Master Craft Construction, LLC v. Pronoun, Inc.

CourtLouisiana Court of Appeal
DecidedDecember 20, 2017
DocketCA-0017-0569
StatusUnknown

This text of Master Craft Construction, LLC v. Pronoun, Inc. (Master Craft Construction, LLC v. Pronoun, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Master Craft Construction, LLC v. Pronoun, Inc., (La. Ct. App. 2017).

Opinion

STATE OF LOUISIANA COURT OF APPEAL, THIRD CIRCUIT

17-569

MASTER CRAFT CONSTRUCTION, LLC

VERSUS

PRONOUN, INC.

************

APPEAL FROM THE THIRTIETH JUDICIAL DISTRICT COURT PARISH OF VERNON, NO. 92421C HONORABLE SCOTT WESTERCHIL, DISTRICT JUDGE

************ SYLVIA R. COOKS JUDGE ************

Court composed of Sylvia R. Cooks, John D. Saunders and Candyce G. Perret, Judges.

AFFIRMED.

Francis R. White, III 434 East Lockwood Street Covington, LA 70433 (985) 898-2124 COUNSEL FOR PLAINTIFF/APPELLEE: Master Craft Construction, LLC

Elvin C. Fontenot, Jr. 110 East Texas Street Leesville, LA 71446 (337) 239-2684 COUNSEL FOR PLAINTIFF/APPELLEE: Master Craft Construction, LLC

Robert J. Williams 4830 Lake Street Lake Charles, LA 70605 (337) 562-1116 COUNSEL FOR DEFENDANT/APPELLANT: Pronoun, Inc. COOKS, Judge.

FACTS AND PROCEDURAL HISTORY

In February 2014, the City of Lake Charles contracted with Master Craft

Construction, LLC for the construction of water service lines. The contract

between the City of Lake Charles and Master Craft required that the work be

completed within sixty (60) days and provided for liquidated damages in the event

of non-completion within the specified time period.

In connection with this contract, Master Craft entered into a subcontract with

Pronoun, Inc., to install several thousand feet of underground water pipes.

Problems arose concerning the performance of Pronoun’s duties under the

subcontract. According to Master Craft, it took Pronoun fifteen days out of the

sixty day project period to man the job. Master Craft also found out later that

Pronoun did not have the insurance required by the subcontract, nor did it have the

capital to purchase the insurance. Pronoun also did not have the necessary

manpower or equipment to perform the contracted work. Master Craft claimed any

work done by Pronoun was substandard and untimely. When Master Craft

terminated the job, they alleged Pronoun had already pulled off the job to work on

another project.

Pronoun was not paid for any of the work it performed. In response,

Pronoun recorded a lien in Calcasieu Parish under the Louisiana Public Works Act,

La.R.S. 38:2241 et seq. Suit to enforce the lien was subsequently filed in the

Fourteenth Judicial District Court. Upon Master Craft’s motion, the suit was

stayed in the district court pursuant to the arbitration clause set forth in the contract

between Master Craft and Pronoun.

Pursuant to the terms of the contract, Master Craft initiated the arbitration by

making demand on Pronoun by certified mail on August 27, 2015. The contract

provided that each party could select an arbitrator; and if both did so, then those

2 two arbitrators would select a third arbitrator to handle the proceeding. If only one

party selected an arbitrator, that choice would be the arbitrator. Master Craft

selected William Scott Montgomery, a licensed contractor, who had previous

experience serving as an arbitrator. Pronoun did not select an arbitrator; thus, Mr.

Montgomery became the arbitrator.

On September 18, 2015, counsel for Master Craft forwarded a copy of the

notice of arbitration to Pronoun’s counsel. Pronoun made no claim against Master

Craft and filed no objections to the proceedings. On October 29, 2015, the

arbitrator set the arbitration for November 18, 2015 and sent notice to all parties.

On November 12, 2015, six days before the hearing, counsel for Pronoun

sent a letter requesting the arbitration hearing be reset as his client would be out of

town on the date of the hearing. Master Craft did not oppose the request, and the

arbitration hearing was reset for December 16, 2015. As Master Craft noted,

nothing in the letter sent by Pronoun to the arbitrator referenced any complaint

about the procedures employed by the arbitrator, any need for further discovery or

any need for additional time to prepare.

