a preponderance of the evidence that he is entitled to the relief sought. This he has failed to do.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cr Humphreys General Contractor, Inc. v. Tangipahoa Parish School System
973 So. 2d 178 (Louisiana Court of Appeal, 2007)
Abraham v. Greater Baton Rouge Consolidated Sewerage District
162 So. 2d 15 (Supreme Court of Louisiana, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
159 So. 2d 525, 1963 La. App. LEXIS 2226, Counsel Stack Legal Research, https://law.counselstack.com/opinion/abraham-v-greater-baton-rouge-consolidated-sewerage-district-lactapp-1963.