BLH, Inc. v. United States

31 Cont. Cas. Fed. 71,106, 2 Cl. Ct. 463, 1983 U.S. Claims LEXIS 1770
CourtUnited States Court of Claims
DecidedApril 22, 1983
DocketNo. 433-81C
StatusPublished
Cited by7 cases

This text of 31 Cont. Cas. Fed. 71,106 (BLH, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
BLH, Inc. v. United States, 31 Cont. Cas. Fed. 71,106, 2 Cl. Ct. 463, 1983 U.S. Claims LEXIS 1770 (cc 1983).

Opinion

OPINION

HARKINS, Judge.

The issue presented by cross-motions for summary judgment in this case is whether plaintiff’s dissolution under Delaware corporation law on June 21, 1976, and the expiration of the statutory 3-year winding up period, eliminated plaintiff’s capacity under USCCR 17(b) to sue or be sued on claims defined in a final decision of a contracting officer made July 15, 1980, pursuant to the disputes clause of a contract that was executed on April 15, 1968. For reasons that follow, plaintiff lacked the capacity to sue or be sued when the petition was filed in the United States Court of Claims on July 13,1981, and on September 25,1981, when defendant asserted a counterclaim. Accordingly, plaintiff’s petition (now complaint) will be dismisséd, and defendant’s counterclaim will be dismissed without prejudice.

The following facts, applicable to the issue of plaintiff’s capacity to sue or be sued, are not in dispute.

Plaintiff was incorporated on June 24, 1965, in the State of Delaware as Baldwin-Lima-Hamilton Corporation.1 It manufactured heavy capital goods, including large hydraulic turbines to generate electric power. On April 15, 1968, Baldwin-Lima-Hamilton Corporation contracted with the Army Corps of Engineers (Contract No. DACW 41-68-C-0131) for the design, manufacture and delivery f.o.b. railroad cars at site, of six hydraulic pump-turbines for the Kay-singer Bluff Project (subsequently named the Harry S. Truman Dam and Reservoir Project) on the Osage River in Missouri. The contract price was $6,466,541.

On July 6, 1971, plaintiff’s parent corporation publicly announced plaintiff’s Industrial Equipment Division would be closed, and subsequently all of that Division’s assets, real estate, machinery and product lines, were sold. The hydraulic turbine and valve product line were sold on October 20, 1971. On March 13, 1972, plaintiff notified the Corps of Engineers’ Kansas City office that it would subcontract the domestic [465]*465manufacturing portion of the contract performed by the Industrial Equipment Division to Allis-Chalmers Corporation, York, Pennsylvania, and that all purchases from off-shore manufacturers would remain in effect as BLH subcontracts. On April 21, 1972, doiriestic manufacturing performance obligations under the contract, except design responsibility, performed by BLH, was subcontracted to Allis-Chalmers. The Industrial Equipment plant was closed on April 30,1972, and all manufacturing operations ceased.

In June 1972, plaintiff conferred with the Kansas City District Corps of Engineers on a novation of its contract, to transfer completion from plaintiff to Allis-Chalmers. During this period, BLH executed three novation agreements with the Corps of Engineers with respect to other contracts. On November 22, 1972, plaintiff requested the Comptroller General for an opinion as to the legality of the proposed novation of this contract. In an opinion dated August 28, 1973, the Comptroller General ruled that the Corps of Engineers could recognize a novation if it determined it to be in the best interest of the Government. The decision noted that plaintiffs parent, Armour & Company, was not responsible for plaintiff’s performance of the contract but under the proposed novation would act as guarantor.2 The Corps of Engineers desired an extension of warranty conditions under the contract at no cost in exchange for the novation agreement. The parties were unable to agree to a contract novation.

