Covenant Mutual Insurance v. Able Concrete Pump

609 F. Supp. 27, 1984 U.S. Dist. LEXIS 24808
CourtDistrict Court, N.D. California
DecidedJuly 25, 1984
DocketC-83-0986 WHO
StatusPublished
Cited by1 cases

This text of 609 F. Supp. 27 (Covenant Mutual Insurance v. Able Concrete Pump) is published on Counsel Stack Legal Research, covering District Court, N.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Covenant Mutual Insurance v. Able Concrete Pump, 609 F. Supp. 27, 1984 U.S. Dist. LEXIS 24808 (N.D. Cal. 1984).

Opinion

OPINION AND ORDER

ORRICK, District Judge.

The sole issue left to be decided in this action is whether a surety for both payment and performance bonds on a government contract who completes performance for the defaulting contractor and also deposits the full amount of the payment bond with the court is entitled to sums retained by the government from the original contractor’s progress payments even though the payment bond does not fully compensate that contractor’s subcontractors. For the reasons set forth herein, plaintiff surety in this case is a subrogee of the government and has an equitable right to the retainages.

I

On November 16, 1981, Joel-Li Construction Company (“Joel-Li”) entered into a contract with the United States government to construct a research facility for

*29 NASA at the Ames Research Center in Mountain View, California. The total contract price of $1,312,000 was amended by change orders to $1,334,285. Payment and performance bonds, as required by the Miller Act, 40 U.S.C. § 270a 1 , were executed by Joel-Li as principal and plaintiff, Covenant Mutual Insurance Company (“Covenant”), as surety. The liability limit on the payment bond was $524,800. 2 The liability limit on the performance bond was $1,180,-000. The contract between the government and Joel-Li provided that 10 percent of each progress payment be retained by the government. This is a standard provision in government contracts. The sums retained are commonly referred to as “contract retainages”.

Joel-Li defaulted on January 19, 1983, having completed work with a value of $1,246,165. To that date, the government had paid $1,180,565 to Joel-Li and had retained the balance of $65,600. Pursuant to a Takeover Agreement, dated February 2, 1983, Covenant completed the contract, which it had the option to do under its performance bond. After Covenant took over, additional change items were issued totalling $45,374.99, increasing the total contract price to $1,379,659.99. Subtracting the amount previously paid to Joel-Li, this left $199,094.99 to cover the cost of the work: $133,494.99 as the balance of the contract and $65,600 in prior retainages. Covenant spent $238,548.03 to complete the project. Thus, Covenant suffered financial losses, even if it is entitled to the retainages.

On March 2, 1983, Covenant filed an interpleader action and paid $524,800, the full sum of its obligations under the payment bond, into the Court. The defendants are creditors of the contractor, Joel-Li, i.e., subcontractors who have not been paid. The payment bond is designed to pay them. During the first hearing the creditors organized themselves. A Creditors’ Committee was formed to oversee their interests and to accept and review claims on the payment bond. On April 20, 1983, an Order re Interpleader submitted by the Creditors’ Committee was filed.

Paragraph 8 of that Order provided that the preliminary report of the Committee would contain a recommendation as to whether plaintiff should be discharged from further liability. The Court approved the preliminary report of the Committee at a December 2,1983, hearing. At that time, the parties suggested that the Court postpone ruling on the issue of who is entitled to retainages until it could be determined whether the interpleaded payment bond fund would be sufficient to satisfy all bona fide claims. Unfortunately, it was not sufficient to cover all claims approved for disbursement by the Committee. After a pro rata distribution among approved claims, *30 each claimant will recover approximately 67 percent of its claim.

II

Contracts for construction of a government building are subject to the provisions of the Miller Act, 40 U.S.C. §§ 270a-270d. This Act requires parties contracting with the government to secure two bonds: a performance bond and a payment bond. If the original bonded contractor fails to complete performance, the performance bond surety must either complete performance or reimburse the government for its completion costs, minus retainages. A payment bond surety must pay laborers and materialmen whom the bonded contractor failed to pay. 3 The issue in this case is whether a surety for both performance and payment, who has completed performance at a cost greater than the balance owing on the contract and who has deposited the full amount of the payment bond with the court, is entitled to retainages even though the laborers and materialmen will not be fully reimbursed by the amount of the payment bond.

The defendant subcontractors attempt to characterize the bonds in this case as one bond. But the Miller Act was enacted to provide a separate bond for laborers and materialmen. 4 United States v. Munsey Trust Co., 332 U.S. 234, 243, 67 S.Ct. 1599, 1603, 91 L.Ed. 2022 (1947). See also United States ex rel. James E. Simon Co. v. Ardelt-Hom Construction Co., 446 F.2d 820, 821 (8th Cir.1971) (“[T]he Miller Act by its clear language, which is fully supported by the legislative history, provides for a payment bond for protection of those providing labor and material on government projects and a performance bond for the protection of the United States”). Furthermore, the defendants agreed to discharge plaintiff from its obligations under the payment bond, implicitly recognizing that the two are separate.

Several parties may be entitled to assert equitable liens against sums retained by the government during the course of performance. The priority of rights to such retainages has been adjudicated in a variety of contexts, but the Court is aware of no authority that squarely addresses the issue presented by this case. In all the reported cases, a surety has performed on one bond or the other; in this case the plaintiff has performed on both.

Covenant claims entitlement to the retainages because it completed the contract under its performance bond. Under the theory of equitable subrogation, one who pays the debts or fulfills the duties of another steps into the shoes of that party and is entitled to the securities and remedies of that party. Defendants contend that unpaid laborers and materialmen have a prior equitable claim, and argue that a surety is not entitled to equitable subrogation unless and until the laborers and materialmen are paid in full. • '

A surety who completes performance has an “equitable right” to indemnification out of a retained fund superior to the right of a bank that loaned the defaulting contractor money. Prairie State Bank v. United States, 164 U.S. 227, 17 S.Ct. 142, 41 L.Ed.2d 412 (1896). A surety is also entitled to retainages when it pays laborers and materialmen although the contractor has completed the contract. Hen

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Ex Rel. Gray Road Fill, Inc. v. Wray
673 N.E.2d 198 (Ohio Court of Appeals, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
609 F. Supp. 27, 1984 U.S. Dist. LEXIS 24808, Counsel Stack Legal Research, https://law.counselstack.com/opinion/covenant-mutual-insurance-v-able-concrete-pump-cand-1984.