Construction Aggregates Corporation v. Hewitt-Robins, Incorporated

404 F.2d 505
CourtCourt of Appeals for the Seventh Circuit
DecidedJanuary 15, 1969
Docket16124_1
StatusPublished
Cited by42 cases

This text of 404 F.2d 505 (Construction Aggregates Corporation v. Hewitt-Robins, Incorporated) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Construction Aggregates Corporation v. Hewitt-Robins, Incorporated, 404 F.2d 505 (7th Cir. 1969).

Opinion

CUMMINGS, Circuit Judge.

This action was brought to recover damages for breach of implied warranties, assertedly arising from a contract to design and furnish a conveyor system. After a month-long jury trial, judgment was entered on the verdict for the defendant, resulting in this appeal.

In April 1962, plaintiff Construction Aggregates Corporation (“CAC”), was the successful bidder on a contract 1 for the construction of dikes enclosing approximately 60 square miles of the Dead Sea, forming “evaporation pans” to be used to extract minerals from which pot *507 ash could be produced. In order to construct the evaporation pans, it was necessary to move vast amounts of sand, gravel and rock from a large “borrow pit” to the Dead Sea contract site.

In May and June 1962, CAC representatives commenced discussing the conveyor system with Hewitt-Robins, Incorporated (“H-R”), with CAC exhibiting a proposed conveyor layout to H-R. CAC said that it would obtain some used conveyor equipment for the proposed system.

On May 25, 1962, H-R wrote CAC, offering for CAC’s consideration the “basis for a cost-plus contract to design, furnish and provide the necessary erection supervision for the subject earth moving conveyor system.”

A few weeks thereafter, CAC and H-R representatives conferred further, resulting in an exchange of letters dated June 15, 1962. CAC’s letter said that its understanding was that H-R would “furnish the necessary engineering services,” dividing the work between CAC and H-R “as may best suit the needs of the work.” CAC’s letter also said that it would give H-R preference in the purchase of equipment, but that CAC might purchase used conveyor equipment located in Little Valley, Utah, or other used equipment, to be utilized by H-R “to the greatest extent practicable in the design of the materials handling system.”

On the same date, H-R wrote CAC it understood that CAC was accepting HR’s cost-plus letter of May 25, 1962, which was to form the basis of a contract, and stated that H-R would have engineers in CAC’s offices within a few days to meet with CAC personnel “to determine the ultimate scheme so that design engineering can start.” H-R reported its understanding that it would furnish products of its own manufacture at prices offered to original equipment manufacturers, without competitive bidding. H-R’s letter also solicited a written agreement.

After further negotiations, H-R wrote CAC on June 20, 1962, that it would proceed with the project as a result of telephone agreements reached bétween certain officers of CAC and H-R and agreed to give additional discounts on its products. The letter thanked CAC for accepting H-R’s proposal and concluded that H-R was looking forward to receiving CAC’s purchase order, which was supposed to refer to H-R’s letters of May 25, June 15 and June 20.

On June 27, 1962, H-R’s Melrose Park, Illinois, office advised its New York office that CAC had assigned purchase order No. 16112 for the Dead Sea project, and that when the actual purchase order was received, Melrose Park would send it to New York for acceptance. The memorandum concluded as follows:

“This contract has been negotiated on the basis of a cost/plus letter written on May 25, 1962, by R. W. Eichen-berger. Copies of this cost/plus letter and other pertinent correspondence have been sent to our Legal Department at Stamford for approval. It is not certain at this time whether Construction Aggregates will write their own version of the purchase order or whether they will accept our cost/plus letter. Upon clarification of this matter, it is suggested that the Legal, Contract Administration and Sales Departments get together to insure that we have the necessary terms and conditions included in our contract to minimize our risk and exposure.”

On the same date, H-R issued a “contract authority” booking the work in question, although an H-R representative testified that the work would be stopped and the bookings reduced if the contract were not consummated.