Between January 1,1975, and October 21, 1975, the pump-turbines manufactured under the contract were delivered to the project site. Pump-turbine units consist of several basic components, one of which is a steel vaned intake ring. The steel vaned intake rings were designed, manufactured, and delivered f.o.b. project site under plaintiff’s contract. Installation of the vaned intake ring, and the other pump-turbine unit components, was performed by the erection contractor, Truman Powerhouse Contractors (TPC) under a separate prime contract with the Corps of Engineers. Plaintiff’s contract included an obligation to provide the services of one or more engineers to supervise the work of the erecting contractor.

In April 1975, a problem surfaced that resulted in a dispute under the contract, which in correspondence between the parties is referred to as the “vaned intake ring problem.” During installation of the vaned intake ring in Unit No. 5 of the powerhouse, it was observed that the anchor foundation concrete for the ring had cracked. TPC was instructed by the contracting officer, in April 1975, to suspend all work regarding torquing bolts, welding for vaned intake ring supports, and concrete placement in the vicinity of the vaned intake ring, pending investigation and correction of the problem.

On May 1, 1975, plaintiff advised the contracting officer that it denied responsibility for all costs relating to foundation problems, but agreed to participate in the effort to resolve the problem. In these efforts, plaintiff’s representatives participated in meetings with representatives of the contracting officer and representatives of TPC. Correction procedures subsequently were agreed upon and were used in the installation of all of the pump-turbine units. The correction used installation procedures recommended or approved by BLH.

In connection with its participation in the correction of the vaned intake ring problem, BLH incurred costs which were included in a claim submitted to the contracting officer on August 27, 1975.3

On November 30, 1975, as part of its dissolution program, BLH paid a liquidating dividend to its shareholder in exchange for all its existing shares. On June 21, 1976, BLH filed a Certificate of Dissolution with the Delaware Secretary of State.

Pursuant to its obligations under the contract, after November 1974, BLH provided [466]*466the services of an erecting engineer to supervise the erection contractor, TPC, for a period in excess of 3,000 calendar days. After June 21, 1976, BLH maintained an office in Media, Pennsylvania, solely to provide assistance relative to the contract. This office consisted of three full time employees and four temporary consultants. Defendant has compensated BLH through a series of contract modifications for the expense incurred in maintaining this office.

During the 3-year period following June 21, 1976, defendant did not make final any claim against BLH arising out of the April 1975 damage to the two upper concrete anchor piers in Unit No. 5, or for additional costs related to correction of the vaned intake ring problem. Defendant made no application to the appropriate Delaware court for an extension of the statutory winding up period following the dissolution of BLH.

On July 15, 1980, the contracting officer rendered a decision on the dispute concerned with the vaned intake ring problem. The contracting officer decided that BLH is responsible for costs of $476,900 for additional work, and for $3,750,000 for impact, delay and acceleration costs, which amounts had been paid to TPC. The decision determined that BLH is indebted to the Government in the total amount of $4,266,900 due to BLH’s defective design of the pump-turbines.

Plaintiff’s appeal from the decision of the contracting officer was the filing of a petition in the United States Court of Claims on July 13, 1981, pursuant to section 10(a) of the Contract Disputes Act of 1978.4

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Keeter Trading Co. v. United States
79 Fed. Cl. 243 (Federal Claims, 2007)
In Re Tutu Wells Contamination Litigation
846 F. Supp. 1243 (Virgin Islands, 1993)
Harthman v. Texaco, Inc.
846 F. Supp. 1243 (Virgin Islands, 1993)
City Investing Co. Liquidating Trust v. Continental Casualty Co.
624 A.2d 1191 (Supreme Court of Delaware, 1993)
Computer Products International, Inc. v. United States
39 Cont. Cas. Fed. 76,626 (Court of Claims, 1992)
BLH, Inc. v. United States
34 Cont. Cas. Fed. 75,376 (Court of Claims, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
31 Cont. Cas. Fed. 71,106, 2 Cl. Ct. 463, 1983 U.S. Claims LEXIS 1770, Counsel Stack Legal Research, https://law.counselstack.com/opinion/blh-inc-v-united-states-cc-1983.