Comtel Technologies, Inc. v. Paul H. Schwendener, Inc.

710 F. Supp. 2d 704, 2010 U.S. Dist. LEXIS 29178, 2010 WL 1257766
CourtDistrict Court, N.D. Illinois
DecidedMarch 26, 2010
DocketCase 04 C 3879
StatusPublished

This text of 710 F. Supp. 2d 704 (Comtel Technologies, Inc. v. Paul H. Schwendener, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Comtel Technologies, Inc. v. Paul H. Schwendener, Inc., 710 F. Supp. 2d 704, 2010 U.S. Dist. LEXIS 29178, 2010 WL 1257766 (N.D. Ill. 2010).

Opinion

MEMORANDUM OPINION AND ORDER

VIRGINIA M. KENDALL, District Judge.

Plaintiffs Comtel Technologies, Inc. (“Comtel”) and Solai & Cameron (“Solai”) (collectively “Plaintiffs”) brought suit against Paul H. Schwendener, Inc. (“PHS”) and Nuline Technologies (“Nu-line”) alleging violations of Plaintiffs’ civil rights and bringing various tort claims related to Plainfield school construction projects for which PHS was the general contractor and the other parties were electrical subcontractors. Defendant American Home Assurance Company (“American”) issued a payment surety bond (“the Bond”) to PHS in connection with two relevant projects, the Plainfield Fourth Middle School (“the Middle School *706 Project”) and the Plainfield Second High School (the “High School Project”) (collectively “the Projects”). The Court has supplemental jurisdiction over Plaintiffs’ bond claims against American pursuant to 28 U.S.C. § 1367(a).

American now moves for summary judgment on the grounds that Plaintiffs’ suit to recover under the Bond was not timely filed and that Plaintiffs’ claims are barred by the doctrine of res judicata. For the reasons set forth below, American’s Motion for Summary Judgment is granted.

UNDISPUTED FACTS

I. The Underlying Contracts

PHS entered into a construction contract (“the Contract”) with the Plainfield Community Consolidated School District No. 202 (“the District”) on April 5, 2001. (Pl. 56.1 Resp. ¶ 5.) 1 The Contract provided for four school construction projects, including the Middle School Project and the High School Project that are at issue here. (Pl. 56.1 Resp. ¶ 6.) Healy, Snyder, Bender & Associates, Inc. (“HSB”) was the architect for the two projects. (Pl. 56.1 Resp. ¶ 7.)

The Contract provided that the projects would be deemed “substantially complete” when they were “sufficiently complete in accordance with the Contract Documents so that the Owner can occupy or utilize the Work for its intended use.” (Pl. 56.1 Resp. ¶ 8.) The Contract further stated that when each project “or designated portion thereof is substantially complete, the Architect will prepare a Certificate of Substantial Completion which shall establish the date of Substantial Completion .... ” (Pl. 56.1 Resp. ¶ 9.) The Contract required the projects to be substantially completed on or before July 15, 2002, and stated that the District would pay a bonus of $2,000 for each day prior to July 15 that each of the two projects was substantially complete. (Pl. 56.1 Resp. ¶ 11.) The Contract also contained a liquidated damages clause allowing the assessment of $2,000 in damages for each day following July 15 that the projects were not ready. (Pl. 56.1 Resp. ¶ 11.)

PHS obtained a Payment Bond for the Contract with American as the listed surety. (Pl. 56.1 Resp. ¶ 12.) The Bond provided that no suit could be brought more than one year following the earlier of the date on which the party bringing suit gave notice of a claim under the Bond or the last day on which any labor or service was performed or any materials or equipment were furnished under the Contract. (Pl. 56.1 Resp. ¶ 13.) 2 American and PHS also entered into a General Agreement of Indemnity, assigning to American all of PHS’s rights, claims, and defenses arising under the Bond. (Pl. 56.1 Resp. ¶ 14.)

PHS hired the Plaintiffs as the electrical subcontractor for the projects. (Pl. 56.1 Resp. ¶ 15.) Under their contracts with PHS, Plaintiffs were to be paid $1,108,840 for the Middle School Project, and $1,008,160 for the High School Project. (Pl. 56.1 Resp. ¶ 15.) Plaintiffs began work on the projects in June 2001; PHS subsequently terminated them from the Middle School Project on June 7, 2002 and from the High School Project on June 15, 2002. (Pl. 56.1 Resp. ¶¶ 16-18.)

