Master Craft Constr., LLC v. Pronoun, Inc.

258 So. 3d 802
CourtLouisiana Court of Appeal
DecidedDecember 20, 2017
Docket17–569
StatusPublished
Cited by4 cases

This text of 258 So. 3d 802 (Master Craft Constr., LLC v. Pronoun, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Master Craft Constr., LLC v. Pronoun, Inc., 258 So. 3d 802 (La. Ct. App. 2017).

Opinion

COOKS, Judge.

*804FACTS AND PROCEDURAL HISTORY

In February 2014, the City of Lake Charles contracted with Master Craft Construction, LLC for the construction of water service lines. The contract between the City of Lake Charles and Master Craft required that the work be completed within sixty (60) days and provided for liquidated damages in the event of non-completion within the specified time period.

In connection with this contract, Master Craft entered into a subcontract with Pronoun, Inc., to install several thousand feet of underground water pipes. Problems arose concerning the performance of Pronoun's duties under the subcontract. According to Master Craft, it took Pronoun fifteen days out of the sixty day project period to man the job. Master Craft also found out later that Pronoun did not have the insurance required by the subcontract, nor did it have the capital to purchase the insurance. Pronoun also did not have the necessary manpower or equipment to perform the contracted work. Master Craft claimed any work done by Pronoun was substandard and untimely. When Master Craft terminated the job, they alleged Pronoun had already pulled off the job to work on another project.

Pronoun was not paid for any of the work it performed. In response, Pronoun recorded a lien in Calcasieu Parish under the Louisiana Public Works Act, La.R.S. 38:2241 et seq. Suit to enforce the lien was subsequently filed in the Fourteenth Judicial District Court. Upon Master Craft's motion, the suit was stayed in the district court pursuant to the arbitration clause set forth in the contract between Master Craft and Pronoun.

Pursuant to the terms of the contract, Master Craft initiated the arbitration by making demand on Pronoun by certified mail on August 27, 2015. The contract provided that each party could select an arbitrator; and if both did so, then those two arbitrators would select a third arbitrator to handle the proceeding. If only one party selected an arbitrator, that choice would be the arbitrator. Master Craft selected William Scott Montgomery, a licensed contractor, who had previous experience serving as an arbitrator. Pronoun did not select an arbitrator; thus, Mr. Montgomery became the arbitrator.

On September 18, 2015, counsel for Master Craft forwarded a copy of the notice of arbitration to Pronoun's counsel. Pronoun made no claim against Master Craft and filed no objections to the proceedings. On October 29, 2015, the arbitrator set the arbitration for November 18, 2015 and sent notice to all parties.

On November 12, 2015, six days before the hearing, counsel for Pronoun sent a letter requesting the arbitration hearing be reset as his client would be out of town on the date of the hearing. Master Craft did not oppose the request, and the arbitration hearing was reset for December 16, 2015. As Master Craft noted, nothing in the letter sent by Pronoun to the arbitrator referenced any complaint about the procedures employed by the arbitrator, any need for further discovery or any need for additional time to prepare.

On December 1, 2015, Pronoun propounded written discovery on Master Craft. At the request of the arbitrator, Master Craft expedited its responses, providing answers on December 9 and 10. On December 9, 2015, at Pronoun's request, a telephone conference was held. Pronoun requested the reset date of December 16, 2015 be continued, claiming it had not had sufficient time to conduct discovery. The arbitrator agreed to postpone the hearing one day to December 17, 2015.

*805On December 14, 2015, Pronoun filed a request with the Fourteenth Judicial District Court (where the previously stayed action was pending), requesting a Temporary Restraining Order to prevent the arbitration from going forward. In the request for TRO, Pronoun argued the arbitrator was governed by the rules of the American Arbitration Association and Federal Rules of Civil Procedure, which he failed to properly "observe." The district court denied the request for the TRO, but ordered that Master Craft's principal, C.J. Burgess, be made available for a deposition.

The arbitration hearing occurred on December 17, 2015, during which documentary and testimonial evidence was presented. At the end of the hearing, the arbitrator concluded that Pronoun had performed some work for which it merited compensation. Thus, the arbitrator awarded Master Craft $40,000.00 in damages rather than the $65,000.00 it had requested, determining Pronoun was entitled to $25,000.00 for the work it performed. Master Craft was also awarded $16,500.00 in attorney fees.

Master Craft then applied to the district court to confirm the arbitration award and Pronoun moved that the award be vacated. After a hearing, the district court denied Pronoun's motion to vacate and entered judgment confirming the arbitration award. This appeal followed, wherein Pronoun asserts the "trial court erred in denying [its] Motion to Vacate the Arbitration award, which motion was based upon the alleged misconduct/misbehavior of the arbitrator." For the following reasons, we affirm the trial court's judgment denying Pronoun's motion to vacate and confirming the arbitration award.

ANALYSIS

It has long been noted that "[b]ecause of the strong public policy favoring arbitration, arbitration awards are presumed to be valid." National Tea Co. v. Richmond , 548 So.2d 930, 932 (La.1989). Moreover, "[e]rrors of fact or law do not invalidate a fair and honest arbitration award," and "[t]he burden of proof rests upon the party attacking the award." Firmin v. Garber , 353 So.2d 975, 978 (La.1977). Such deference to arbitral awards is consistent with the longstanding recognition that arbitration is intended to "speedily ... determine disputes and controversies by quasi-judicial means, thus avoiding the formalities, the delay, the expense, and the vexation of ordinary litigation." Housing Authority of New Orleans v. Henry Ericsson Co. , 197 La. 732, 2 So.2d 195, 199 (1941).

A district court may not vacate an arbitrators' award unless specifically authorized by statute. See La. R.S. 9:4210. An arbitration award, therefore, must be confirmed by a district court unless statutory grounds for vacating the award exist. See Johnson v. 1425 Dauphine, L.L.C. , 10-793 (La.App. 4 Cir. 12/1/10), 52 So.3d 962. Here, Pronoun sought relief under La.R.S. 9:4210, which provides:

In any of the following cases the court in and for the parish wherein the award was made shall issue an order vacating the award upon the application of any party to the arbitration.
A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
258 So. 3d 802, Counsel Stack Legal Research, https://law.counselstack.com/opinion/master-craft-constr-llc-v-pronoun-inc-lactapp-2017.