JWM Memphis, LLC v. Terracon Consultants, Inc.

CourtDistrict Court, W.D. Tennessee
DecidedMarch 27, 2025
Docket2:24-cv-02316
StatusUnknown

This text of JWM Memphis, LLC v. Terracon Consultants, Inc. (JWM Memphis, LLC v. Terracon Consultants, Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
JWM Memphis, LLC v. Terracon Consultants, Inc., (W.D. Tenn. 2025).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE WESTERN DISTRICT OF TENNESSEE WESTERN DIVISION

JWM MEMPHIS, LLC, ) ) Plaintiff, ) ) No. 2:24-cv-02316-TLP-atc v. ) ) JURY DEMAND TERRACON CONSULTANTS, INC., ) ) Defendant. )

ORDER ON MOTION TO DISMISS

Plaintiff JWM Memphis, LLC (“JWM”) sued Defendant Terracon Consultants, Inc. (“Terracon”) in the Circuit Court of Shelby County for negligence, professional negligence, fraudulent and negligent misrepresentation, fraudulent concealment, civil conspiracy, and breach of warranty. (ECF No. 1-1.) Terracon then removed the case to federal court (ECF No. 1) and moved to dismiss (ECF No. 14). JWM opposed the motion. (ECF No. 17.) And Terracon replied. (ECF No. 19.) For the reasons explained below, the Court GRANTS in part and DENIES in part the motion to dismiss. BACKGROUND In January 2020, Terracon entered an agreement with TPA Group, LLC (“TPA”) to perform certain geotechnical engineering services on soil for the Memphis Airport Logistics Center Project (“Project” or “Property”).1 (ECF No. 1-1 at PageID 5; ECF No. 14-2 at PageID

1 The Project was “a newly constructed, large warehouse structure with a building footprint of over one million (1,000,000) square feet, located at 5300 Airways Boulevard, Memphis, Shelby County, Tennessee.” (ECF No. 1-1 at PageID 5.) TPA, or its related entity Holmes Airways Partners, LLC, owned the Property. (Id.; ECF No. 14-1 at PageID 572 n.2.) There seems to be 595.2) According to the Complaint, Terracon agreed to “explore, test, and perform geotechnical engineering of the existing soils and subsurface conditions for the construction of future warehouse buildings.” (ECF No. 1-1 at PageID 5; see ECF No. 14-2 at PageID 595–96 (initial contract between TPA and Terracon).) And in August 2020, Holmes Airways Partners, LLC

(“Holmes”), in care of TPA, hired Evans General Contractors, LLC (“Evans”) to build the buildings for the Project on the soil Terracon had tested. (ECF No. 1-1 at PageID 8.) Evans began working on the site in September. (ECF No. 1-1 at PageID 8.) Then in October, Terracon and TPA entered a second agreement under which Terracon would “supervise, observe, inspect, report and test the earthwork activities during the construction of the Project” on an “as-requested basis” (collectively with the initial agreement, the “Contracts”). (ECF No. 1-1 at PageID 8; ECF No. 14-2 at PageID 755; see ECF No. 14-2 at PageID 762–63.) Just over a year later, in December 2021, Terracon’s Senior Engineer for the Project issued a signed, stamped letter “confirming that Terracon’s monitoring and testing of the soils that were placed and compacted on the Project were conducted under the supervision of a

registered, Terracon engineer and in accordance with the Project specifications and local soil engineering practices.” (ECF No. 1-1 at PageID 8; ECF No. 14-2 at PageID 765 (letter confirming test results that the earthwork complied with Project plans, documents, and

some dispute on this point, but, because it is a distinction without difference at this stage, the Court will use the facts from the Complaint. (See ECF No. 1-1 at PageID 5; ECF No. 14-1 at PageID 572 n.2.) After all, on a motion to dismiss, the Court accepts a plaintiff’s factual allegations as true anyway. See Marchek v. United Servs. Auto. Ass’n, 118 F.4th 830, 833 (6th Cir. 2024). 2 Because this case arrived here by notice of removal, the Complaint and its attachments were scanned and uploaded in a difficult-to-read and low-resolution format. (See ECF No. 1-1 at PageID 24–540.) Terracon attached clean, color versions of these exhibits to its motion to dismiss to facilitate review of them. (ECF No. 14-1 at PageID 571 n.1; ECF No. 14-2.) The Court cites these cleaner versions but considers them part of the Complaint. specifications and with soil engineering requirements).) The Project received a Certificate of Occupancy in March 2022. (ECF No. 1-1 at PageID 8.) In May and June 2022, J.W. Mitchell Company, LLC purchased the Property from Holmes through a Purchase and Sale Agreement.3 (ECF No. 1-1 at PageID 9.) And about a

week after obtaining the Property, J.W. Mitchell Company, LLC entered into an Assignment and Assumption of Purchase and Sale Agreement for the Property with JWM, making Plaintiff the owner of the Property. (ECF No. 1-1 at PageID 9.) Then JWM and Holmes entered an Assignment of Intangible Property, which included, among other things, a “post-construction completion one-year warranty” from Evans. (ECF No. 1-1 at PageID 9.) Holmes also transferred title to the Property to JWM by Special Warranty Deed, filed with the Office of the Shelby County Register on July 11, 2022. (ECF No. 1-1 at PageID 9.) A few months later, in September, the Property’s tenant Medtronic Logistics, LLC (“Medtronic”) noticed that the concrete slab of the Project had cracked. (ECF No. 1-1 at PageID 9.) Evans refused to make repairs under the one-year warranty and denied liability. (ECF No. 1-