On June 30, 1962, CAC sent H-R a letter the purpose of which was “to set forth the final agreement” between the two companies and asking H-R to send its confirmation to CAC. On July 5, 1962, H-R’s Melrose Park office forwarded CAC’s purchase order No. 16112, dated July 3, 1962, to its New York office, stating that H-R’s representatives had “indicated to C.A.C. that this order is not accepted by H-R until one of our *508 corporate officers approves of all conditions and agreements.”

On July 20, 1962, H-R sent CAC the executed acceptance copy of its purchase order No. 16112, but stating that H-R’s acceptance was predicated on certain modifications, including a substitute warranty clause providing as follows:

“This warranty is in lieu of all other warranties expressed or implied.
The Seller warrants that machinery and/or machinery parts to be manufactured by it shall be free from defects in workmanship and material. Such warranty shall be binding upon the Seller for a period of one year from and after delivery of such equipment. If, at any time within such period, it is established to the Seller’s satisfaction that any machinery, part or parts manufactured by the Seller were defective at time of delivery, the Seller shall promptly furnish replacements of or repair such items. It is understood that the Seller’s liability under this warranty shall be limited to such repair or replacement. Rubber products manufactured by the Seller are not warranted for any specific length of time or measure of service. In the event of failure of such rubber products through defects, the Seller will at its option make replacement or refund, after charging for the service already rendered by the defective products; but in any event, the Seller’s liability under this warranty is limited to the refund of the purchase price.
Any parts or equipment which the Seller does not manufacture shall be subject only to the warranties of the Seller’s vendors.
Unless repairs to, alterations of, or work done on said equipment by the Purchaser, shall be specifically authorized in writing by the Seller, any warranty applicable thereto shall become null and void.”

The July 20th letter also absolved H-R of liability “for any loss of profits or any indirect or consequential damages.” CAC made no written objection to the terms of this letter. But on July 31, 1962, its treasurer telephoned a representative of H-R, requesting a change only in the terms of payment set forth in said letter. These changes were accepted in an H-R letter dated July 31, 1962, referring to the previous letter setting forth H-R’s conditions for acceptance. CAC made no objection to this reference or to the other terms H-R had imposed.

On July 31, 1962, CAC purchased three used conveyor systems from the Southern Pacific Company, which were incorporated into the Dead Sea project. Ninety per cent of the electric motors and other electrical equipment used by CAC was second-hand.

CAC commenced the construction of the conveyor system in Israel in late October or early November of 1962. The plant did not operate satisfactorily.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Westfield Insurance Company v. Dynacom Management, Inc
2022 IL App (1st) 191804-U (Appellate Court of Illinois, 2022)
Klocek v. Gateway, Inc.
104 F. Supp. 2d 1332 (D. Kansas, 2000)
Lambert v. Kysar
First Circuit, 1993
Major Mat Company v. Monsanto Company
969 F.2d 579 (Seventh Circuit, 1992)
W.A. Taylor & Co. v. Griswold & Bateman Warehouse Co.
719 F. Supp. 697 (N.D. Illinois, 1989)
Roma Tool & Plastics, Inc. v. Battenfeld of America, Inc.
705 F. Supp. 1380 (D. Minnesota, 1989)
Dresser Industries, Inc. v. Gradall Co.
702 F. Supp. 726 (E.D. Wisconsin, 1988)
Fratello v. Socorro Electric Cooperative, Inc.
758 P.2d 792 (New Mexico Supreme Court, 1988)
Casio, Inc. v. S.M. & R. Co., Inc.
755 F.2d 528 (Seventh Circuit, 1985)
Daitom, Inc. v. Pennwalt Corporation
741 F.2d 1569 (Tenth Circuit, 1984)
United States v. Construction Aggregates Corp.
559 F. Supp. 414 (E.D. Michigan, 1983)
US for Use of US Steel v. Const. Aggregates
559 F. Supp. 414 (E.D. Michigan, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
404 F.2d 505, Counsel Stack Legal Research, https://law.counselstack.com/opinion/construction-aggregates-corporation-v-hewitt-robins-incorporated-ca7-1969.