Conopco, Inc. v. Allen & Hoshall, Inc.

129 F. App'x 131
CourtCourt of Appeals for the Sixth Circuit
DecidedFebruary 22, 2005
Docket03-6635
StatusUnpublished
Cited by1 cases

This text of 129 F. App'x 131 (Conopco, Inc. v. Allen & Hoshall, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Conopco, Inc. v. Allen & Hoshall, Inc., 129 F. App'x 131 (6th Cir. 2005).

Opinion

PER CURIAM.

Plaintiff-Appellant Conopeo Incorporated (“Slim-Fast”) appeals the district court order of summary judgment for the defendant, an architectural firm, on claims of breach of contract and professional negligence. Slim-Fast argues that summary judgment is inappropriate because the contract at issue is ambiguous and because a reasonable person could conclude the defendant violated its professional duty. For the reasons stated below, we affirm.

I

This is diversity case about the construction of a floor in Slim-Fast’s warehouse in Covington, Tennessee. Slim-Fast hired Allen & Hoshall (“A & H”), an architectural firm, to design the warehouse, including the floor. Slim-Fast wanted a white concrete floor in the warehouse. A & H submitted a design for the warehouse, including the floor, on December 12, 1997. Pursuant to Tennessee law, Tenn.Code Ann. § 62-2-306, A & H submitted its design under the firm’s seal. That design was used to solicit bids from contractors. Linkous Construction Company (“Linkous”) was then selected to serve as the contractor.

Before construction began, Slim-Fast rejected A & H’s floor design. Not just any floor would do; Slim-Fast wanted a white floor. Slim-Fast first asked A & H to develop a concrete mix that would make the floor white, but A & H declined because of a lack of expertise with concrete mixes. Then, in the summer of 1998, Slim-Fast retained William B. Allen of Allen & Associates (“Allen”) to develop another design for the floor. On October 7, 1998, Slim-Fast directed Linkous to build the floor in accordance with Allen’s design. On October 8, 1998, Allen formally submitted a floor design with several modifications to the original A & H design. Specifically, Allen recommended 1) elimination of wire mesh reinforcement, 2) using dowels at all construction and control joints, and 3) using Eucosil to cure the concrete. Before the floor was poured, A & H was asked by Slim-Fast to approve the new floor design. Again, A & H declined because of a lack of expertise with “slag” (the mixed concrete employed here to make the floor white).

Linkous poured the concrete for the floor on October 19-21, 1998. On November 10, 1998, A & H submitted to Slim-Fast Amendment 1 (the “Amendment”). The Amendment was drafted by Allen and incorporated all the changes Allen had recommended. It is not disputed that A & H had no part in the design alterations in the Amendment. No seal was included in the Amendment, and the documents indicate , that the floor design was done by Allen.

The floor proved defective. Slim-Fast claims that the design and construction of the floor was improper, which led to the “curling” of the slabs in the warehouse floor. Slim-Fast’s experts have identified four potential causes: 1) the use of Eucosil to cure the concrete, 2) the failure of Lin *133 kous to install dowels in the control joints, 3) the use of a vapor barrier, and 4) the elimination of the wire mesh reinforcement.

Slim-Fast sued A & H for breach of contract and professional negligence. 1 On August 21, 2003, the district court resolved cross summary judgment motions by holding for the defendant on all claims. Slim-Fast’s breach of contract claim had two components: first, liability for the defective floor design; second, liability for the failure of the contractor to construct the floor in accordance with the design. The district court concluded that A & H was not liable for the floor design in light of Slim-Fast’s undisputed rejection of A & H’s design and solicitation of a replacement design from Allen. The court further concluded that A & H was under no contractual obligation to inspect or supervise the construction of the warehouse. Finally, the district court concluded that the professional negligence claim simply duplicated the breach of contract claim for faulty design, and that the defendant could not be liable for professional negligence for alleged omissions that were not within A & H’s contractual duties.

II

We review a grant of summary judgment motion de novo, taking all facts in the light most favorable to the non-moving party. Shamaeizadeh v. Cunigan, 338 F.3d 535, 543-44 (6th Cir.2003).

It is not disputed that Tennessee law governs. In diversity cases, we apply the choice of law doctrine of the state in which the district court sits. Cole v. Mileti, 133 F.3d 433, 437 (6th Cir.1998). The contract specifies that Tennessee law governs. Tennessee will honor such choice of law provisions if it shows a reasonable relationship to the transaction, unless it violates the public policy of the forum state. Tenn. Code Ann. § 47-1-105; Arcata Graphics Co. v. Heidelberg Harris, Inc., 874 S.W.2d 15, 27 (Tenn.Ct.App.1993). For tort claims, including the professional negligence claim in this case, Tennessee applies a “most significant relationship” test. Hataway v. McKinley, 830 S.W.2d 53, 59 (Tenn.1992). The events at issue — including the formation of the contract, the floor designing, and the construction — all took place in Tennessee. This satisfies the “most significant relationship” tort law test and “reasonably related to the transaction” contract law test.

A

“The cardinal rule for interpretation of contracts is to ascertain the intention of the parties from the contract as a whole and to give effect to that intention consistent with legal principles.” Sherman v. Am. Water Heater Co., Inc., 50 S.W.3d 455, 457-58 (Tenn.Ct.App.2001). “[A] contract’s provisions must be interpreted in the context of the entire contract, viewed from beginning to end and all its terms must pass in review, for one clause may modify, limit or illustrate another.” D & E Const. Co., Inc. v. Robert J. Denley Co., Inc., 38 S.W.3d 513, 519 (Tenn.2001) (citations omitted). Whether a contract is ambiguous is a question of law for the court. Bratton v. Bratton, 136 S.W.3d 595, 601 (Tenn.2004).

A & H’s basic duties under the contract are set out in Article 2, under the title “Basic Services.” The principal duty is to provide “Construction Documents” that set out the requirements for construction and *134 are suitable for bidding.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
129 F. App'x 131, Counsel Stack Legal Research, https://law.counselstack.com/opinion/conopco-inc-v-allen-hoshall-inc-ca6-2005.