Conmac Corp. v. Southern Diversified Development, Inc.

539 S.E.2d 532, 245 Ga. App. 895, 2000 Fulton County D. Rep. 3879, 2000 Ga. App. LEXIS 1143
CourtCourt of Appeals of Georgia
DecidedSeptember 14, 2000
DocketA00A1124, A00A1125
StatusPublished
Cited by8 cases

This text of 539 S.E.2d 532 (Conmac Corp. v. Southern Diversified Development, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Georgia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Conmac Corp. v. Southern Diversified Development, Inc., 539 S.E.2d 532, 245 Ga. App. 895, 2000 Fulton County D. Rep. 3879, 2000 Ga. App. LEXIS 1143 (Ga. Ct. App. 2000).

Opinion

Ellington, Judge.

In Case No. A00A1124, Conmac Corporation appeals from the Fulton County Superior Court’s order vacating the modification of an arbitration award Conmac obtained against Southern Diversified Development, Inc. (“SDDI”). In Case No. A00A1125, Conmac appeals from the trial court’s denial of its emergency motion to enter judgment against intervenor Continental Casualty Company (“Continental”). Finding no error, we affirm.

In December 1996, SDDI hired Conmac to build a multi-story condominium building in northwest Atlanta. The construction contract specified that disputes would be arbitrated pursuant to the Construction Industry Arbitration Rules of the American Arbitration Association (“AAA”). When SDDI refused to pay for construction work performed by Conmac, Conmac filed a $907,553 Claim of Lien against SDDI’s property on February 4, 1998. Two days later, Con-mac sued SDDI for breach of contract, quantum meruit, lien foreclosure, tortious interference with contractual relations, fraud, business defamation, and conversion. Conmac demanded arbitration under the contract, and the trial court stayed the case pending arbitration.

SDDI filed a bond discharging the lien on April 20, 1998. See OCGA § 44-14-364. The bond named Continental as surety. Although Continental was not named in the lawsuit and did not participate in the arbitration, it was permitted to intervene on June 10, 1999.

Conmac and SDDI presented extensive evidence of their claims and counterclaims to an arbitration panel during 16 days of hearings. On February 2, 1999, the arbitrators awarded Conmac $978,185 in damages, pre-judgment interest from December 10, 1997, plus post-judgment interest. In addition, the award stated that: “All other claims of The CONMAC CORPORATION are denied”; “The claims of [SDDI] are denied”; and “This Award is in full settlement of all claims submitted to this arbitration.”

Conmac immediately filed a motion to “clarify and modify” the arbitrators’ award, pursuant to Rule 44 of the AAA’s Construction Industry Arbitration Rules. Rule 44 allows a party to request an arbi *896 trator to correct “any clerical, typographical, technical or computational errors in the award.” It also prohibits an arbitrator from redetermining the merits of any claim already decided. According to Conmac’s motion, the award did not “specifically address one of the issues which the parties agreed to submit to the Arbitrators for a decision; specifically, whether the Claim of Lien ... is valid.” SDDI objected to any modification of the award, asserting that the award clearly denied Conmac’s entitlement to the lien. In March 1999, the arbitration panel issued a modified award which stated that Conmac “is entitled to a mechanics lien against the property of [SDDI] in the amount of [the] Award.”

On April 13, 1999, Conmac moved the trial court to confirm the arbitrators’ award, as modified, pursuant to OCGA § 9-9-12; to lift the stay on the proceedings; and to enter judgment on the award. SDDI opposed Conmac’s motion and moved to vacate the award. The trial court confirmed the original award of $978,185 plus interest, but ruled that the arbitration panel had overstepped its authority by modifying the merits of this award when none of the grounds for modification under OCGA § 9-9-11 (a) had been met. Based upon this finding, the trial court vacated the modification.

Case No. A00A1124

Conmac appeals only from that portion of the trial court’s order vacating the modification. 1

1. Conmac argues that the trial court failed to apply the proper standard for vacating the modification, so that SDDI was relieved of its responsibility to prove that it was prejudiced by the modification. The record demonstrates, however, that the trial court utilized the proper standard and that its decision to vacate the modification was supported by sufficient evidence.

(a) Under OCGA § 9-9-13 (b), a trial court shall vacate an arbitration panel’s award only if it finds that a party was prejudiced by one of four bases, including an “overstepping by the arbitrators of their authority.” OCGA § 9-9-13 (b) (3). See Greene v. Hundley, 266 Ga. 592, 594-595 (1) (468 SE2d 350) (1996) (holding that the four bases listed in the Arbitration Code are the exclusive grounds for vacating an arbitration award, and that the Arbitration Code must be strictly construed). In this case, the trial court vacated the modification under OCGA § 9-9-13 (b) (3) after finding that the arbitration panel had overstepped its authority by modifying, the merits of its award, when none of the statutory grounds for modification under *897 OCGA § 9-9-11 (a) 2 had been met. As the trial court utilized the proper statutory bases for vacating the modification, there was no error.

(b) Conmac challenges the trial court’s finding that the arbitration panel overstepped its authority. Conmac relies on language from cases which define “overstepping” narrowly as “addressing issues not properly before the arbitrator.” (Citations and punctuation omitted.) Haddon v. Shaheen & Co., 231 Ga. App. 596, 598 (1) (b) (499 SE2d 693) (1998). See also Ralston v. City of Dahlonega, 236 Ga. App. 386, 388 (3) (512 SE2d 300) (1999). Even under this limited definition of “overstepping,” however, the trial court’s decision to vacate is supported by the record.

In this case, the arbitration panel decided the merits of an issue which was not properly before them, as it had already been presented to them and rejected by them. It is undisputed that Conmac petitioned the arbitration panel to validate the existing lien against SDDI’s property and to allow its foreclosure. Under “other relief sought” in its demand for arbitration, Conmac noted that it requested foreclosure on the lien. In its pre-hearing brief, Conmac asked the arbitration panel to validate the lien. According to an affidavit signed by Conmac’s counsel, both Conmac and SDDI “made it clear” that they wanted the arbitrators to decide the issue of whether the lien was valid, and “extensive evidence on this issue was submitted by both parties at the hearings.” As the trial court specifically found in its order vacating the modification, “the timeliness of Con-mac’s lien was hotly disputed and this issue had specifically been submitted to the arbitration panel for decision.”

Even so, the arbitration panel failed to validate the lien in its original award to Conmac.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Docs of Ct, LLC v. Biotek Services, LLC
321 Ga. 588 (Supreme Court of Georgia, 2025)
Docs of Ct, LLC v. Biotek Services, LLC
Court of Appeals of Georgia, 2023
XIE LAW OFFICES, LLC v. HOU MIN LUO
Court of Appeals of Georgia, 2023
Magwell, LLC. v. Susan Wells-Wilson
Court of Appeals of Georgia, 2021
Debra Gray King v. Daniel Rosson King
Court of Appeals of Georgia, 2020
City of Gainesville v. Dodd
573 S.E.2d 369 (Supreme Court of Georgia, 2002)
Ghertner v. Solaimani
563 S.E.2d 878 (Court of Appeals of Georgia, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
539 S.E.2d 532, 245 Ga. App. 895, 2000 Fulton County D. Rep. 3879, 2000 Ga. App. LEXIS 1143, Counsel Stack Legal Research, https://law.counselstack.com/opinion/conmac-corp-v-southern-diversified-development-inc-gactapp-2000.