Corporación Mexicana de Mantenimiento Integral, S. de R.L. de C.V. v. PEMEX-Exploración y Producción

962 F. Supp. 2d 642, 2013 WL 4517225
District Court, S.D. New York·Decided August 27, 2013·No. No. 10 Civ. 206(AKH)·Published·Cited by 12 cases

Opinion

OPINION AND ORDER GRANTING PETITIONER’S MOTION TO CONFIRM ARBITRATION AWARD AND DENYING RESPONDENT’S MOTION TO DISMISS PETITION

ALVIN K. HELLERSTEIN, District Judge:

I. INTRODUCTION

Generally, arbitration awards issued in one nation can be enforced by judgments and executions granted by the courts of another nation. However, arbitration awards also can be nullified, and if nullified by the courts of the nation in which, or according to the law of which, the arbitration was conducted, a conflict is created for the courts of other nations. Which is to be given primacy, the award or the nullifying judgment?

This is the issue of the case; After a vigorously contested arbitration, a panel of arbitrators in Mexico City issued an award (the “Award”) in favor of petitioner, Corporación Mexicana de Mantenimiento Integral, S. de R.L. de C.V. (“COMMISA”). The Award, with interest, is now worth almost four hundred million U.S. dollars. COMMISA obtained judgment in this court confirming the Award. Respondent, PEMEX-Exploración y Production (PEP), an instrumentality of Mexico, continued to resist, appealing from the judgment to the Second Circuit of Appeals, and filing litigation proceedings in the Mexican courts to nullify the Award.

PEP was successful in the Mexican courts. On September 21, 2011, the Eleventh Collegiate Court on Civil Matters of the Federal District (the “Eleventh Collegiate Court,” generally equivalent in hierarchy and authority to the U.S. Court of Appeals for the D.C. Circuit) issued a 486-page decision that held that the Award was invalid. It reversed the Mexican district court, and remanded the case to it to issue a judgment in favor of PEP. On October 25, 2011, the district court issued such a judgment with its own 46-page opinion.

The Eleventh Collegiate Court held that arbitrators are not competent to hear and decide cases brought against the sovereign, or an instrumentality of the sovereign, and that proper recourse of an aggrieved commercial party is in the Mexican district court for administrative matters. Hence, it nullified the Award. The court based its decision in part on a statute that was not in existence at the time the parties’ entered their contract, [644] and the decision left COMMISA without the apparent ability to obtain a hearing on the merits of its case.

In response to that decision and its finality, the Second Circuit Court of Appeals remanded the case to me to address the effect that the decree of nullification should have on the Award and on my judgment confirming the Award. Following remand, I received further briefing from the parties, heard arguments on the complex issues that were presented, and conducted a three-day trial of the parties’ experts on Mexican law. This decision reflects my findings and conclusions.

I hold, for the reasons discussed below, that the Eleventh Collegiate Court decision violated basic notions of justice in that it applied a law that was not in existence at the time the parties’ contract was formed and left COMMISA without an apparent ability to litigate its claims. I therefore decline to defer to the Eleventh Collegiate Court’s ruling, and I again confirm the Award and grant judgment thereon.

II. FACTUAL AND PROCEDURAL BACKGROUND

a. The Parties and Their Agreements

Under the Political Constitution of the United Mexican States, all petroleum and hydrocarbons in Mexico belong to the state. State-owned Petróleos Mexicanos (“PEMEX”) controls and manages those resources, PEP, based in Mexico City, is the PEMEX subsidiary responsible for oil and natural gas exploration and production, COMMISA, a Mexican corporation, is a subsidiary of KBR, Inc., a construction company and military contractor incorporated in Delaware and headquartered in Houston, Texas.

In October 1997, PEP and COMMISA entered into a contract (the “October 1997 Contract”) for COMMISA to build and install two offshore natural gas platforms in the Bay of Campeche, in the southerly part of the Gulf of Mexico, Among other provisions, the October 1997 Contract includes: (i) a clause providing that the contract is governed by Mexican law;1 (ii) a clause providing for any dispute to be settled through arbitration conducted in Mexico City in accordance with the Conciliation and Arbitration Regulations of the International Chamber of Commerce (“ICC”);2 (iii) a clause allowing PEP to rescind the contract (i.e., issue an administrative rescission) if COMMISA failed to comply with certain obligations under the contract; 3 and (iv) a clause requiring COM[645] MISA to obtain a performance bond guaranteeing its contractual obligations.4

In May 2003, PEP and COMMISA entered into a related contract (the “May 2003 Contract” and together with the October 1997 Contract, the “Contracts”). Like the October 1997 Contract, the May 2003 Contract is governed by Mexican law and provides for both arbitration and administrative rescission by PEP. Ex. 4 at §§ 9.2,19.1,19.3.

The parties’ arbitration agreement was made pursuant to the PEMEX enabling statute, which also applied to PEP as a subsidiary of PEMEX. The Organic Law by which PEMEX was organized as a wholly-owned, government entity, contemplated the possibility of arbitration. Section 14 of the PEMEX and Affiliates Organic Law provides: “In the event of international legal acts, Petróleos Mexicanos or its Affiliates may agree upon the application of foreign law, the jurisdiction of foreign courts in trade matters, and execute arbitration agreements whenever deemed appropriate in furtherance of their purpose.” Ex. MMM at 443. The PEMEX law was passed following the enactment, in 1994, of the North American Free Trade Agreement (“NAFTA”), which sought to encourage investment in Mexico by providing for the arbitration of international disputes. See Evidentiary Hearing Tr. 39:4-25; North American Free Trade Agreement, U.S.-Can.-Mex., Dec. 17, 1992, 32 I.L.M. 289 (1993), art. 1115, 2022.

b. COMMISA’s Judicial Challenge to PEP’s Administrative Rescission

On March 29, 2004, after each party charged the other with breaching contractual obligations, PEP notified COMMISA that it intended to administratively rescind the Contracts. However, before doing so, PEP and COMMISA engaged in conciliation efforts, attempting to resolve their disputes amicably. On December 1, 2004, conciliation having failed, COMMISA filed a demand for arbitration with the ICC. Two weeks later, on December 16, 2004, PEP gave COMMISA notice that it was proceeding by administrative rescission.

Free access — add to your briefcase to read the full text and ask questions with AI

Corporación Mexicana de Mantenimiento Integral, S. de R.L. de C.V. v. PEMEX-Exploración y Producción, 962 F. Supp. 2d 642, 2013 WL 4517225 (S.D.N.Y. 2013).

962 F. Supp. 2d 642 (Corporación Mexicana de Mantenimiento Integral, S. de R.L. de C.V. v. PEMEX-Exploración y Producción) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related