On December 1, 2015, Pronoun propounded written discovery on Master

Craft. At the request of the arbitrator, Master Craft expedited its responses,

providing answers on December 9 and 10. On December 9, 2015, at Pronoun’s

request, a telephone conference was held. Pronoun requested the reset date of

December 16, 2015 be continued, claiming it had not had sufficient time to

conduct discovery. The arbitrator agreed to postpone the hearing one day to

December 17, 2015.

On December 14, 2015, Pronoun filed a request with the Fourteenth Judicial

District Court (where the previously stayed action was pending), requesting a

Temporary Restraining Order to prevent the arbitration from going forward. In the

request for TRO, Pronoun argued the arbitrator was governed by the rules of the

3 American Arbitration Association and Federal Rules of Civil Procedure, which he

failed to properly “observe.” The district court denied the request for the TRO, but

ordered that Master Craft’s principal, C.J. Burgess, be made available for a

deposition.

The arbitration hearing occurred on December 17, 2015, during which

documentary and testimonial evidence was presented. At the end of the hearing,

the arbitrator concluded that Pronoun had performed some work for which it

merited compensation. Thus, the arbitrator awarded Master Craft $40,000.00 in

damages rather than the $65,000.00 it had requested, determining Pronoun was

entitled to $25,000.00 for the work it performed. Master Craft was also awarded

$16,500.00 in attorney fees.

Master Craft then applied to the district court to confirm the arbitration

award and Pronoun moved that the award be vacated. After a hearing, the district

court denied Pronoun’s motion to vacate and entered judgment confirming the

arbitration award. This appeal followed, wherein Pronoun asserts the “trial court

erred in denying [its] Motion to Vacate the Arbitration award, which motion was

based upon the alleged misconduct/misbehavior of the arbitrator.” For the

following reasons, we affirm the trial court’s judgment denying Pronoun’s motion

to vacate and confirming the arbitration award.

ANALYSIS

It has long been noted that “[b]ecause of the strong public policy favoring

arbitration, arbitration awards are presumed to be valid.” National Tea Co. v.

Richmond, 548 So.2d 930, 932 (La.1989). Moreover, “[e]rrors of fact or law do

not invalidate a fair and honest arbitration award,” and “[t]he burden of proof rests

upon the party attacking the award.” Firmin v. Garber, 353 So.2d 975, 978

(La.1977). Such deference to arbitral awards is consistent with the longstanding

recognition that arbitration is intended to “speedily . . . determine disputes and

4 controversies by quasi-judicial means, thus avoiding the formalities, the delay, the

expense, and the vexation of ordinary litigation.” Housing Authority of New

Orleans v. Henry Ericsson Co., 2 So.2d 195, 199 (La. 1941).

A district court may not vacate an arbitrators’ award unless specifically

authorized by statute. See La. R.S. 9:4210. An arbitration award, therefore, must

be confirmed by a district court unless statutory grounds for vacating the award

exist. See Johnson v. 1425 Dauphine, L.L.C., 10-793 (La.App. 4 Cir. 12/1/10), 52

So.3d 962. Here, Pronoun sought relief under La.R.S. 9:4210, which provides:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Webb v. Massiha
993 So. 2d 345 (Louisiana Court of Appeal, 2008)
Firmin v. Garber
353 So. 2d 975 (Supreme Court of Louisiana, 1977)
National Tea Co. v. Richmond
548 So. 2d 930 (Supreme Court of Louisiana, 1989)
Moak v. Illinois Cent. R. Co.
631 So. 2d 401 (Supreme Court of Louisiana, 1994)
Housing Authority v. Henry Ericsson Co.
2 So. 2d 195 (Supreme Court of Louisiana, 1941)
Johnson v. 1425 Dauphine, L.L.C.
52 So. 3d 962 (Louisiana Court of Appeal, 2010)
Constructionsouth, Inc. v. Jenkins
97 So. 3d 515 (Louisiana Court of Appeal, 2012)
Mixon v. St. Paul Fire & Marine Ins.
84 So. 790 (Supreme Court of Louisiana, 1920)
Haase Construction Co. v. Strohmeyer
738 So. 2d 152 (Louisiana Court of Appeal, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
Master Craft Construction, LLC v. Pronoun, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/master-craft-construction-llc-v-pronoun-inc-lactapp-2017.