Cooper v. State

103 Misc. 209
CourtNew York Court of Claims
DecidedApril 15, 1918
DocketNo. 15150
StatusPublished
Cited by5 cases

This text of 103 Misc. 209 (Cooper v. State) is published on Counsel Stack Legal Research, covering New York Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cooper v. State, 103 Misc. 209 (N.Y. Super. Ct. 1918).

Opinion

Cunningham, J.

The claimant during the year 1917 was the owner of a farm in the town of Frankfort, Herkimer county. The Mohawk river bounds a thirty-acre parcel of the farm on the north.. The New York Central Railroad embankment and tracks extend generally parallel with this thirty-acre parcel and the Mohawk river, and lie to the north of the latter. Northerly of the New York Central tracks is an extensive, level, swampy area,, and northerly of said area, and running generally parallel with the railway tracks, is the Barge canal. Two culverts pierce the railway embankment, one circular, five feet by seven feet, and the other an arch, nine feet by twelve feet. The former is opposite that part of the Mohawk river, and the adjacent premises of the claimant, which are nearest to the tracks, the river at this point being about 450 feet from the railway embankment. The embankment is about 600 feet from the canal. The larger culvert is about 700 feet from the circular culvert, and about 450 feet from the river. The territory between the canal and the railway embankment was approximately seven feet lower than the normal water level maintained in the banal, prior to June 11, 1917, and two feet lower than the.elevation of claimant’s thirty-acre parcel. On that [211]*211day there was growing on the thirty-acre parcel about nineteen acres of hay, practically all of which was on that portion nearest to the tracks and to the circular culvert. Certain other crops were in process of growth on other portions of the thirty acres.

The' southerly bank of the canal, northerly of and across the river and the railway tracks from the claimant’s premises, still was under construction on June 11,1917. The water in this portion of the canal, which was a part of a level nine miles long, had been maintained, prior thereto, at an elevation of 401. This was the minimum elevation permitting navigation, which it was the desire of the state officials to maintain, and which was being maintained, at this time. This elevation was maintained, under normal conditions, by the operation of the valves in the lock, at the lower end of the Nine Mile level. The maximum elevation of water, for which the canal at this point was designed, was 406, and there was a spillway in this level set, presumably, at the maximum elevation of 406, and was so designed that any water discharged into this level would be discharged over the spillway, after the water had reached an elevation of 406, unless it was fed to the lower level of the canal through the lock valves. Various natural streams of water flowing from the north were diverted into this level, and added their waters to those of the canal. The banks of the canal were designed, when completed, to reach an elevation of at least 406, and to confine safely water at that elevation. But, on June 11, 1917, this part of the southerly bank had not been completed to the planned elevation. The necessary amount of earth and wash-wall to complete and protect it, as planned, had not been placed. As a result, the upper part of the embankment, because of its incompleteness, was weak. There had been a “ wet season,” and on the tenth and elev[212]*212enth there was particularly excessive precipitation. The United States Government weather observer at Utica testified that, at that place, the rainfall from eight a. m. on June tenth, to eight a. m. on June eleventh, was two and ninety-five one-hundredths inches, and during the period thereafter to eight a. m., of June twelfth, forty-two one-hundredths of an inch. The storm began at eleven a. m. on the tenth, and ended at four p. m. on the eleventh, measurements being taken by the observer at eight a. m. each day. This rainfall was the heaviest ever recorded by the United States observer at this point. The claimant’s farm is about six miles east of Utica. The rainfall was general in the vicinity. Streams overflowed their banks. Roads were flooded. Several bridges on streams within four miles of the claimant’s farm were carried away. At Oriskany on the Oriskany creek, a stream tributary to the Mohawk at a point westerly and above the claimant’s premises, and about twenty-five miles distant from the latter, a flood, disastrous to life and property, occurred. At about six o’clock a. m. of June eleventh, the water in the Nine Mile level, augmented by the influx of the streams, swollen by the excessive rain and discharging into it, had risen so rapidly, that the lock valves were unable to carry off the excess, and to hold the level at 401. On the contrary, at that hour, the water had reached an elevation of 406, subjecting the uncompleted southerly bank to a strain beyond its power of resistance. Two hundred and twenty feet of the embankment thereupon broke, to a depth of seven feet, precipitating the water of the canal rapidly upon and over the territory between the canal and the railway embankment, and through the culverts into the already full channel of the Mohawk, and across the latter, covering the thirty acres of the claimant to a depth of approximately one and four-tenths feet. At [213]*213that hour, the Mohawk, although full, had not overflowed yet, to any great extent if at all. The flood waters from the west and south had not yet had their effect at this point. The river was rising constantly and rapidly, and at about eight a. m., had overflowed adjacent lands, and continued to overflow rapidly during June eleventh, until later that day the thirty-acre parcel was inundated in excess of four feet, and was submerged to a depth of several feet, during the two days following. Meantime the elevation of the water in the canal receded, until no water was flowing through the breaks therefrom, and, at the same time, and thereafter, the water of the river increased in elevation until it was on the same level with the water in the canal. After water had ceased to flow from the canal, and the elevation of the latter had decreased approximately six feet, the elevation of the water, owing to the flooded condition of the river, steadily increased and remained at its greatest depth on the claimant’s premises. The water gradually receded from claimant’s premises after having covered same during a period of about three days. As a result of the overflow, the hay and other crops on the claimant’s thirty-acre parcel were injured or destroyed.

This claim presents two questions for our consideration :

1. Was the state guilty of negligence resulting in the overflow of the claimant’s premises?

2. Is the state liable for the damage which accrued to claimant as a result of the overflow of his premises, or for any part of such damage?

We are in agreement with the contention so earnestly advanced by the state, that the claimant cannot recover, unless he has established negligence on the part of the state. Harris & Briggs v. State, 12 Ct. of Claims, 22; Gordon v. Ellenville & K. R. R. Co., 119 [214]*214App. Div. 797; Stone v. State, 138 N. Y. 124; Conklin v. New York, O. & W. R. Co., 102 id. 107; Warner v. State, 132 App. Div. 611.

The negligence of the state has been established. In its anxiety to utilize the Barge canal for navigation immediately the state allowed the Nine Mile level to fill to an elevation of 401, and diverted into that level various natural streams, flowing from the north. The state knew, or in the exercise of due care ought to have known, the volume of discharge of these streams, under conditions such as existed at and prior to the break.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Montezuma Garden Co. v. State
121 Misc. 820 (New York State Court of Claims, 1923)
Holland-Dale Garden Co. v. State
113 Misc. 219 (New York State Court of Claims, 1920)
Bauer v. State
106 Misc. 1 (New York State Court of Claims, 1919)
Harter v. State
106 Misc. 9 (New York State Court of Claims, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
103 Misc. 209, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cooper-v-state-nyclaimsct-1918.