Constructora Andrade Gutiérrez, S.A. v. American International Insurance

467 F.3d 38, 2006 U.S. App. LEXIS 26816, 2006 WL 3041969
CourtCourt of Appeals for the First Circuit
DecidedOctober 27, 2006
DocketNo. 05-2303
StatusPublished
Cited by16 cases

This text of 467 F.3d 38 (Constructora Andrade Gutiérrez, S.A. v. American International Insurance) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Constructora Andrade Gutiérrez, S.A. v. American International Insurance, 467 F.3d 38, 2006 U.S. App. LEXIS 26816, 2006 WL 3041969 (1st Cir. 2006).

Opinion

HANSEN, Senior Circuit Judge.

C & M Constructora, S.A. (C & M) appeals from the July 13, 2005, amended judgment nunc pro time of the district court in which the district court granted summary judgment in favor of Constructo-ra Andrade Gutierrez, S.A. (CAG) on its claim against American International Insurance Company of Puerto Rico (AIICO); granted summary judgment in favor of AIICO on its third-party claim for indemnification against C & M; and dismissed C & M’s cross-claims against CAG on the basis that the cross-claims were subject to mandatory arbitration. We affirm those portions of the district court’s judgment that are properly the subject of this appeal.

I. Background

C & M, a construction company headquartered in the Dominican Republic, entered into an agreement titled “Agreement on Grouping Enterprises” (hereinafter “Joint Venture Agreement”) in November 1995 with CAG, a Brazilian corporation, for the sole purpose of bidding on the reconstruction of the Pont Sondé-Mireba-lais Highway in the Republic of Haiti. In the event that the joint venture won the contract, CAG agreed to provide 100% of the guarantees for performance and payment to the Republic of Haiti, and C & M agreed to provide counter-guarantees to CAG for C & M’s participation in the project.

The Republic of Haiti awarded the project to the joint venture in May 1996. Pursuant to the Joint Venture Agreement, CAG obtained a performance and payment bond on behalf of the joint venture for the benefit of the Republic of Haiti, and C & M obtained a bond from AIICO for the benefit of CAG in proportion to C & M’s participation in the construction project. The AIICO bond stated that it was “an irrevocable and unconditional guarantee ... for the completion by the contractor of its obligations to [CAG] pursuant to the stipulations of the contract dated May 6, 1996.” (Appellant’s App. at 165.)

The parties were unable to settle disputes that developed during the construction project, and on February 11, 1998, C & M and CAG entered into an agreement titled “Modifications to Agreement of Enterprise Group” (Modifications Agreement) in which participation in the construction project was reallocated 99% to C & M and 1% to CAG. The Modifications Agreement incorporated a letter of the same date (Letter Agreement) written by C & M and approved by CAG, wherein the parties agreed that C & M would pay $967,000 to CAG as reimbursement for expenses incurred by CAG, to the extent that amount was supported by a to-be-performed audit, and C & M would pay $440,000 to CAG for loss of business and profits. The Letter Agreement contemplated that C & M would provide CAG with a bank bond or insurance guarantee for the amounts specified in the Letter Agreement. Although C & M provided two surety bonds, CAG returned the bonds, and no additional bonds were ever issued on the Letter Agreement.

[42]*42The subsequent audit performed pursuant to the Letter Agreement revealed that CAG was responsible for cost overruns while it controlled the project, and that C & M’s resulting losses far exceeded the amounts C & M had agreed to pay in the Letter Agreement. C & M thereafter refused to pay the agreed-upon amounts pursuant to the terms of the Letter Agreement. On July 19, 1999, CAG filed a complaint against AIICO in the United States District Court for the District of Puerto Rico, invoking the district court’s diversity jurisdiction and seeking to recover on the AIICO bond for the amounts specified in the Letter Agreement that C & M refused to pay.

C & M attempted to intervene in CAG’s complaint against AIICO to protect its interests. Meanwhile, AIICO filed a third-party complaint against C & M in the original action, seeking to invoke the separate indemnity agreement it had entered into with C & M to cover any payments that AIICO might be required to make on the bond it had issued on C & M’s behalf in favor of CAG. Thereafter, C & M filed cross-claims against CAG, claiming that CAG had breached the Joint Venture Agreement.

