Couch v. Delmarva Power & Light Co.

593 A.2d 554, 1991 Del. Ch. LEXIS 66
CourtCourt of Chancery of Delaware
DecidedMarch 20, 1991
StatusPublished
Cited by8 cases

This text of 593 A.2d 554 (Couch v. Delmarva Power & Light Co.) is published on Counsel Stack Legal Research, covering Court of Chancery of Delaware primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Couch v. Delmarva Power & Light Co., 593 A.2d 554, 1991 Del. Ch. LEXIS 66 (Del. Ct. App. 1991).

Opinion

OPINION

ALLEN, Chancellor.

Delmarva Power & Light Company (“DP & L”) is presently installing a new 25 kilo-volt electrical transmission line along the easterly side of Route 10 in Appoquinimink Hundred, New Castle County. This work is supposedly being done within the State of Delaware highway right of way with the approval of the Delaware Department of Transportation (“DelDOT”). Plaintiffs own about 170 acres of farmland bordering the easterly side of Route 10. They bring this action against both DP & L and Del-DOT seeking an order requiring DP & L to halt such installation and to remove the poles and wires it has already installed.

Plaintiffs assert several theories in support of the relief they request. First, they contend that DelDOT’s grant of the franchise permitting this work is invalid because the Department did not, in considering that matter, take into consideration the mandated state policy of fostering and protecting farmland. See Agricultural Lands Preservation Act, 3 Del.C. § 901, et seq. (“the Act” or “ALPA”).

Second, plaintiffs assert that DP & L is installing these facilities not in the DelDOT right of way but on their property. Thus, they claim DP & L’s action constitutes a simple continuing trespass warranting in-junctive relief.

Third, plaintiffs claim that the 25kv electrical transmission line that DP & L is in the process of installing will interfere unreasonably with the use of their land; that is, that it is a nuisance. In particular plaintiffs assert that the 25kv lines in question will create electromagnetic fields that will be of the low-level non-ionizing type. These electromagnetic fields are not regulated by any governmental agency. Their effects, plaintiffs say may be linked “to birth defects and higher incidents of cancer” although plaintiffs admit that the evidence on this is “inconclusive.” Whatever the risks, plaintiffs contend, it is not reasonable that their farmland be subjected to them.

Finally, plaintiffs contend that DP & L’s franchise should be declared void and action pursuant to it enjoined because Del-DOT could not reasonably find, as its regulations required it to find in this instance, that to deny the franchise request would constitute an extreme hardship. Thus, plaintiffs assert that DelDOT actions were in violation of its own regulation, arbitrary and consequently legally void.

[[Image here]]

This action was commenced with an application for a temporary restraining order. That application was denied on February 22, 1991, and the matter was set down for a prompt hearing of a motion for preliminary injunction. It is that motion that is now pending.

*556 At the conclusion of the presentation of the application, preliminary injunctive relief was denied with respect to plaintiffs’ continuing trespass theory and their nuisance theory. With respect to both of those matters, any evaluation of the right to relief would require a clearer sense of underlying facts than the presently conflicting record would now permit. Thus, judicial action with respect to these theories must necessarily await trial. What remains for present consideration is an evaluation of plaintiffs’ two remaining theories which are not so thoroughly factual in nature.

I.

A sketch of the background facts will orient a discussion of these issues. Increased growth in lower New Castle County has required DP & L to upgrade and modify its present infrastructure in order to continue to assure consistent and reliable service in that region. The existing Townsend circuit is presently capable of meeting normal demand; however, in the event of the failure of an adjacent circuit, that circuit lacks the capacity to serve additional customer requirements that are emerging as a result of increased development. In 1988, DP & L had identified this as a potential problem and sought to alleviate it via interim measures such as replacing reclosers. Ultimately, these alternatives were exhausted, yet the outage level in southern New Castle County apparently remains at 3-V2 times that of the average DP & L customer.

As part of a larger plan to resolve outage problems in the Middletown, Odessa and Townsend areas, DP & L decided to upgrade its transmission lines along Route 10 (also known as Levels Road). Levels Road presently has a 69kv transmission line running along its western side. It appeared to DP & L to be uneconomical to utilize this existing line, however, because to do so would require the replacement of the existing poles with taller and thicker poles spaced at more frequent intervals in order to accommodate the increased weight of the new cables and to maintain vertical clearance between them and the existing lines. DP & L estimated that the cost of this alternative would be $950,328. DP & L also rejected the alternative of running the new lines underground because it would have involved more intrusive construction, longer outages as problems would be more difficult to locate, and significant additional expense. Installing the circuit underground would cost $769,672 plus an additional $16,000 to install a switch every time a new customer was added.

DP & L determined that the most feasible and flexible alternative would be to run another line along the easterly side of Route 10. Running a new line along the easterly side of the road would cost $112,-779. This plan, however, presented a problem with respect to DelDOT regulations. Section 18(a)(1) of the DelDOT Division of Highways Utility Manual provides:

A utility will not be issued a franchise or utility construction permit to place their facilities on both sides of a travelway, except in cases of extreme hardship. In cases of extreme hardship, a written request and justification shall be submitted to the District Engineer for his action,

(emphasis added).

On October 10, 1990, DP & L formally applied to the District Engineer for a franchise. On November 14, 1990, citing its “hardship” regulation, DelDOT requested additional documents and supplemental information that might justify extending a hardship exception. On November 21, 1990, DP & L provided DelDOT with additional information detailing the cost of alternatives. It contended that other alternatives had non-finance drawbacks, e.g., less flexibility and longer outages; and explained that the proposed project was the last in an integrated three-prong approach to improve service in southern New Castle County. It also indicated that the existing lines and poles were scheduled to be removed around 2004.

On November 30, 1990, DelDOT indicated it would grant the hardship request only subject to four conditions:

1) The existing transmission line on Levels Road was to be removed by 2004.
*557 2) The new line was to be with vertical construction and no crossarms and within one foot of the easterly edge of the right of way.
3) Additional spacing was required to decrease the number of poles. 1

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Evans v. Phelps
D. Delaware, 2023
Reylek v. Albence
Superior Court of Delaware, 2023
Dayton v. Collison
Superior Court of Delaware, 2019
Holland v. Zarif
794 A.2d 1254 (Court of Chancery of Delaware, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
593 A.2d 554, 1991 Del. Ch. LEXIS 66, Counsel Stack Legal Research, https://law.counselstack.com/opinion/couch-v-delmarva-power-light-co-delch-1991.