Constructionsouth, Inc. v. Jenkins

97 So. 3d 515, 12 La.App. 5 Cir. 63, 2012 La. App. LEXIS 929, 2012 WL 2476654
CourtLouisiana Court of Appeal
DecidedJune 28, 2012
DocketNo. 12-CA-63
StatusPublished
Cited by4 cases

This text of 97 So. 3d 515 (Constructionsouth, Inc. v. Jenkins) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Constructionsouth, Inc. v. Jenkins, 97 So. 3d 515, 12 La.App. 5 Cir. 63, 2012 La. App. LEXIS 929, 2012 WL 2476654 (La. Ct. App. 2012).

Opinion

MARION F. EDWARDS, Chief Judge.

12Pefendant/appellant, Gayle O. Jenkins (“Jenkins”), appeals a judgment of the Twenty-Fourth Judicial District Court confirming an arbitration award in favor of plaintiff/appellee, ConstructionSouth, Inc. (“CSI”). On March 24, 2004, CSI entered into a construction contract with 3901 Ridgelake, LLC (“Ridgelake”) to build Pontchartrain Caye Condominiums, a condominium project at 3901 Ridgelake Drive in Metairie, Louisiana. Jenkins, is the managing member of Ridgelake. CSI and Ridgelake entered into a contract, a standard form AIA Document “for Construction Projects of Limited Scope where the basis of payment is a STIPULATED SUM.” The contract contains the standard AIA arbitration provision. The contract showed the name of the owner as Ridgelake, underneath which was Jenkins’ signature, absent a title or other designation.

CSI sought to recover damages under the contract for failure of Ridgelake to pay sums due under the contract. According to the record, in December 2007, CSI initi[518]*518ated an arbitration proceeding against Ridgelake with the American Arbitration Association. While the arbitration proceeding was still pending in January 2009, |3CSI filed a petition in the Twenty-Fourth Judicial District Court against Jenkins personally, alleging that she made certain misrepresentations and diverted proceeds from insurance, as well as advances on a construction loan, and that she failed to pay particular applications for payment made by CSI. CSI alleged the following causes of action: detrimental reliance; fraud; disregard of corporate identity; and negligent or intentional misrepresentation. Jenkins filed an Exception of Prematurity and Motion to Stay, averring that the dispute in question was the subject of the arbitration proceedings and that the claims against her were required to be decided in that forum. In April 2009, the court ordered the parties to the lawsuit, including Jenkins, to proceed to arbitration and granted the Motion to Stay, finding the Exception of Prematurity to be moot.

On January 14, 2011, the arbitrator entered his Final Award, finding that CSI substantially performed the construction contract with Ridgelake and that the unpaid balance owed by Ridgelake was $1,040,550, plus interest. It was also determined that Ridgelake’s failure to pay constituted an unexcused material failure to perform its obligations and was a breach of contract. The arbitrator also found that Jenkins, as the managing member of Ridgelake, was personally liable for its obligations to CSI because she disregarded the corporate formalities and conducted the business in such a manner that she and Ridgelake were alter egos of one another. She co-mingled corporate and personal funds, undercapitalized the company, and made preferential payments out of company funds to herself in lieu of outstanding obligations to CSI. CSI was not liable for bad faith or intentional misconduct.

Ridgelake and Jenkins were ordered to pay the amount of $1,499,725, as well as the administrative fees and expenses of the arbitrator, within thirty days.

|4On January 28, 2011, CSI moved to confirm the arbitration award, but learned that Jenkins had filed a voluntary petition for Chapter 11 Bankruptcy on January 18, 2011. In February 2011, CSI moved the Bankruptcy Court for relief from the automatic stay in order to resume and complete the confirmation of the arbitration award in state court. Counsel for Jenkins had no opposition to the motion, which was then granted by the Bankruptcy Court.

