C.R. Batts Const. v. 101 Construction Co.

CourtCourt of Appeals of Tennessee
DecidedApril 23, 2001
DocketM2004-00322-COA-R3-CV
StatusPublished

This text of C.R. Batts Const. v. 101 Construction Co. (C.R. Batts Const. v. 101 Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C.R. Batts Const. v. 101 Construction Co., (Tenn. Ct. App. 2001).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE MARCH 3, 2005 Session

C. R. BATTS CONSTRUCTION, LLC v. 101 CONSTRUCTION COMPANY, ET AL.

Direct Appeal from the Circuit Court for Rutherford County No. 45736 J. S. Daniel, Judge

No. M2004-00322-COA-R3-CV - Filed August 4, 2005

This appeal arises out of a breach of contract action filed by the plaintiff against the defendants. After a hearing, the trial court entered a judgment in favor of the plaintiff, awarding the plaintiff $24,260.11. Additionally, the trial court awarded the plaintiff pre-judgment interest in the amount of $5,579.82. The defendants have appealed to this Court. We affirm the judgment of the trial court.

Tenn. R. App. P. 3; Appeal as of Right; Judgment of the Circuit Court Affirmed

ALAN E. HIGHERS, J., delivered the opinion of the court, in which DAVID R. FARMER , J., and HOLLY M. KIRBY, J., joined.

Henry Haile, Nashville, TN, for Appellant

John W. Rodgers, Murfreesboro, TN, for Appellee

OPINION

Facts and Procedural History

C.R. Batts Construction, LLC (“C.R. Batts” or “Appellee”) and 101 Construction Company (“101 Construction”) entered into a subcontract agreement on April 23, 2001, wherein C.R. Batts agreed to prepare a site upon which Murfreesboro Fire Hall #11 (“Fire Hall”) was to be constructed in Murfreesboro, Rutherford County, Tennessee. Specifically, 101 Construction, the general contractor for the project, employed C.R. Batts, the subcontractor, to excavate and remove portions of mass and trench rock and grade the site so that construction of the Fire Hall could commence. The terms of the contract included a flat fee of $37,776.001 plus an additional $20 per cubic yard of mass rock removed and $75 per cubic yard of trench rock removed. During the course of performance, 101 Construction made four payments on June 8, July 13, November 16, and December 24, 2001, of $4,500.00, $10,660.50, $3,053.14, and $5,966.79, respectively, for a total of $24,180.43.

During the excavation, Verlon Gill (“Gill”), an operator of heavy equipment for C.R. Batts, recorded on each work day the dimensions of the rock areas excavated. Disputes arose between the parties concerning the amount due to C.R. Batts, and, as a result, C.R. Batts temporarily ceased work on two occasions in July and September 2001. In June and July 2001, Judy Stanley (“Stanley”), the office manager for C.R. Batts, was temporarily unable to work, and, as a result, another employee for C.R. Batts, Tim West (“West”), prepared the invoices and sent them to 101 Construction, listing the quantities of trench and mass rock removed. West mistakenly listed the amount of trench rock removed on two invoices, and, as a result, Stanley prepared a corrected invoice in August 2001, listing the proper current amounts of trench and mass rock excavated, and sent this invoice to 101 Construction, effectively cancelling the prior two mistaken invoices. Finally, in December 2001, while C.R. Batts was laying topsoil, the ground froze, and, at this point, 101 Construction terminated the contract before C.R. Batts could resume and complete the project. After terminating the agreement with C.R. Batts, 101 Construction hired two other companies to spread the topsoil, perform the final grading, and clean the site.

On November 13, 2001, C.R. Batts filed a complaint against 101 Construction and Travelers Casualty and Surety Company of America (“Travelers Casualty” or collectively with 101 Construction, the “Appellants”),2 alleging breach of contract for failure to pay monies due under the contract for labor performed and equipment furnished. C.R. Batts alleged that it excavated 689 cubic yards of mass rock and 99.6 cubic yards of trench rock. Travelers Casualty and 101 Construction denied these amounts excavated and counterclaimed, seeking damages in the form of fees for professionals to determine the amount of rock excavated and attorney’s fees pursuant to the contract. The trial court entered a judgment in favor of C.R. Batts and awarded it $24,260.11 plus pre- judgment interest in the amount of $5,579.82. Travelers Casualty and 101 Construction now appeal to this Court and present the following issues,3 as we perceive them, for our review:

1 Before a hearing, the parties stipulated that, after C.R. Batts began work, the contract price was changed on three occasions: first, it was reduced by $12,518.00, then increased b y $1,2 79.1 4, and finally, increased again by $6 55.0 0. As su ch, the final flat fee for the contra ct between the parties is $27 ,192 .14.

2 Travelers Casualty is the surety for 101 Construction and delivered a bond to the City of Murfreesboro for the p rotection of p erson s supp lying labo r and materials for the work listed in the contra ct at issue.

