Covanta Maine, LLC v. Public Utilities Commission

2012 ME 74, 44 A.3d 960, 2012 WL 1994832, 2012 Me. LEXIS 74
CourtSupreme Judicial Court of Maine
DecidedJune 5, 2012
DocketDocket: PUC-11-36
StatusPublished
Cited by4 cases

This text of 2012 ME 74 (Covanta Maine, LLC v. Public Utilities Commission) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Covanta Maine, LLC v. Public Utilities Commission, 2012 ME 74, 44 A.3d 960, 2012 WL 1994832, 2012 Me. LEXIS 74 (Me. 2012).

Opinions

JABAR, J.

[¶ 1] Covanta Maine, LLC (Covanta), a subsidiary of Covanta Energy, appeals from orders of the Public Utilities Commission (Commission) denying Covanta’s requests for certification of two of its facilities as Class I new renewable resources pursuant to 35-A M.R.S. § 3210 (2010)1 [961]*961and 9 C.M.R. 65 407 311-1 to -2 § 3 (2008). Covanta argues that the Commission erred by basing its conclusion that the facilities were not refurbished on the ratio of Covanta’s expenditures in the facilities to the value of those facilities, and it therefore asserts that the Commission improperly denied certification of its two facilities. For the reasons set forth in this opinion, we agree that the Commission improperly denied certification.

I. BACKGROUND

[¶ 2] In 2007 the Legislature enacted the Act to Stimulate Demand for Renewable Energy, P.L.2007, ch. 403, codified at 35-A M.R.S. § 3210, requiring competitive electricity providers to obtain a percentage of their electricity offered at retail to Maine’s consumers from “new” renewable capacity resources. 35-A M.R.S. § 3210(3-A). The statutory portfolio standards require each competitive electricity provider to increase the amount of new renewable capacity resources in its portfolio by one percent every year. Id. § 3210(3-A)(A). Specifically, the Act requires that in 2008, new renewable capacity resources make up at least 1% of the electricity provider’s portfolio and that by 2017, new renewable capacity resources make up at least 10% of its portfolio. Id. § 3210(3-A)(A)(1), (10). Generally, new renewable capacity resources are facilities that began service, were added to an existing facility, resumed operation, or were refurbished after September 1, 2005. 35-A M.R.S. § 3210(2)(B-4). The statute states, in relevant part:

B-4. “New” as applied to any renewable capacity resource means a renewable capacity resource that:
(1) Has an in-service date after September 1, 2005;
(2) Was added to an existing facility after September 1, 2005;
(3) For at least 2 years was not operated or was not recognized by the New England independent system operator as a capacity resource and, after September 1, 2005, resumed operation or was recognized by the New England independent system operator as a capacity resource; or
(4) Was refurbished after September 1, 2005 and is operating beyond its previous useful life or is employing an alternative technology that significantly increases the efficiency of the generation process.

35-A M.R.S. § 3210(2)(B^4).

[¶ 3] The Commission modified its rules to conform with the statute, including adding a provision that requires generators to pre-certify facilities as new renewable resources. 9 C.M.R. 56 407 311-2 § 3(B)(4) (2008). This provision allows the Commission to resolve whether a facility satisfies one of the vintage requirements of section 3210(2)(B-4) on a case-by-case basis. See Order Adopting Rule and Statement of Actual and Policy Basis, No. 2007-391, Order at 6 (Me.P.U.C. Oct. 22, 2007). Per the requirements set forth in the Commission’s rules, on June 10, 2010, Covanta submitted an application for certification of its West Enfield biomass plant as a Maine Class I new renewable resource. See 9 C.M.R. 65 407 311-2 § 3(B)(4) (2008). Two weeks later, on June 24, 2010, Covanta submitted an application seeking the same certification for its biomass plant in Jonesboro. Both applications asserted that the facilities’ resource type was “biomass generator” and their [962]*962vintage category was “refurbished” pursuant to section 3210(2)(B-4)(4). See 9 C.M.R. 65 407 311-2 § 3(B)(1)(g), (3)(d) (2008).

[¶ 4] Specific to the issue of refurbishment, Covanta explained that each facility was operating beyond its twenty-year useful life due to investments made after September 1, 2005. The Jonesboro and West Enfield plants were first-of-a-kind circulating fluidized bed combustion biomass-fired plants that, according to Co-vanta, were redesigned and improved to “maximize combustion efficiency and extend the boiler’s useful life beyond 20 years.” Since September 1, 2005, Covan-ta, together with the facilities’ previous owners,2 has expended $3,969,515 on its West Enfield facility and $6,097,522 on its Jonesboro facility for “design changes, material upgrades[,] and capital expenditures.” After receiving a protective order from the Commission, Covanta submitted a list of these expenditures, identifying the kind of refurbishment project, the previous useful life of each item, the age of the item at the time of the expenditure, the item’s estimated new useful life, and the total cost of each expenditure.

[¶ 5] In October 2010 the Commission requested information on the accounting and tax treatment of the listed expenditures, specifically inquiring whether the items were capitalized or expensed. Although the record does not include tax returns for Covanta, Ridgewood, or In-deck, the record does contain a document submitted to the Commission by Covanta indicating the manner in which the expenditures were treated on Covanta’s tax returns and Indeck’s financial records. This document indicated that for the years 2009 and 2010, the years that Covanta owned the facilities, about 51.1% of the expenditures at the West Enfield facility and 78.5% of the expenditures at the Jonesboro facility were capitalized on Covanta’s tax returns. The document also summarized the information contained in the accounting records submitted to the Securities and Exchange Commission by Indeck relating to expenditures for the years 2006 and 2007, the years that Indeck owned the facilities. These records indicate that the value of Indeck’s non-current assets increased by $2,139,000 in 2006 and by $602,000 in 2007.

[¶ 6] In November 2010, after reviewing Covanta’s applications and the confidential list of major refurbishment projects, the Commission issued orders denying certification to both the West Enfield and Jonesboro facilities on the basis that these facilities did not satisfy the vintage requirement. The Commission determined that, although the facilities were built in 1986 and are operating beyond their previous useful lives, neither facility had been refurbished within the meaning of section 3210(2)(B— 4) (4).

[¶ 7] The Commission stated, in making its determination that the facilities were not refurbished, that “it is appropriate to consider whether investments in the facility were routine maintenance items or refurbishment investments.” The Commission made this determination in two ways. First, the Commission examined Covanta’s tax treatment of its expenditures and determined that a number of the projects listed by Covanta were expensed rather than capitalized, and therefore concluded that the expensed items were more representative of maintenance-type activi[963]*963ties rather than refurbishment projects. The only evidence before the Commission relevant to this determination was the documentation from Covanta indicating that, for 2009 and 2010, 51.1% of the expenditures for the West Enfield facility and 78.5% of the expenditures for the Jones-boro facility were capitalized.

[¶ 8] The Commission also compared the total expensed and capitalized expenditures to the facilities’ 2008 value.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eno v. Town of Bar Harbor
Maine Superior, 2020
Fuhrmann v. Staples the Office Superstore East, Inc.
2012 ME 135 (Supreme Judicial Court of Maine, 2012)
Covanta Maine, LLC v. Public Utilities Commission
2012 ME 74 (Supreme Judicial Court of Maine, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
2012 ME 74, 44 A.3d 960, 2012 WL 1994832, 2012 Me. LEXIS 74, Counsel Stack Legal Research, https://law.counselstack.com/opinion/covanta-maine-llc-v-public-utilities-commission-me-2012.