Connecticut L P v. Dept. of P.U.C., No. Cv92 070 37 77 (Dec. 2, 1993)

1993 Conn. Super. Ct. 10464, 9 Conn. Super. Ct. 82
CourtConnecticut Superior Court
DecidedDecember 2, 1993
DocketNo. CV92 070 37 77
StatusUnpublished

This text of 1993 Conn. Super. Ct. 10464 (Connecticut L P v. Dept. of P.U.C., No. Cv92 070 37 77 (Dec. 2, 1993)) is published on Counsel Stack Legal Research, covering Connecticut Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Connecticut L P v. Dept. of P.U.C., No. Cv92 070 37 77 (Dec. 2, 1993), 1993 Conn. Super. Ct. 10464, 9 Conn. Super. Ct. 82 (Colo. Ct. App. 1993).

Opinion

[EDITOR'S NOTE: This case is unpublished as indicated by the issuing court.] MEMORANDUM OF DECISION The plaintiff Connecticut Light Power Company (CLP) appeals a decision of the defendant Department of Public Utility Control (DPUC) in its Docket No. 90-02-03. CT Page 10465 The DPUC's decision followed an investigation pursuant to General Statutes 16-8 and an extended hearing at which all parties participated and furnished evidence. In addition, the DPUC had a report from an independent expert, RCG/Hagler, Bailly, Inc. (RCG), that it had hired pursuant to General Statutes 16-8 (b)(3). The plaintiff appeals pursuant to General Statutes 4-183. The appeal is sustained in part and dismissed in part.

CLP is a public service company, as defined in General Statutes 16-1, that provides retail electric service to ratepayers in Connecticut. The DPUC is the state agency which is charged with the regulation and supervision of public service companies and the establishment of retail electric service rates, pursuant to chapter 277 of the general statutes. CLP purchases electric power at wholesale from the Connecticut Yankee Atomic Power Company (CYAPCO). Such wholesale transactions, including the wholesale rates, are regulated by the Federal Energy Regulatory Commission (FERC).

CLP owns a 34.5% interest in CYAPCO and is entitled to a proportionate share of its electrical power output. Pursuant to the wholesale electric power contract between the companies, CYAPCO charges CLP a proportionate share of CYAPCO's operational costs as part of the wholesale rate structure. FERC has formally approved this contract, including the rate structure.

In 1989, during a scheduled refueling shutdown of CYAPCO, the DPUC learned that the shutdown would be extended beyond its planned duration. The extension was needed to deal with the failure of the thermal shield, which had been repaired during a previous refueling shutdown in 1987/1988. CYAPCO had discovered that the previous repairs to the thermal shield had failed. In addition to damage caused by excessive wear and tear on various components of the shield, a large number of fuel rods had been damaged by debris which had been left in the reactor following the previous repairs.

As a result of these discoveries, CYAPCO decided to remove the thermal shield entirely.

The 1989/1990 refueling process, including the removal CT Page 10466 of the thermal shield, repair of the fuel rods, and removal of the debris left over from the previous repairs took three hundred forty-six days. An additional forty-four days was required to bring the plant back to 100% power. In the report it submitted to the DPUC, the consultant, RCG, found that 28.5 days of the total shutdown period were attributable to the debris clean-up. CLP disputes this finding, among others, claiming that only 16 days of the shutdown should be attributed to debris clean-up. In its final decision, which is the subject of this appeal, the DPUC adopts the finding of its consultant, 28.5 days.

In its decision, the DPUC found that CYAPCO had acted imprudently in its nuclear power plant operation in that CYAPCO failed to take reasonable steps to ensure that foreign materials were not left in the reactor vessel. Specifically, the DPUC found that the company's foreign materials exclusion procedure was deficient in that it required only one person to verify the removal of foreign objects. In this regard, the DPUC found that the company should have required that at least two people independently verify the removal of foreign objects. As evidence of this deficiency, a device known as an "annulus stuffer," which the company had placed in the reactor to serve as a debris barrier during the 1987/1988 shutdown, was discovered to have been inadvertently left in the reactor.

The DPUC further found that CYAPCO failed to take reasonable steps to remove debris generated by the 1987/1988 refueling and repair operation. Specifically, the DPUC found that CYAPCO should have undertaken additional underwater vacuuming, known as "swarping", in the reactor vessel.

The DPUC's findings that certain acts or, rather, omissions of CYAPCO were imprudent, led to the conclusions and orders that give rise to this appeal. As indicated above, pursuant to the wholesale contract, a proportionate share of CYAPCO's operating costs and expenses are passed on to CLP in the wholesale rate, ultimately to be paid by CLP's ratepayers. Such operating costs and expenses included, in this case, those incurred by CYAPCO for the debris clean-up and removal. As a result of CLP's ownership interest in CYAPCO, the DPUC also concluded that any imprudence on the part of CYAPCO management is CT Page 10467 imputable to the full extent to CLP. CLP does not dispute that it is fully accountable for CYAPCO's imprudence. The DPUC further concluded, however, that it has the power to order that the costs associated with such imprudence not be borne by CLP's ratepayers. The DPUC found that the costs and expenses of the 1989/1990 cleanup operation which were attributable to CYAPCO's imprudence amounted to $230,000, and it ordered that that amount be deducted from the total cleanup costs which the companies sought to charge to CLP's ratepayers. CLP does dispute this order.

A significant additional expense incurred by CLP as result of the shutdown of the nuclear power plant was the cost of replacement power it had to purchase and supply to its ratepayers during the shutdown. The total cost of this replacement power for the entire shutdown period was $39,953,000. of that sum, $3,003,000 was incurred during the 28.5 days of shutdown that the DPUC found was caused by CYAPCO's imprudence. Accordingly, the DPUC ordered that that amount be deducted from the total cost of replacement power to be paid by the ratepayers.

During the 1989/1990 shutdown, CLP was insured against the cost of extended shutdowns, collectible after a twenty-one week deductible period. CLP collected $6,300,000 on this insurance for the shutdown. The DPUC found that the evidence did not establish that the insurance was payable solely as a result of the 28.5 day shutdown period which was related to CYAPCO's imprudence. Even if the 28.5 day period was the sole insurance triggering event, however, the DPUC concluded that the proceeds could not be applied to reduce or erase the costs associated with that period. To do so, the DPUC reasoned, would have the effect of charging the ratepayers for the imprudence of the utility companies. In this regard, the DPUC noted that the ratepayers were being charged approximately $25,000,000 even without the costs associated with the "imprudence period". In order to give full benefit of the insurance to the ratepayers, the DPUC ordered that the proceeds be applied first to the costs of the shutdown that are not associated with the utilities' imprudence. This, of course, would totally exhaust the proceeds.

CLP raises three issues as the bases of its appeal of the DPUC's orders. They may be summarized as follows: CT Page 10468

1. The order disallowing CLP's recovery from its ratepayers of $230,000 of costs charged by CYAPCO violates the supremacy clause of the United States constitution and is preempted by federal law.

2. The DPUC erroneously found that CYAPCO's acts and/or omissions following the 1987/1988 refueling operation were imprudent. The order that CLP not collect or refund to its ratepayers $3,003,000 of power replacement costs, which was based on the finding of imprudence, was therefore, in error.

3.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
1993 Conn. Super. Ct. 10464, 9 Conn. Super. Ct. 82, Counsel Stack Legal Research, https://law.counselstack.com/opinion/connecticut-l-p-v-dept-of-puc-no-cv92-070-37-77-dec-2-1993-connsuperct-1993.