Six days prior to the confirmation hearing, Jenkins filed a notice of removal of the matter to federal court. In turn, CSI moved to remand the matter back to state court, which motion was granted. In so doing, the federal court further assessed reasonable attorney’s fees and costs against Jenkins. Prior to the confirmation hearing re-set in state court, Jenkins requested the award be vacated, urging that the arbitrator exceeded his authority in rendering an award against her, a non-party; that the award was not based on contract; and that the findings constituted a manifest disregard of the law. Following a hearing, the trial court found that Jenkins consented to and voluntarily joined in the arbitration between Ridge-lake and CSI; that the arbitrator did not exceed the authority granted him by the parties; and that statutory grounds for vacatur were not established. In the transcript, the court also found that the motion to vacate was untimely. The court confirmed the award in the amount of $1,538,610 plus legal interest. Jenkins appeals.

On appeal, Jenkins urges that the request to vacate was timely. She further [519]*519avers that the tort causes of action were not before the arbitrator and that the findings of the arbitrator did not arise out of the contract that was the subject of the mediation. Jenkins argues that the award “finds its essence” in an equitable remedy rather than in contract.

|aOn appeal, we decline to address the issue of timeliness because of our findings below.

The arbitration clause contains the following language:

Except by written consent of the person or entity sought to be joined, no arbitration arising out of or relating to the Contract Documents shall include, by consolidation, joinder or in any other manner, any person or entity not a party to the Agreement under which such arbitration arises, unless it is shown that at the time the demand for arbitration is filed that (1) such person or entity is substantially involved in a common question of fact or law, (2) the presence of such person or entity is required if complete relief is to be accorded in the arbitration, (3) the interest or responsibility of such person or entity in the matter is not insubstantial, and (4) such person or entity is not the Architect or any of the Architect’s employees or consultants. The agreement herein among the parties to the Agreement and any other written agreement to arbitrate referred to herein shall be specifically enforceable under applicable law in any court having jurisdiction thereof.

As the basis for her exception of prematurity and motion to stay, Jenkins invoked the arbitration clause in the contract and confessed in her memorandum that she had filed a written demand for arbitration and

thereby has supplied the written consent required by that provision in order to join in the arbitration ‘any person or entity not a party to the Agreement under which such arbitration arises.’ Furthermore ... the exception of persons who are not parties to the Agreement but may be joined in arbitration ... covers Jenkins. That is, Jenkins is a person who is ‘substantially involved in a common question of fact or law.’

She further stated that

ConstructionSouth has clearly raised the issue of veil-piercing and alter ego through its factual allegations and third count of its complaint, It would be inequitable to permit ConstructionSouth to litigate under a theory of piercing the veil or alter ego liability while denying Jenkins the right to arbitrate these claims....

In argument to the court, Jenkins argued that the arbitration clause in the contract between Jenkins, Ridgelake, and CSI applied to any disputes arising from |fithe work performed, citing Grigson v. Creative Artists Agency, LLC,1 a federal Fifth Circuit case, as controlling. Grigson

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Master Craft Constr., LLC v. Pronoun, Inc.
258 So. 3d 802 (Louisiana Court of Appeal, 2017)
Thomas v. Robinson
176 So. 3d 698 (Louisiana Court of Appeal, 2015)
Goodrich Petroleum Co. v. MRC Energy Co.
137 So. 3d 200 (Louisiana Court of Appeal, 2014)
Detraz v. Banc One Securities Corp.
123 So. 3d 875 (Louisiana Court of Appeal, 2013)
Frances R. Detraz v. Banc One Securities Copr.
Louisiana Court of Appeal, 2013

Cite This Page — Counsel Stack

Bluebook (online)
97 So. 3d 515, 12 La.App. 5 Cir. 63, 2012 La. App. LEXIS 929, 2012 WL 2476654, Counsel Stack Legal Research, https://law.counselstack.com/opinion/constructionsouth-inc-v-jenkins-lactapp-2012.