3 Appellants also state in the sum mary o f their argument that “the general contractor is entitled to a set off for [sic] $4052 .22 for expenses necessary to complete the work.” This conclusory statement asking this Court to require a setoff appears in the summary of the argument, the statement of the issues, an d in the conclusion. The App ellants’ brief does not address this issue in their argument or otherwise follow our rules of court or the rules of app ellate procedure. See Tenn. R. App. P. 27(a)(7) (2005); Tenn. Ct. App. R. 6(a) (2005). Appellant also did not (continued...)

-2- I. Whether the evidence supports the trial court’s judgment awarding C.R. Batts $24,260.11; and II. Whether the trial court abused its discretion when it awarded C.R. Batts $5,579.82 as pre-judgment interest.

For the following reasons, we affirm the judgment of the trial court.

Standard of Review

In a civil suit, we review the findings of fact of a trial court judge, sitting without a jury, de novo on the record affording those findings a presumption of correctness, unless the preponderance of the evidence is otherwise. Tenn. R. App. P. 13(d) (2005). When a trial court has failed to make specific findings of fact, we must review the record to determine the preponderance of the evidence. Ganzevoort v. Russell, 949 S.W.2d 293, 296 (Tenn. 1997) (citing Kemp v. Thurmond, 521 S.W.2d 806, 808 (Tenn. 1975)). However, we recognize that certain findings of fact are implicit in the trial court’s rulings, and we review these implicit findings of fact de novo on the record affording these findings a presumption of correctness. Hollingsworth v. Hollingsworth, No. 02A01-9103-CV- 00043, 1991 Tenn. App. LEXIS 848, at *6 (Tenn. Ct. App. Oct. 31, 1991). We review questions of law de novo on the record affording the trial court’s decisions no presumption of correctness. Union Carbide Corp. v. Huddleston, 854 S.W.2d 87, 91 (Tenn. 1993) (citing Estate of Adkins v. White Consol. Indus., Inc., 788 S.W.2d 815, 817 (Tenn. Ct. App. 1989)).

Quantity of Rock Removed

Appellants argue that Appellee’s proof of the quantity of rock removed was unpersuasive and uncertain. Appellants contend that the testimony of their expert, Michael Williams (“Williams”), a licensed land surveyor, establishes that the amount of trench and mass rock excavated by Appellee is much lower than Appellee asserts.

As an initial matter, Appellants argue that the trial court failed to make a factual finding regarding the quantity of rock removed from the work site. As such, Appellants argue that this Court should review the record de novo and determine where the preponderance of the evidence lies. We disagree.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Win Myint and wife Patti KI. Myint v. Allstate Insurance Company
970 S.W.2d 920 (Tennessee Supreme Court, 1998)
Ganzevoort v. Russell
949 S.W.2d 293 (Tennessee Supreme Court, 1997)
Bean v. Bean
40 S.W.3d 52 (Court of Appeals of Tennessee, 2000)
Mitchell v. Archibald
971 S.W.2d 25 (Court of Appeals of Tennessee, 1998)
Blair v. Badenhope
940 S.W.2d 575 (Court of Appeals of Tennessee, 1996)
Kemp v. Thurmond
521 S.W.2d 806 (Tennessee Supreme Court, 1975)
Unlimited Equipment Lines, Inc. v. Graphic Arts Centre, Inc.
889 S.W.2d 926 (Missouri Court of Appeals, 1994)
Bowman v. Bowman
836 S.W.2d 563 (Court of Appeals of Tennessee, 1991)
Union Carbide Corp. v. Huddleston
854 S.W.2d 87 (Tennessee Supreme Court, 1993)
Otis v. Cambridge Mutual Fire Insurance Co.
850 S.W.2d 439 (Tennessee Supreme Court, 1993)
State v. Grear
568 S.W.2d 285 (Tennessee Supreme Court, 1978)
Community State Bank Royal Center v. O'Neill
553 N.E.2d 174 (Indiana Court of Appeals, 1990)
Wells v. Tennessee Board of Regents
9 S.W.3d 779 (Tennessee Supreme Court, 1999)
Spencer Ex Rel. Spencer v. A-1 Crane Service, Inc.
880 S.W.2d 938 (Tennessee Supreme Court, 1994)
Bingham v. Dyersburg Fabrics Co., Inc.
567 S.W.2d 169 (Tennessee Supreme Court, 1978)
Textile Workers Union, Local No. 513 v. Brookside Mills, Inc.
326 S.W.2d 671 (Tennessee Supreme Court, 1959)
Humphrey v. David Witherspoon, Inc.
734 S.W.2d 315 (Tennessee Supreme Court, 1987)
Mitchell v. Mitchell
876 S.W.2d 830 (Tennessee Supreme Court, 1994)
State v. Pruett
788 S.W.2d 559 (Tennessee Supreme Court, 1990)
Estate of Adkins v. White Consolidated Industries, Inc.
788 S.W.2d 815 (Court of Appeals of Tennessee, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
C.R. Batts Const. v. 101 Construction Co., Counsel Stack Legal Research, https://law.counselstack.com/opinion/cr-batts-const-v-101-construction-co-tennctapp-2001.