*707 II. Completion of the Projects and Initial Claims

The High School Project reached substantial completion on July 5, 2002, upon which HSB issued a Certificate of Substantial Completion. (Pl. 56.1 Resp. ¶ 19.) The Middle School Project reached substantial completion on July 17, 2002, and a Certificate of Substantial Completion was issued that day. (Pl. 56.1 Resp. ¶ 21.) In both cases, the District took possession of the projects on the dates of substantial completion and assumed responsibility for their heat, electricity, water, security, and maintenance. (Pl. 56.1 Resp. ¶¶20, 22.) The District issued Certificates of Occupancy for both projects on August 26, 2002. (Pl. 56.1 Resp. ¶ 25.) In accordance with the Contract, the District agreed to pay PHS a $20,000 bonus for early completion of the High School Project and to assess $4,000 in liquidated damages for late completion of the Middle School Project. (Pl. 56.1 Resp. ¶ 26.)

On or about June 5, 2002, Plaintiffs notified American of a claim under the Bond in the amount of $537,118.30, which Plaintiffs claimed to be owed for labor and materials related to the Middle School Project. (Pl. 56.1 Resp. ¶ 27.) On the same day, Plaintiffs notified American of a Bond claim in the amount of $559,553.60 for labor and materials related to the High School Project. (Pl. 56.1 Resp. ¶ 28.)

III. Amended Claims

On December 3, 2002, Plaintiffs filed notice to American of additional Bond claims over and above those which they had originally claimed. (Pl. 56.1 Resp. ¶¶ 31, 32.) Plaintiffs’ amended claims sought an additional $1,152,915.70 over the original Bond claim for the High School Project, for a total claimed amount of $1,690,034; and an additional $336,041.99 over the original Bond claim for the Middle School Project, for a total claimed amount of $895,595.59. (Pl. 56.1 Resp. ¶¶ 31, 32.) These new claims (the “Change Order Claims”) were based upon asserted “Change Orders” amending the terms of Plaintiffs’ original contract with PHS and related to work “extra work performed by” Plaintiffs “which was not included in the original claim.” (Pl. 56.1 Resp. ¶¶ 30-32.) 3

IV. State and Federal Court Litigation

Plaintiffs filed suit on July 16, 2002, against American and others in the Will County, Illinois Circuit Court (the ‘‘Will County suit”) seeking recovery for their Bond claims as initially noticed to American. (Pl. 56.1 Resp. ¶ 29.) On June 29, 2004, more than eighteen months after notifying American of the new claims, Plaintiffs amended their state court complaint to reflect the amended claims regarding the High School Project. (Pl. 56.1 Resp. ¶ 35.) On July 8, 2004, Plaintiffs amended their state court complaint to reflect the new claims for the Middle School Project. (Pl. 56.1 Resp. ¶ 35.) In their amended complaints, Plaintiffs also asserted claims against American for “Unreasonable and Vexatious Delay,” which claims the state court dismissed without *708 prejudice on October 7, 2004. (PL 56.1 Resp. ¶ 36.)

On June 7, 2004, Plaintiffs filed this federal lawsuit, although American was not included as a Defendant at that time. (Pl. 56.1 Resp.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Cooter & Gell v. Hartmarx Corp.
496 U.S. 384 (Supreme Court, 1990)
Crop-Maker Soil Services, Inc. v. Fairmount State Bank
881 F.2d 436 (Seventh Circuit, 1989)
Albiero v. City Of Kankakee
246 F.3d 927 (Seventh Circuit, 2001)
James Bennington v. Caterpillar Incorporated
275 F.3d 654 (Seventh Circuit, 2001)
Shaw Industries, Inc. v. Community College District No. 515
741 N.E.2d 642 (Appellate Court of Illinois, 2000)
City of DeKalb v. Sornsin
205 N.E.2d 254 (Illinois Supreme Court, 1965)
Cartwright v. Moore
913 N.E.2d 1163 (Appellate Court of Illinois, 2009)
River Park, Inc. v. City of Highland Park
703 N.E.2d 883 (Illinois Supreme Court, 1998)
Charles F. Murphey Co. v. Fulton Bag & Cotton Mills
280 F. 367 (Seventh Circuit, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
710 F. Supp. 2d 704, 2010 U.S. Dist. LEXIS 29178, 2010 WL 1257766, Counsel Stack Legal Research, https://law.counselstack.com/opinion/comtel-technologies-inc-v-paul-h-schwendener-inc-ilnd-2010.