Cooper Industries, Inc. v. Tarmac Roofing Systems, Inc.

276 F.3d 704, 2002 WL 2853
CourtCourt of Appeals for the Fifth Circuit
DecidedJanuary 7, 2002
Docket00-60150
StatusPublished
Cited by21 cases

This text of 276 F.3d 704 (Cooper Industries, Inc. v. Tarmac Roofing Systems, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cooper Industries, Inc. v. Tarmac Roofing Systems, Inc., 276 F.3d 704, 2002 WL 2853 (5th Cir. 2002).

Opinion

EMILIO M. GARZA, Circuit Judge:

Cooper Industries, Inc. (“Cooper”) sued Tarmac Roofing Systems, Inc. (“Tarmac”) and International Fidelity Insurance Co. (“IFIC”) for damages arising from the installation of a roof on Cooper’s Vicksburg, Mississippi manufacturing plant. A jury found Tarmac liable to Cooper for negligence, breach of contract and warranty, and IFIC liable to Cooper for negligence and breach of contract. Tarmac and IFIC each contest their liability and the amount of damages awarded. We REVERSE the district court’s decision on Tarmac’s Rule 50 motion, but AFFIRM the district court’s decisions as to IFIC.

I

Cooper hired Moisture Protection Associates, Inc. (“MPA”), a roofing consulting firm, to advise it regarding the roofs installation, and to monitor the installation process. MPA, inter alia, assisted Cooper in soliciting bids for the roofing contract and devising the following conditions for prospective contractors: (1) prove that they were trained by one of the membrane manufacturers to install the membrane; (2) agree to install the membrane in accordance with the manufacturer’s specifications, and obtain the manufacturer’s approval; (3) promise to procure a twelve-year labor and materials warranty from the membrane manufacturer; and (4) obtain performance and payment bonds. Castro, the contractor chosen by Cooper, identified Tarmac as the manufacturer of the membrane Castro planned to use. Castro provided proof that Tarmac certified Castro as trained to install the Tarmac product, and Tarmac agreed that the project was satisfactory to proceed. Castro also obtained performance and payment bonds from IFIC. 2

Shortly after the project began, Castro’s owners died. While Castro continued to perform under the contract, IFIC hired a consultant to monitor the payment of Castro’s bills. What occurred next is subject to dispute. IFIC asserts that it was informed that Castro had not made timely payment to some suppliers, and subsequently learned that Castro could not meet its payroll obligations. Thereafter, IFIC entered into an assignment agreement with Castro in which it received Cooper’s *707 payments to Castro in return for providing financial assistance to Castro. As a consequence of the financial assistance provided by IFIC, Castro was able to complete the project through its subcontractor, Weath-erguard. Cooper, however, contends that after demands for payment were made, Castro defaulted and IFIC took over the contract, entering into a subcontract with Weatherguard to complete the project.

Under either theory, problems arose regarding the quality of Weatherguard’s work. At one point, Cooper requested that IFIC remove Weatherguard from the project, but IFIC refused. IFIC’s consultant, however, responded to Cooper’s complaints by informing Cooper that IFIC remained committed to completing the project, that it would monitor Weather-guard’s daily progress, and would procure another contractor to assist Weatherguard. IFIC then hired Canton Sheet Metal & Roofing to complete the drainage system on the roof, and to perform any warranty work under the contractor’s two-year “Roofing Guarantee,” which was executed in IFIC’s name as Castro’s surety.

Upon completion of the project, IFIC obtained the Tarmac twelve-year workmanship and material warranty for Cooper. The warranty covered defects in the roof as long as the roof was installed in accordance with Tarmac’s specifications. The Weatherguard representative signed the warranty application “[f]or Castro Roofing / International Fidelity Insurance Company” and listed “Castro Roofing C/O dba Castro RFG International Fidelity Insurance Company” as the contractor. On the warranty, “Castro Rfg Co. c/o Int’l Fidelity Ins. Co.” was identified as the contractor. Tarmac asserts that it issued the warranty based on Weatherguard’s representations, as it did not inspect the roof.

