Computer Products International, Inc. v. United States

39 Cont. Cas. Fed. 76,626, 26 Cl. Ct. 518, 1992 U.S. Claims LEXIS 238, 1992 WL 114686
CourtUnited States Court of Claims
DecidedMay 29, 1992
DocketNo. 652-86C
StatusPublished
Cited by12 cases

This text of 39 Cont. Cas. Fed. 76,626 (Computer Products International, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Computer Products International, Inc. v. United States, 39 Cont. Cas. Fed. 76,626, 26 Cl. Ct. 518, 1992 U.S. Claims LEXIS 238, 1992 WL 114686 (cc 1992).

Opinion

OPINION

HORN, Judge.

This Opinion confirms in writing a decision previously issued orally by the court. On the eve of trial, the defendant filed a Motion to Dismiss, requesting the court to dismiss plaintiff’s complaint pursuant to Rule 12(b)(1) of the Rules of the United States Claims Court (RUSCC), for lack of subject matter jurisdiction. Defendant asserts that the plaintiff corporation did not have the capacity to sue in this court because, at the time the lawsuit was filed, the power, rights and privileges of the plaintiff corporation had been suspended under the laws of its state of incorporation, California, for failure to pay taxes, allegedly corporate franchise taxes.

BACKGROUND

It appears from the record that on or about October 26, 1977, a contract, N00104-78-C-4517, was entered into between Computer Products International, Inc. (CPI), a California corporation,1 and the United States Navy to supply 494 recording head assemblies for a firm fixed price of $71,136.00. The following contract terms were agreed to by the parties:

Test Specifications: December 27, 1977
Government Approval: January 24, 1977
First Article Testing Sample: May 24, 1978
Approval of First Article: July 24, 1978
Material: December 20, 1978
Complete: June 18, 1978

In the amended complaint, CPI asserts that prior to award of the contract, it had agreed with defendant that the tolerances for the recording heads would be left open due to problems defendant was encountering with heads produced from other suppliers. CPI contends this was done with the specific understanding of the parties that CPI would determine the appropriate acceptance test procedure because tolerances would be assigned by plaintiff at the time [520]*520of First Article Samples. Section E of the contract states:

The tolerance in the values of head inductance (L) and “Q” of the spec, on dwg. # 220113 has been left open and will be assigned at time of first article testing. This will result in uniformity in the product during production phase.

Unilateral contract modification A00001 apparently was executed on December 2, 1977. It states:

The contract is amended as follows:

SECTION E—SUPPLIES AND SERVICES—ADD:
Item No. Amount
0001AA First Article Samples NSP
0001AB Contract Data Requirements (See DD Form 1423) NSP

Unilateral contract modification A00001 was replaced by unilateral contract modification A00002, dated January 12, 1978, which states:

SECTION E—SUPPLIES AND SERVICES—ADD:
Item No. Amount
0003 First Article Samples NSP
0004 Contract Data Requirements (See DD Form 1423) NSP

In the claim filed with the contracting officer, and in the complaint, CPI argues that contract modifications A00001 and A00002 constituted constructive changes to the requirements of the contract because the requirements of First Article Samples and Contract Data Requirements were added. Plaintiff asserts that it should have been awarded an adjustment in the contract price to compensate for such changes. CPI contends that the effect of these changes was to shift the responsibility for determining the acceptance test procedures and for setting the tolerances from CPI to the defendant, in direct conflict with the original intention of the parties. CPI further asserts that due to the changes set forth in modifications A00001 and A00002, defendant regularly rejected drawing packages on the grounds that they did not meet defendant’s requirements, as defendant interpreted them under the contract. CPI states that it spent over 3,580 hours attempting to comply with defendant’s additional test procedures and first article sample requirements.

Defendant contends that, because the original contract contains detailed descriptions of first article testing and approval requirements, unilateral contract modifications A00001 and A00002 were administrative changes and did not alter the contract requirements. Therefore, defendant asserts that contract modifications A00001 and A00002 could not have increased the costs to perform the contract and that no adjustment to the contract price is necessary.

On July 28, 1978, the contract was amended by bilateral amendment A00003 to change the completion date from July 18, 1979, to December 30, 1978, in exchange for plaintiff’s request to extend the time for performance of another contract. Bilateral amendment A00003 states:

As consideration for an extension of Contract N00104-77-C-3840, the subject contract is modified as follows:
[521]*5211. Change the contract completion date in Section H:
From: 79 Jun 18 (79169)
To: 78 Dec 30 (78364)
2. There is no change in the contract price as a result of this modification.

In July, 1978, the government furnished equipment for this contract was sent to CPl. CPI asserts that the government’s delivery of this equipment was delayed and defective because at least three essential parts were missing. In February, 1979, the Navy requested CPI to send the government furnished equipment to another contractor because CPI was not yet in production and did not need the equipment at the time. CPI asserts that the government agreed to redeliver, in a timely manner, correct government furnished equipment by December 31, 1979, but did not deliver it until the fall of 1980. CPI contends that it performed additional work beyond the scope envisioned in its contract with defendant as a direct result of the alleged defective and delayed delivery of government furnished equipment and that the government’s actions constituted a constructive change to the contract.

Effective March 27, 1979, bilateral amendment A00004 was executed by the parties. This amendment changed several portions of the contract schedule and resulted in a reduced contract price of $70,-987.80. In addition, the amendment contains the following language: “This modification represents complete and equitable adjustment for all claims of either party up to this point.”

On February 15, 1983, the Navy terminated the contract for convenience. Defendant alleges, at that time, CPI had not sent First Article Samples to the Navy for testing and no production of articles had been authorized. Plaintiff asserts that defendant’s decision to terminate the contract and refusal to reimburse CPI for costs incurred was due, in part, to the delay and additional costs incurred by CPI as a result of defendant’s alleged breach of its duty to cooperate with CPI and to act reasonably in the administration of the contract.

On May 23, 1984, CPI submitted a letter to the government which CPI’s president, Mr. Syed, titled a settlement proposal, requesting $179,000.00 for development, fabrication and testing. According to Mr. Syed, the figure is based on an estimate of 3,580 hours of work allegedly performed by CPI pursuant to the contract and charged at the rate of $50.00 per hour.2

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Van Leeuwen v. United States
Federal Claims, 2025
Quoquoi v. United States
Federal Claims, 2019
Medical Weight Control Specialist v. Comm'r
2015 T.C. Memo. 52 (U.S. Tax Court, 2015)
Affourtit v. United States
79 Fed. Cl. 776 (Federal Claims, 2008)
Keeter Trading Co. v. United States
79 Fed. Cl. 243 (Federal Claims, 2007)
Galen Medical Associates, Inc. v. United States
74 Fed. Cl. 377 (Federal Claims, 2006)
Pueblo of Zuni v. United States
467 F. Supp. 2d 1099 (D. New Mexico, 2006)
Renda Marine, Inc. v. United States
71 Fed. Cl. 782 (Federal Claims, 2006)
First Heights Bank, FSB v. United States
53 Fed. Cl. 195 (Federal Claims, 2002)
Coast-to-Coast Financial Corp. v. United States
53 Fed. Cl. 241 (Federal Claims, 2002)
Hamza v. United States
40 Cont. Cas. Fed. 76,951 (Federal Claims, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
39 Cont. Cas. Fed. 76,626, 26 Cl. Ct. 518, 1992 U.S. Claims LEXIS 238, 1992 WL 114686, Counsel Stack Legal Research, https://law.counselstack.com/opinion/computer-products-international-inc-v-united-states-cc-1992.