Coos-Curry Electric Cooperative, Inc. v. Jura

821 F.2d 1341
CourtCourt of Appeals for the Ninth Circuit
DecidedJune 26, 1987
DocketNos. 85-7339, 86-7340
StatusPublished
Cited by5 cases

This text of 821 F.2d 1341 (Coos-Curry Electric Cooperative, Inc. v. Jura) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coos-Curry Electric Cooperative, Inc. v. Jura, 821 F.2d 1341 (9th Cir. 1987).

Opinion

STEPHENS, District Judge:

Facts

The Bonneville Power Administration (“BPA”) is a power marketing agency within the United States Department of Energy. The BPA markets electric power obtained primarily from hydroelectric generators at the sites of federal dams and delivers the power to its customers through its system of transmission lines. The BPA sells wholesale electric power to utilities, direct service industries, and government customers. Coos-Curry Electric Cooperative, Inc. (“CCEC”) is a cooperatively owned utility that buys most of its power from the BPA and resells that power to its members.

The BPA transmits power to utility customers at voltage levels ranging from 230 kV to 115 kV. The utilities distribute the power at 115 kV or lower. When there is a difference in voltage between the BPA’s transmission and a utility’s transmission, the power transmitted by the BPA must be transformed or “stepped” down to coincide with the utility’s lower voltage at the point of wholesale power delivery to the utility. The transformer required to lower the voltage can be owned and maintained by either the BPA or the utility.

In 1974, the BPA instituted and imposed a “transformation charge” on those utilities that used the BPA’s transformers to step down the BPA’s transmission voltage to accomodate the utilities’ voltage requirements. This charge was designed to recoup the BPA’s cost of transforming the power. Utilities that used their own transformers to step down the power were not charged. In 1979, the BPA decided to drop the transformation charge. The BPA learned that the cost to it of stepping down its transmission to the utilities’ distribution voltage was, in some instances, negligible. This fact led the BPA to conclude that the continued imposition of the transformation charge was not justified.

However, some utilities had purchased or built transformers in order to avoid the transformation charge. These utilities had incurred the cost of a transformer on the assumption that the charge would continue indefinitely. In response to this situation, the BPA created a program to provide mitigation relief to those utilities that had been financially harmed by their reliance on the assumed continuance of the transformation charge. Fourteen instances of possible reliance were identified. CCEC was identified as one of the utilities possibly eligible for mitigation relief.

Petitioner, CCEC, claims that it is entitled to monetary relief under the BPA’s program. The BPA determined that CCEC did not qualify for relief because of its failure to show reliance. CCEC is seeking to overturn the denial of relief in this court.

Before 1979, CCEC maintained a 69 kV transmission line between a BPA transformer substation at Gold Beach, Oregon and Brookings, Oregon. The BPA substation at Gold Beach stepped down the BPA’s 115 kV transmission to CCEC’s 69 kV line. In 1979, CCEC completed an upgrading of its system that included the conversion of the 69 kV line into a 115 kV line. The [1344]*1344upgrading also included a rebuilding of CCEC’s substations at Gold Beach, Pistol River, and North Brookings to handle 115 kV. These improvements led to an avoidance of the transformation charge.

In 1982, CCEC made its first request for mitigation relief. In this request CCEC claimed that one of the reasons for upgrading its system was the desire to avoid the transformation charge and that it was therefore entitled to mitigation relief.

However, CCEC conceded in oral argument and the record shows that the overriding reason for upgrading the Gold Beach substation and making other improvements was to improve the condition of CCEC’s deteriorated transmission system along its 69 kV line. A report prepared in 1976 at CCEC’s request by an engineering consulting firm called attention to the need for major repairs along CCEC’s 69 kV line and urged improvement. The report made clear that improvements were necessary. It stated:

The existing 69 kV line between Gold Beach and Brookings needs extensive repairs and maintenance. The preliminary inspection of the 69 kV line made in June 1976 revealed that up to about 50 percent of the poles are in a state of decay and need to be replaced. Many of the cross-arms need reinforcing or replacing, and the conductor at many locations needs to be resagged and reclipped to the insulators.

The report recommended a conversion of the 69 kV line into a 115 kV line in order to accomplish the necessary repairs and meet long-term system demands. The financial benefit resulting from an avoidance of the transformation charge was cited as an additional incentive for the improvements. However, it is fair to conclude from this report that the system would have been upgraded regardless of the existence of the transformation charge.

The BPA denied the initial request for relief, and during the following years CCEC maintained correspondence with the BPA in a continuing attempt to obtain financial relief. There were no formal, “trial-type” hearings conducted by the BPA. The parties attempted to resolve the claim through an exchange of correspondence and submission of documents.

On March 22, 1985, the BPA issued another denial of CCEC’s claim for the following reasons: (i) the lack of evidence that avoidance of the transformation charge was the primary reason for upgrading the system; (ii) the existence of evidence that the improvements were made for other reasons; (iii) the fact that the existing facilities would not comply with the BPA’s customer service policy. CCEC alleges and the BPA does not deny that these criteria were based on guidelines formulated in the process of deciding an earlier claim for mitigation relief by another utility. On December 31, 1981, the BPA Chief of the Contract Management Branch had written an internal memorandum recommending that relief be granted to a utility with a transformer substation located at West Burley, Idaho. The memorandum proposed several factors to apply to the West Burley case and to use “as guidelines for evaluation of any future” claims for mitigation relief.1 Among these factors was the re[1345]*1345quirement that avoidance of the transformation charge be a primary reason for upgrading the utility’s system.

CCEC filed a petition for review in this court from the March 22 decision and requested reconsideration from the BPA. The request for reconsideration was denied on March 28, 1986, and the BPA issued its Administrator’s Record Of Decision On Reconsideration Of The Coos-Curry Electric Cooperative, Inc., Request For Reimbursement. In the Record Of Decision, the BPA made clear that CCEC’s claim was denied because avoidance of the transformation charge was not the primary reason for CCEC’s upgrade. The BPA also cited other reasons for the denial of relief. CCEC filed a petition for review from this decision, and the two petitions have been consolidated in this review.

CCEC is seeking an order from this court directing the BPA to pay CCEC $742,122.00, the amount claimed as mitigation relief. CCEC challenges the BPA’s denial of relief on two grounds. First, it alleges that the guidelines are invalid because the BPA violated the rulemaking procedures set forth in the Administrative Procedure Act (“APA”). CCEC claims that the BPA’s guidelines for mitigation relief are rules, as defined by the APA, and that the BPA’s failure to comply with the notice and comment and publication procedures renders them invalid.2

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
821 F.2d 1341, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coos-curry-electric-cooperative-inc-v-jura-ca9-1987.