Coughlan Construction Co. v. Town of Rockport

505 N.E.2d 203, 23 Mass. App. Ct. 994, 1987 Mass. App. LEXIS 1766
CourtMassachusetts Appeals Court
DecidedMarch 19, 1987
StatusPublished
Cited by7 cases

This text of 505 N.E.2d 203 (Coughlan Construction Co. v. Town of Rockport) is published on Counsel Stack Legal Research, covering Massachusetts Appeals Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coughlan Construction Co. v. Town of Rockport, 505 N.E.2d 203, 23 Mass. App. Ct. 994, 1987 Mass. App. LEXIS 1766 (Mass. Ct. App. 1987).

Opinion

In these actions consolidated in the Superior Court judgments were entered confirming an arbitration award dated August 17, 1982, in favor of Coughlan Construction Company; Inc. (Coughlan). Rockport appealed and Coughlan has filed a crpss appeal. We affirm.

Coughlan and Rockport made a contract on April 10, 1978, for sewer construction. This contract contained provisions for arbitration of disputes. A dispute arose while work was in progress and Coughlan (on July 30, 1979) filed a demand for arbitration with the American Arbitration Association (AAA). See the AAA Construction Industry Arbitration Rules § 13 (1979).

In August, 1979, AAA sent identical lists of possible arbitrators to Coughlan and Rockport, each- of which was to strike the names of those to whom that party objected. One or both of the parties objected to all but one of the names on the list submitted. AAA thereupon on a date (illegible in this record) prior to the end of November, 1979, appointed three arbitrators no one of whom had been on the lists earlier submitted to the [995]*995parties.2 Rockport offered no proof before the Superior Court that it (Rockport) had made objection to AAA’s appointment of the arbitrators prior to its filing on January 9, 1981, a complaint3 in the Superior Court for Essex County requesting, among other relief, a stay of arbitration. That complaint alleged (a) that Coughlan had failed to comply with the proper procedures for selecting arbitrators, and (b) that Coughlan and Rockport had abandoned the contract, thus making the arbitration provisions of the contract inapplicable. After Coughlan filed its answer, a Superior Court judge, on April 14, 1981, ordered the parties to proceed to arbitration of the claims made by Coughlan in July, 1979, some months before Coughlan had stopped work under the contract in December, 1979.

The arbitration started on September 28, 1981. Hearings were held from time to time until March 30, 1982. The arbitrators unanimously, on August 17, 1982, made an award to Coughlan of $271,811.

Rockport on September 20, 1982, filed a complaint in the Superior Court, Suffolk County, seeking to vacate the arbitrators’ award. Coughlan in a separate proceeding sought confirmation of the award. The actions were consolidated. A District Court judge, sitting by designation in the Superior Court, heard the consolidated cases on January 17, 1984, and filed findings and rulings on December 31, 1984. The present appeals are from the judgments entered pursuant to the judge’s findings and rulings in the consolidated actions.

1. Coughlan contends that the order of April 14, 1981, on the Essex County complaint compelling arbitration controlled determination of the validity of the arbitration provisions of the contract on principles of res judicata. The Essex County order, however, was not appealable. See G. L. c. 251, § 18; School Comm. of Agawam v. Agawam Educ. Assn., 371 Mass. 845, 846-847 (1977, arising under the substantially identical language of G. L. c. 150C, § 16). The issue is still open on appeal in the present proceeding now that confirmation of the award has taken place.

The contract contained a provision, par. 30.1,4 which under 40 C.F.R. § 35.938-8 (1978) and because this was a project funded in part by the [996]*996Federal government appears to control other arbitration provisions of the contract. The arbitrators were selected under this provision in accordance with AAA’s Construction Industry Arbitration Rules § 13 (1979). Rockport participated in this procedure without objection and must be taken to have accepted it by failing to object promptly.