After much litigation, the district court filed an Opinion and Order on February 26, 2003, granting summary judgment in favor of CAG on its original claim against AIICO in the amount of $1,407,000, finding that the bond issued by AIICO was in actuality an unconditional guarantee essentially payable on demand. In an Opinion and Order filed on February 27, 2003, the district court granted CAG’s motion to dismiss C & M’s cross-claims without prejudice, finding that the claims were subject to mandatory arbitration. The district court then entered judgment on CAG’s claim against AIICO and on C & M’s cross-claims against CAG on February 27, 2003, in accordance with the aforementioned Opinions and Orders.

On November 1, 2004, the district court filed a Memorandum and Order finding that C & M was liable to AIICO on the third-party complaint against C & M for indemnification of the amounts that AIICO was ordered to pay to CAG pursuant to the February 26, 2003, Opinion and Order. The district court then filed an amended judgment on November 1, 2004, amending the February 27, 2003, judgment to add the judgment against C & M in favor of AIICO. Finally, on July 13, 2005, the district court granted CAG’s motion to include prejudgment interest on the amount of $1,407,000 that AIICO was ordered to pay to CAG in the February 26, 2003, order. The district court entered an Amended Judgment Nunc Pro Tunc reflecting the three prior judgments and the newly awarded pre-judgment interest.

From this final judgment, both C & M and AIICO filed separate notices of appeal. AIICO’s appeal was docketed as No. 05-2302, and its caption does not list C & M as a party to that appeal. C & M’s appeal was docketed as No. 05-2303. The appeals were consolidated for oral argument. AIICO eventually settled its dispute with CAG by paying $1,600,000 to CAG and moved to dismiss its appeal in this court on November 2, 2005. Accordingly, this court dismissed appeal No. 05-2302. C & M’s appeal No. 05-2303 is therefore the subject of the case before us.

II. Issues on Appeal and Standard of Review

C & M filed its notice of appeal on August 3, 2005, in which it appealed

from a final amended judgment nunc pro tunc (and memorandum and order) entered on July 13, 2005 by the Hon. Jay A. Garcoa [sic], amendingan [sic] amended judgment (and memorandum [43]*43and order) entered on November 1, 2004 granting defendant and third-party plaintiff [AIICO]’s motion for summary judgment and ruling that C & M was obligated to indemnify AIICO for any disbursements made to plaintiff, [CAG], as well as any costs and attorneys fees resulting from the court’s February 25, 2003 judgment and February 27, 2003 Opinion and Order entered in CAG’s favor.

(Appellant’s App. at 1067.) One week later, C & M filed an amended notice of appeal, which was nearly identical in language to the original notice of appeal, but added the phrase “dismissing C & M’s cross claims against plaintiff [CAG], without prejudice, finding that they were subject to mandatory arbitration” to its description of which portions of the July 13, 2005, amended judgment nunc pro tunc it was appealing.2 (Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gonpo v. Sonam's Stonewalls & Art, LLC
41 F.4th 1 (First Circuit, 2022)
Rivera v. Kress Stores P.R., Inc.
30 F.4th 98 (First Circuit, 2022)
Luceus v. State of Rhode Island
923 F.3d 255 (First Circuit, 2019)
Santos-Santos v. Torres-Centeno
842 F.3d 163 (First Circuit, 2016)
Biltcliffe v. CitiMortgage, Inc.
772 F.3d 925 (First Circuit, 2014)
United States v. Ortiz
741 F.3d 288 (First Circuit, 2014)
Campos v. Van Ness
711 F.3d 243 (First Circuit, 2013)
Rojas-Velazquez v. Figueroa-Sancha
676 F.3d 206 (First Circuit, 2012)
Markel American Insurance v. Díaz-Santiago
674 F.3d 21 (First Circuit, 2012)
Vallejo v. Santini-Padilla
607 F.3d 1 (First Circuit, 2010)
Gray v. Evercore Restructuring, L.L.C.
544 F.3d 315 (First Circuit, 2008)
Alstom Caribe, Inc. v. Geo. P. Reintjes Co.
484 F.3d 106 (First Circuit, 2007)
Brooks v. AIG SunAmerica Life Assurance Co.
480 F.3d 579 (First Circuit, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
467 F.3d 38, 2006 U.S. App. LEXIS 26816, 2006 WL 3041969, Counsel Stack Legal Research, https://law.counselstack.com/opinion/constructora-andrade-gutierrez-sa-v-american-international-insurance-ca1-2006.