Construction, Ltd. v. Brooks-Skinner Building Co.

488 F.2d 427
CourtCourt of Appeals for the Third Circuit
DecidedDecember 4, 1973
DocketNo. 73-1089
StatusPublished
Cited by15 cases

This text of 488 F.2d 427 (Construction, Ltd. v. Brooks-Skinner Building Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Construction, Ltd. v. Brooks-Skinner Building Co., 488 F.2d 427 (3d Cir. 1973).

Opinion

OPINION OF THE COURT

ADAMS, Circuit Judge.

This appeal arises from a dispute between a prime construction contractor and one of its subcontractors, that generated a lawsuit by the prime contractor in which a counterclaim was interposed by the subcontractor. A jury returned a verdict for the latter. The questions with which we must deal concern the admissibility at trial of certain evidence and the propriety of a particular jury instruction.

In June of 1969, Construction, Ltd. was awarded a Government contract for the building of the so-called “South East Asia (SEA) Project” at Fort Dix, New Jersey. Under the terms of the contract, Construction was responsible for the installation of a series of control towers, latrines, classroom buildings, [429]*429“test” buildings, a shower building, and various other facilities, on a range at Fort Dix. Construction was to receive $1,498,000 for the job.

On July 17, 1969, Construction entered into a subcontract with the Brooks-Skinner Building Company, whereby Brooks-Skinner agreed to supply and erect all of the prefabricated metal buildings for the SEA Project.1 Under the subcontract Brooks-Skinner was to deliver the buildings to the job site by October 28, 1969, and to finish its work by November 28, 1969. The subcontract specified a consideration payable to Brooks-Skinner of $175,0002 The parties inserted a notation in their agreement to the effect that actual — not liquidated — damages would be recoverable in the event of a delay by Brooks-Skinner.3

There was testimony at the trial that Brooks-Skinner was late in completing the work required of it, an admitted breach of the subcontract, and that only a few of the buildings were finished by Brooks-Skinner as of December 31, 1969. Further testimony indicated that Brooks-Skinner did not complete all of its work until May 8,1970.

Another critical item developed at trial was that the Government, during the course of construction of the SEA Project, had deleted its order for four of the latrines from the prime contract, its prerogative under the terms of that contract. The Government offered to take a “credit” of $10,963 for the four deleted latrines, and finally withheld payment from Construction for these latrines in the amount of $13,113.4

Construction brought suit against Brooks-Skinner seeking to recover damages allegedly brought about by the subcontractor’s delay,5 and asserted that Brooks-Skinner’s tardiness had caused it a loss of $206,386.6 However, inasmuch as Construction still owed Brooks-Skinner $114,446 under the subcontract, Construction sought a judgment in the amount of only $91,940.7 Brooks-Skinner counterclaimed for the balance owing it under the subcontract, $114,446, and denied any liability to Construction based on the delay. There was a general verdict in favor of Brooks-Skinner in the amount of $68,925,8 and Construction appealed.

I.

At the trial, Brooks-Skinner introduced certain documents evidencing the profit made by Construction from the [430]*430SEA Project. In addition, Brooks-Skinner elicited from several witnesses testimony concerning the same topic, as well as Construction’s general profitability and solvency. On this appeal Construction maintains, inter alia, that the evidence regarding its profits was irrelevant, that it tended to prejudice the' jury, and that its admission therefore constituted reversible error.9

The theory offered by Brooks-Skinner at trial to establish the relevancy of the challenged evidence is contained in the following statement by Brooks-Skinner’s trial counsel:

“But your honor, if this project happened to be the most profitable project for a corporation that has been running in the red, I think it certainly shows that they didn’t sustain the loss that they are attempting to show ”10

And again, in his summation to the jury, counsel repeated that “the amount of profit goes to whether or not these damages were actually sustained.” 11 In other words, Brooks-Skinner contended at trial — and repeats the argument here —that evidence of an overall profit on the SEA Project tended to disprove Construction’s allegation that it actually suffered a loss because of the subcontractor’s delay, or at least indicated that any loss incurred was not as great as alleged.

Under ordinary circumstances, there would be serious doubt whether the evidence of profits bore the indispensible hallmark of legal relevancy — that it had some tendency to make the existence of a material fact more probable or less probable than it would be without the evidence.12 To illustrate, suppose Construction had planned to earn $100,000 on the SEA Project, over costs of $500,000, or a 20 per cent profit. Then assume further that losses, proved to be directly attributable to Brooks-Skinner, reduced the expected profit to a realized amount of only $50,000, or 10 per cent. The fact that 10 per cent was in fact earned, or that 10 per cent was a “fair” profit in the industry, or that it was the greatest percentage profit ever made by Construction, appear largely irrelevant to the question in issue — whether, by reason of Brooks-Skinner’s delay, Construction earned less than the gross amount it had contracted to earn.

At the trial, however, Construction failed to introduce any evidence of its itemized costs for the project, notwithstanding that Brooks-Skinner had caused a subpoena to issue in an attempt to obtain such evidence from Construction. Without evidence of itemized costs, Brooks-Skinner could not develop, the extent to which Construction’s projected profit for those aspects of the work subcontracted to Brooks-Skinner exceeded the profit actually made. Under these circumstances, with the jury in the dark regarding Construction’s projected and actual profits for the portion of the job done by Brooks-Skinner, and thus unable to gauge the magnitude of the alleged loss with any precision, evidence of overall profit became at least arguably relevant. Evidence that tended to show that Construction had indeed garnered a very high profit on the whole project had, in these circumstances, some tendency to prove that Construction did not suffer a loss of profits, or that its loss could not have been very great. Based on such evidence, the jury might rationally have concluded that [431]*431Construction’s itemized cost and profit projections did not contemplate a greater profit than the high profit actually earned.

This is not to suggest that the challenged evidence of profits was in any sense conclusive as to the existence vel non of the alleged loss. But neither can it be said that, in the context of this case, the evidence was utterly without probative value.13 Thus we conclude that, standing alone, Construction’s assertion that the evidence was irrelevant does not warrant reversal of the district court’s judgment.

In sustaining the trial judge’s ruling on relevancy, we are mindful of the precept that:

“[A] trial court has a great latitude in ruling on the admissibility of evidence. His determination of legal relevancy is also an act of discretion not to be disturbed absent a clear showing of abuse.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
488 F.2d 427, Counsel Stack Legal Research, https://law.counselstack.com/opinion/construction-ltd-v-brooks-skinner-building-co-ca3-1973.