2. Rockport also contends that the contract, including its arbitration provisions, was abandoned by the parties when Coughlan informed Rockport on December 6, 1979, that it could not complete the contract because of inability to obtain vital insurance. There is no indication that Coughlan was agreeing to a rescission of the contract because it was compelled by events to stop work. Coughlan had demanded in July, 1979, arbitration of disputes involving extra work, contract interpretation, and other matters. It persisted in doing so. See Riess v. Murchison, 384 F.2d 727, 733-735 (9th Cir. 1967). Coughlan in July had not stopped work because of the dispute but had proceeded with performance. In similar circumstances, no rescission of a broad arbitration provision has been found. County of Middlesex v. Gevyn Constr. Corp., 450 F.2d 53, 55-56 (1st Cir. 1971). See also A. Sangivanni & Sons v. Floryan & Co., 158 Conn. 467, 473 (1969). See and compare Mendez v. Trustees of Boston Univ., 362 Mass. 353, 356-357 (1972, where a teacher failed to appear at the beginning of an academic year for which she had been hired, and the court upheld as not plainly wrong a trial judge’s holding of abandonment of the contract); Computer Corp. of America v. Zarecor, 16 Mass. App. Ct. 456, 460-461 (1983, a confused situation leading to uncertainty whether certain persons, who had never rendered services under a contract, had been intended to be parties to the contract which contained an arbitration provision). We hold that the arbitration provisions were in effect when Rockport was ordered to proceed to arbitration on April 14, 1981.

3. Rockport contends that the award must be vacated because of a possible bias (a) of one arbitrator and (b) of the successor AAA tribunal administrator of the arbitration. The trial judge heard the evidence concerning these contentions fully and concluded that neither the arbitrator nor the second tribunal administrator did anything to taint the arbitration process. The judge found that Rockport had “failed to meet its burden of proof with respect to either” person and had “not provided the specific and direct evidence of fraud, corruption, undue influence, or partiality . . . necessary to overturn an arbitration ruling.”

As to the tribunal administrator, it was shown that he had not been employed by AAA until after the arbitrators had been selected, he did not attend the hearings, and made no attempt to influence the proceedings. His duties were purely administrative. Although the tribunal administrator later left the AAA and worked in the law office of Coughlan’s counsel, allegations concerning his having taken papers concerning this arbitration with him to that office could be found not to have been substantiated.

[997]*997With respect to the arbitrator, the trial judge found that he is an officer of a general contracting corporation, and is (or was) “a founder, treasurer, president, member of the board of directors, and life member of the Utility Contractors Association.” This arbitrator had nominated the attorney for Coughlan as general counsel to the association. Coughlan’s counsel had represented a company belonging to one of the arbitrator’s brothers in an action against the town of Duxbury and, in about half his practice, has represented construction industry clients. He also has contributed material for the association’s journal and has rendered legal advice to it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sheriff of Suffolk County v. Jail Officers & Employees of Suffolk County
990 N.E.2d 1042 (Massachusetts Supreme Judicial Court, 2013)
Northern Assurance Co. of America v. Payzant
952 N.E.2d 436 (Massachusetts Appeals Court, 2011)
Hiltz v. Whited
2008 Mass. App. Div. 245 (Mass. Dist. Ct., App. Div., 2008)
Weston Securities Corp. v. Aykanian
46 Mass. App. Ct. 72 (Massachusetts Appeals Court, 1998)
Barnstead v. Ridder
659 N.E.2d 753 (Massachusetts Appeals Court, 1996)
Sansone v. Metropolitan Property & Liability Insurance
572 N.E.2d 588 (Massachusetts Appeals Court, 1991)
Fort Hill Builders, Inc. v. National Grange Mutual Insurance
682 F. Supp. 145 (D. Rhode Island, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
505 N.E.2d 203, 23 Mass. App. Ct. 994, 1987 Mass. App. LEXIS 1766, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coughlan-construction-co-v-town-of-rockport-massappct-1987.