County of Bexar v. Santikos

144 S.W.3d 455, 47 Tex. Sup. Ct. J. 1010, 2004 Tex. LEXIS 736, 2004 WL 1908328
CourtTexas Supreme Court
DecidedAugust 27, 2004
Docket03-0471
StatusPublished
Cited by60 cases

This text of 144 S.W.3d 455 (County of Bexar v. Santikos) is published on Counsel Stack Legal Research, covering Texas Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
County of Bexar v. Santikos, 144 S.W.3d 455, 47 Tex. Sup. Ct. J. 1010, 2004 Tex. LEXIS 736, 2004 WL 1908328 (Tex. 2004).

Opinion

Justice BRISTER

delivered the opinion of the Court.

In this condemnation action, we again address whether severance damages are recoverable when property is taken as a part of a project to raise a roadway above the natural grade. The question is a recurring one, 1 as the growth of controlled-access highways necessarily requires that, at intersections with other major arteries, one road or the other must change grades.

This case presents the issue in a new context — a roadway on the edge of the Texas Hill Country. As the name indicates, the region is not flat, and some properties are necessarily higher than others. Building a highway along the contours of every hill and dale would leave every property at grade level, but at considerable difficulty, discomfort, delay, and danger to the traveling public.

In this case, a sliver of property was taken for an embankment to support the elevation of a frontage road above an occasional creekbed. The question presented is whether lost market value of the remainder property is compensable because it is now well below the frontage road. The trial court held that it is, and the court of appeals affirmed. 2 We hold under the facts of this case that it is not, and thus reverse the court of appeals’ judgment.

I

John L. Santikos owns a 27-acre tract of raw, unimproved land in northwest Bexar County, Texas. For about 2,000 feet, the property fronts Loop 1604 near its intersection with Portranco Road. As part of a project to widen Loop 1604, Bexar County *458 sought to acquire 0.485 acres of the property, an irregular-shaped strip about 850 feet long and decreasing from 25 to zero feet wide.

The 27-acre tract slopes downhill from south to north, with 5 acres on the north side located in the 100-year flood plain of Caracol Creek. As part of plans for constructing a northbound frontage road on the existing right-of-way, the Texas Department of Transportation plans to raise the roadbed along 215 feet of the lowest part of the Santikos tract, and plans to use the 0.485 acres to serve as a sloping embankment. 3 The northern part of the San-tikos tract is already 5 to 6 feet below the existing two lanes of Loop 1604; elevation of the frontage road will place parts of it 10 to 11 feet below the road surface. TxDOT does not plan to build any embankment along the remaining 1,785 feet of the tract fronting Loop 1604.

After attempts to buy the 0.485 acres failed, the County filed this condemnation action. Three special commissioners awarded $53,000 as compensation for the taking. 4 Santikos filed objections to the award, and requested a jury trial. 5

At trial, experts for both sides agreed the tract’s highest and best use was to hold it as an investment until population and traffic grew to support development for retail use. They disagreed a little on the value of the 0.485 acres taken, and disagreed a lot on the effect the taking would have on 3.5 acres of the remainder property abutting it.

According to experts for Santikos, the 3.5 acres will someday be occupied by “pad” users (banks, fast-food retailers, and the like), behind which will someday be a “big box” user (grocery store, home improvement warehouse, or the like). They testified the TxDOT plans would prevent normal driveways to this part of the tract, thus requiring longer access drives, moving pad users back, and preventing a “big box” at the back of the property. They also testified the embankment created a “market perception problem” for investors and developers, as this part of the property was now “in a hole.” These problems could be cured (they explained) only by adding 60,000 cubic yards of fill dirt (plus a retaining wall, guardrail, and drainage improvements) to raise the 3.5 acres skyward, at a cost between $719,801 and $928,302.

By contrast, the County’s witnesses concluded there was no damage to the remainder property, as it had the same elevation and utility before and after the taking. The County’s engineer testified that a commercial driveway with an acceptable slope could be built to the 3.5 acres anywhere on the southern third of its 215-foot frontage. It was undisputed safe driveways could be built along the remaining 1,785-foot frontage of the whole tract.

Over the County’s objections, the trial court instructed jurors that, in determining the diminution in fair market value of the 3.5 acres, they could “consider damages, if any, resulting from unsafe access or diminished market perception of the remainder,” but could not consider “damages resulting from diminished visibility or diminished access to the remainder.” The jury returned a verdict for Santikos for $400,000, and the trial court rendered *459 judgment for that amount less $53,000 (the commissioners’ award) deposited by the County and already withdrawn by Santi-kos.

The County appealed, and the court of appeals affirmed, holding that unsafe access and diminished market perception were appropriate grounds of recovery. 6 The County petitioned this Court for review, seeking a new trial because the damages alleged were not compensable. 7

II

The Texas Constitution requires governmental entities to compensate landowners adequately when property is taken for public use. 8 If a governmental entity condemns only part of a tract, adequate compensation is required for both the part taken and any resulting damage to the remainder. 9 Damages to remainder property are generally calculated by the difference between the market value of the remainder property immediately before and after the condemnation, considering the nature of any improvements and the use of the land taken. 10 In addition, the State must pay for special repair and mitigation costs that would not be reflected in the lost market value. 11

But not all damages to remainder property are compensable. 12 Whether damages can be recovered depends on what kind of damage is involved. 13 Com-pensability is a question of law for the court, and subject to de novo review. 14

We have considered the effects of highway-elevation and frontage-road projects on many occasions before. For example, in DuPuy v. City of Waco, we held a landowner suffered compensable loss from construction of an overpass that raised the street in front of his property 14 feet above grade, and left him on a cul-de-sac that could be accessed only by threading the supporting columns. 15 But in Archen-hold Automobile Supply Co. v. City of

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Houston v. Festival Properties, Inc.
Court of Appeals of Texas, 2025
City of Canton v. Lewis First Monday, Inc.
Court of Appeals of Texas, 2023
in the Estate of Wynell N. Klutts
Court of Appeals of Texas, 2019
State v. Gleannloch Commercial Development, LP
Court of Appeals of Texas, 2018
State v. Luby's Fuddruckers Restaurants, LLC
531 S.W.3d 810 (Court of Appeals of Texas, 2017)
in the Interest of K.I.B.C., a Child
Court of Appeals of Texas, 2015
in the Interest of A.G. and F.G., Children
Court of Appeals of Texas, 2015
in the Interest of S. R.- M. C.
Court of Appeals of Texas, 2015

Cite This Page — Counsel Stack

Bluebook (online)
144 S.W.3d 455, 47 Tex. Sup. Ct. J. 1010, 2004 Tex. LEXIS 736, 2004 WL 1908328, Counsel Stack Legal Research, https://law.counselstack.com/opinion/county-of-bexar-v-santikos-tex-2004.