Less than a year after the roof was completed, it began to blister. For the first two years that the roof required repair, IFIC fulfilled its obligations under the contractor’s warranty by paying to have the roof repaired. After the contractor’s warranty expired, Cooper continued to make repairs. Thereafter, Cooper informed Tarmac that the Tarmac warranty covered the roofing repairs. After re-inspecting the roof, Tarmac denied liability, concluding that the contractor’s failure to follow Tarmac’s installation procedures necessitated the repair work. Next, Cooper informed IFIC that it would seek “liability damages against [IFIC], as surety for Castro.”

Cooper repaired and replaced parts of the roof, and sued IFIC and Tarmac for the repair and replacement costs. The district court denied Tarmac’s and IFIC’s motions for summary judgment and judgment as a matter of law. The jury found IFIC liable for breach of contract and negligence, and Tarmac liable for breach of contract, negligence, and breach of warranty. The jury denied IFIC and Tarmac’s cross claims for indemnification, and awarded damages of $1,640,000 for the repair and replacement costs less better-ments. The district court entered judgment against IFIC and Tarmac for $1,130,402. The court arrived at this amount by deducting the value of Cooper’s use of the defective roof from the amount awarded by the jury.

II

We review a district court’s Rule 50 determination de novo, “applying the same legal standard as the trial court.” Flowers v. So. Reg’l Physician Servs. Inc., 247 F.3d 229, 235 (5th Cir.2001). Judgment as a matter of law is proper if “a party has been fully heard on an issue and there is no legally sufficient evidentiary basis for a reasonable jury to find for the party on that issue.” Fed.R.Civ.P. 50(a); see *708 Reeves v. Sanderson Plumbing Prods. Inc., 530 U.S. 133, 149, 120 S.Ct. 2097, 2109, 147 L.Ed.2d 105 (2000). As the conduct giving rise to this action occurred in Mississippi, and our jurisdiction is predicated on the parties’ diverse citizenship, we apply Mississippi substantive law. See McKee v. Brimmer, 39 F.3d 94, 96 (5th Cir.1994).

A

Cooper charges Tarmac with negligence and breach of contract under a theory that Castro and Weatherguard were Tarmac’s agents, making Tarmac liable for their acts and omissions. Tarmac contends that Cooper failed to produce any evidence that Castro and Weatherguard were Tarmac’s agents, or should be treated as such. In Mississippi, “[t]he burden of proving an agency relationship is on the party asserting it.” Booker v. Pettey, 770 So.2d 39, 45 (Miss.2000). Cooper argues that the controlling law in Mississippi on the issue of whether Tarmac should be held responsible for Castro and Weather-guard’s conduct is found in Fedders Corp. v. Boatright, 493 So.2d 301 (Miss.1986). In Fedders, the Mississippi Supreme Court held a manufacturer of a heat pump liable for breach of an implied warranty of merchantability.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Westport Ins v. PA Natl Mutual
117 F.4th 653 (Fifth Circuit, 2024)
United States v. Gas Pipe
997 F.3d 231 (Fifth Circuit, 2021)
United States v. Duane Sheridan
838 F.3d 671 (Fifth Circuit, 2016)
Steve Simms v. Jerral Jones
836 F.3d 516 (Fifth Circuit, 2016)
United States v. Wissam Allouche
659 F. App'x 766 (Fifth Circuit, 2016)
United States v. Raymond Valas, III
822 F.3d 228 (Fifth Circuit, 2016)
Dulin v. BD. OF COM'RS OF GREENWOOD LEFLORE HOSP.
657 F.3d 251 (Fifth Circuit, 2011)
Jacob Brochtrup v. Mercury Marine
426 F. App'x 335 (Fifth Circuit, 2011)
United States v. Wright
634 F.3d 770 (Fifth Circuit, 2011)
Jourdan v. Schenker International, Inc.
275 F. App'x 371 (Fifth Circuit, 2008)
United States v. Escareno Sanchez
507 F.3d 877 (Fifth Circuit, 2007)
Miller v. TX Tech Univ Hlth
342 F.3d 563 (Fifth Circuit, 2005)
Johnson v. LA Dept of Education
343 F.3d 732 (Fifth Circuit, 2005)
United States v. Ho
Fifth Circuit, 2002
Test Masters Educ v. Singh
Fifth Circuit, 2002
Anthony v. Chevron USA, Inc.
284 F.3d 578 (Fifth Circuit, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
276 F.3d 704, 2002 WL 2853, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cooper-industries-inc-v-tarmac-roofing-systems-inc-ca5-2002.