County of Vernon v. United States

933 F.2d 532, 1991 WL 84655
CourtCourt of Appeals for the Seventh Circuit
DecidedMay 24, 1991
DocketNo. 90-3184
StatusPublished
Cited by12 cases

This text of 933 F.2d 532 (County of Vernon v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
County of Vernon v. United States, 933 F.2d 532, 1991 WL 84655 (7th Cir. 1991).

Opinion

RIPPLE, Circuit Judge.

The County of Vernon and its co-plaintiffs (the County) brought an action against the United States Army Corps of Engineers (the Corps) to compel completion of the LaFarge Dam Project (the Project). Because no funding existed to complete the Project and because various actions undertaken by the Corps were beyond the court’s jurisdiction, the district court granted the Corps’ motion for summary judgment. For the following reasons, we affirm the judgment of the district court.

I

BACKGROUND

The Flood Control Act of 1962, Pub.L. 87-874, 76 Stat. 1173, authorized the Corps to proceed with the Project on the Kickapoo River, Wisconsin. Pursuant to this authorization, the Corps developed a plan that would provide flood control and recreational benefits to the area. The estimated cost of the Project approximated $15,570,-000. Between 1968 and 1971, the Corps acquired several thousand acres in Vernon County, Wisconsin, for the Project. Physical construction of the dam began in 1971 and continued until 1975, when the governor and congressional representatives for the State of Wisconsin withdrew their support for the Project. At least in part because of this change in political climate, the Corps ceased construction on the Project and recommended to Congress that the Project not receive additional funding.

Congress has not appropriated funds for further construction since fiscal year 1977. In that year, the Presidential Review of Water Resource Projects also issued a recommendation that the Project not be further funded. In 1983, however, Congress did appropriate funds for a special report on the status of the Project. This report, presented to Congress in 1984, concluded that the Project lacked economic justification. Despite opposition from several local municipalities, Congress subsequently enacted legislation allowing for the eventual deauthorization of the Project.

The County brought an action that sought declaratory and injunctive relief in an attempt to compel completion of the Project. The district court denied the Corps’ motion to dismiss for lack of subject matter jurisdiction and for failure to state a claim upon which relief could be granted, holding that the County would have a cognizable claim if it could prove that the Corps had failed to complete the Project despite receiving congressional funding. The court later granted the Corps’ motion [534]*534for summary judgment after the court determined that it was undisputed that Congress had failed to appropriate funds for construction of the Project since 1977. Further, the district court concluded that actions challenged by the County as arbitrary and capricious were beyond the court’s jurisdiction.

II

ANALYSIS

We review de novo the entry of summary judgment by the district court. See Renovitch v. Kaufman, 905 F.2d 1040, 1044 (7th Cir.1990). Summary judgment should be granted only if there remains no genuine issue as to any material fact and the moving party is entitled to judgment as a matter of law. Fed.R.Civ.P. 56(c). To preclude summary judgment, the non-moving party must show that a genuine issue exists over a material fact. It “may not rest upon mere allegation or denials of [its] pleadings, but must set forth specific facts showing that there is a genuine issue for trial.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 256-57, 106 S.Ct. 2505, 2514, 91 L.Ed.2d 202 (1986); see also Renovitch, 905 F.2d at 1045. A genuine issue of material fact exists only when there is sufficient evidence favoring the non-moving party for a jury to return a verdict for that party. See Wolf v. City of Fitchburg, 870 F.2d 1327, 1329 (7th Cir.1989).

The County argues that the trial court incorrectly concluded that no material factual dispute existed between the parties. Instead, the County contends that a factual question remains: whether the Corps had sufficient funding to complete the Project. The County asserts that the trial court mistakenly relied upon the Corps’ vague and unsupported assurances that no funds existed and ignored the Corps’ documentation that demonstrates the ready availability of funds. The Corps counters that nothing in the record indicates that funds have ever been appropriated for completion of the Project.

In its complaint, the County alleged that the Corps had failed to complete the Project — a nondiscretionary duty for which funding was available. In granting summary judgment, however, the district court found it undisputed that Congress had failed to appropriate funds for completion of the Project. The record fully supports the district court’s conclusion. As the district court noted, the affidavit of Mr. Kursu, the Corps’ Chief of Program Management for the St. Paul District, explicitly stated that no funding has been appropriated for the Project since 1977. Mr. Kursu also indicated that Congress has never appropriated sufficient funding to complete the Project.1

The County does not challenge directly the accuracy of Mr. Kursu’s statements. Instead, the County merely repeats the assertion contained in its complaint that the Project possessed “sufficient funds available for completion.” To support this contention, the County points to the Corps’ own documents as allegedly demonstrating the availability of funds. These documents, however, do not suggest that Congress has appropriated funds for completion of the Project. Rather, they demonstrate that congressional appropriations fell short of the dollar amount listed in the original program authorization. This will not preclude the grant of summary judgment.

The Flood Control Act of 1962 created an account from which the Corps could draw [535]*535funds should Congress decide to appropriate funding. See Environmental Defense Fund v. Froehlke, 473 F.2d 346, 353-55 (8th Cir.1972). Legislation authorizing a Project does not constitute an appropriation of public monies, but rather contemplates future action by Congress to provide funding. 37 Comp.Gen. 306 (1955). Therefore, the Corps could not continue with construction on the Project absent continuing appropriations from Congress. Regardless of the amount specified in the program authorization, Congress has not appropriated sufficient funds to complete the Project. Thus, we agree that the lack of funding precluded the Corps from completing the Project.

The decision of Congress not to appropriate funds for a particular Project normally is not reviewable by the judiciary. See, e.g., Oklahoma ex rel. Phillips v. Guy F. Atkinson Co., 313 U.S. 508, 527, 61 S.Ct. 1050, 1060, 85 L.Ed. 1487 (decisions whether to fund particular projects “raise not constitutional issues but questions of policy. [Such questions] relate to the wisdom, need, and effectiveness of a particular project. They are therefore questions for the Congress, not the courts.”).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brown v. Runyon
2 F. Supp. 2d 1062 (N.D. Illinois, 1998)
Ruiz v. Stewart Associates, Inc.
171 F.R.D. 238 (N.D. Illinois, 1997)
Door Systems, Inc. v. Overhead Door Systems, Inc.
905 F. Supp. 492 (N.D. Illinois, 1995)
Jones v. Officer Banks
878 F. Supp. 107 (N.D. Illinois, 1995)
Salima v. Scherwood South, Inc.
866 F. Supp. 1125 (N.D. Indiana, 1994)
Hickey v. A.E. Staley Manufacturing
995 F.2d 1385 (Seventh Circuit, 1993)
Bray Ex Rel. Bray v. Hobart City School Corp.
818 F. Supp. 1226 (N.D. Indiana, 1993)
County Of Vernon v. United States
933 F.2d 532 (Seventh Circuit, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
933 F.2d 532, 1991 WL 84655, Counsel Stack Legal Research, https://law.counselstack.com/opinion/county-of-vernon-v-united-states-ca7-1991.