1 at PageID 9.) So Medtronic, through its contractor and expert, conducted additional testing and reports that showed the soil underneath it had “voids and consolidation” and were not compacted with the proper moisture content “as required and represented by Terracon.” (ECF No. 1-1 at PageID 9–10.) Medtronic then undertook the repairs, which cost over $2,000,000, and demanded JWM pay for them. (ECF No. 1-1 at PageID 10.) JWM now seeks to recover those sums through arbitration with Evans and this litigation with Terracon. (ECF No. 1-1 at PageID 10–11.)

3 JWM does not allege that this Purchase and Sale Agreement assigned either contract with Terracon to J.W. Mitchell Company, LLC or to JWM. (See ECF No. 1-1.) And the Parties have stipulated that there was no assignment. (ECF No. 19 at PageID 1183–84.) The many layers of contractors, subcontractors, and holding companies make these facts confusing. But, disregarding some of these technicalities of ownership, a simple summary of the facts and allegations is this: TPA hired Terracon to perform geotechnical engineering services and hired Evans to construct the Project on soil Terracon tested. TPA then sold the Property to

JWM, and a few months later, JWM’s tenant Medtronic noticed the Project’s concrete floor had cracked. Evans denied that the cracks were its fault, and Medtronic’s agents and experts believed defects in the soil caused the cracks, which allegedly relates to Terracon’s work and contractual obligations. Medtronic made $2,000,000 in repairs and apparently recovered that sum from JWM, who then sought recovery from Evans in arbitration and from Terracon in this Court. Before this Court are JWM’s claims against Terracon for negligence, professional negligence, fraudulent and negligent misrepresentation, fraudulent concealment, civil conspiracy, and breach of warranty. STANDARD To survive a motion to dismiss, the plaintiff generally must plead “only enough facts to

state a claim to relief that is plausible on its face.” Bell Atlantic Corp. v. Twombly, 550 U.S. 544, 570 (2007). But claims for fraud, like intentional misrepresentation and fraudulent concealment, must be “pled with particularity” under Federal Rule of Civil Procedure 9(b). United States ex rel. Angelo v. Allstate Ins. Co., 106 F.4th 441, 448 (6th Cir. 2024) (stating that fraud claims have a heightened pleading standard); see also Saltire Indus., Inc. v. Waller, Lansden, Dortch & Davis, PLLC, 491 F.3d 522, 526–27 (6th Cir. 2007) (applying the heightened pleading standard for fraud to “all averments of fraud or mistake”); Fed. R. Civ. P. 9

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Tina Marie Hodge v. Chadwick Craig
382 S.W.3d 325 (Tennessee Supreme Court, 2012)
Estate of Morris v. Morris
329 S.W.3d 779 (Court of Appeals of Tennessee, 2009)
Joseph Davis v. Patrick J. McGuigan - Dissenting
325 S.W.3d 149 (Tennessee Supreme Court, 2010)
Doug Satterfield v. Breeding Insulation Company
266 S.W.3d 347 (Tennessee Supreme Court, 2008)
Robinson v. Omer
952 S.W.2d 423 (Tennessee Supreme Court, 1997)
Professional Lens Plan, Inc. v. Polaris Leasing Corp.
675 P.2d 887 (Supreme Court of Kansas, 1984)
Shadrick v. Coker
963 S.W.2d 726 (Tennessee Supreme Court, 1998)
Kincaid v. SouthTrust Bank
221 S.W.3d 32 (Court of Appeals of Tennessee, 2006)
Briggs v. Riversound Ltd. Partnership
942 S.W.2d 529 (Court of Appeals of Tennessee, 1996)
Bradshaw v. Daniel
854 S.W.2d 865 (Tennessee Supreme Court, 1993)
Trau-Med of America, Inc. v. Allstate Insurance Co.
71 S.W.3d 691 (Tennessee Supreme Court, 2002)
John Martin Co. v. Morse/Diesel, Inc.
819 S.W.2d 428 (Tennessee Supreme Court, 1991)
Ritter v. Custom Chemicides, Inc.
912 S.W.2d 128 (Tennessee Supreme Court, 1995)
Bethlehem Steel Corp. v. Ernst & Whinney
822 S.W.2d 592 (Tennessee Supreme Court, 1991)
Benson v. Tennessee Valley Electric Cooperative
868 S.W.2d 630 (Court of Appeals of Tennessee, 1993)
Dixon v. Mountain City Construction Co.
632 S.W.2d 538 (Tennessee Supreme Court, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
JWM Memphis, LLC v. Terracon Consultants, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/jwm-memphis-llc-v-terracon-consultants-inc-tnwd-2025.