Complete General v. Dept. of Trans., Unpublished Decision (5-25-2000)

CourtOhio Court of Appeals
DecidedMay 25, 2000
DocketNo. 98AP-1619.
StatusUnpublished

This text of Complete General v. Dept. of Trans., Unpublished Decision (5-25-2000) (Complete General v. Dept. of Trans., Unpublished Decision (5-25-2000)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Complete General v. Dept. of Trans., Unpublished Decision (5-25-2000), (Ohio Ct. App. 2000).

Opinion

OPINION
Defendant-appellant, the Ohio Department of Transportation ("ODOT"), appeals from a judgment of the Ohio Court of Claims awarding plaintiff-appellee, Complete General Construction Company ("Complete General"), $374,231.08 in its action for breach of contract. Complete General cross-appeals from the judgment.

This action arises out of the construction of I-670 in Columbus, Ohio from the Convention Center to the airport. Construction of this portion of I-670 was broken into five sections, with each section being bid as a separate contract. In 1991, ODOT accepted bids for each of the five sections of the I-670 project. Complete General won four of the five contracts, including Contract 56, which is the focus of the instant action.

Contract 56 provided for the construction of a section of I-670 extending in an easterly direction from the Convention Center to a point just east of I-71. Contract 56 included the erection of three new bridges: the Third Street bridge, which provides access from I-670 to southbound Third Street; the Fourth Street bridge, which provides access from I-670 to northbound Fourth Street; and a large mainline bridge over several pairs of railroad tracks. Complete General subcontracted with the C.J. Mahan Construction Company for the erection of these three bridges.

Work on Contract 56 was scheduled to begin in March 1991. However, even before work could begin on the project, it was discovered that additional work not called for in original contract documents would be required. Specifically, a building and several underground fuel storage tanks were discovered on the job site. Shortly thereafter, ODOT issued change orders 2 and 4 granting Compete General additional compensation for the removal of the building and underground storage tanks, respectively.

Work on Contract 56 formally got under way on March 15, 1991, with project completion scheduled for August 31, 1992. However, in early June 1991, progress on the construction of the Fourth Street and mainline bridges was indefinitely delayed when it was discovered that the rebar, which had been delivered for use in these two bridges, had been improperly designed and manufactured. The bridge delay lasted almost seven months, ending sometime in late December 1991, when the correct rebar was delivered to the job site. As a result of the bridge delay, ODOT, on May 13, 1992, granted Complete General a full twelve-month work extension, bringing the job completion date to August 31, 1993. On August 17, 1993, ODOT granted Complete General an additional sixty-day extension for the removal of the building and underground storage tanks. Together, the two time extensions pushed the date for final completion of Contract 56 ahead by four hundred twenty-five days, to October 31, 1993. Complete General actually completed all of its work on Contract 56 on October 30, 1993.

Following completion of Contract 56, Complete General and ODOT entered into negotiations regarding Complete General's compensation for costs incurred as a result of the additional time beyond the original completion date which the company spent on Contract 56. On October 31, 1996, Complete General and ODOT entered into a settlement agreement, referred to as "change order 39," by which ODOT agreed to pay Complete General $177,662.47, as compensation for all costs incurred due to the two contract extensions, except "home office overhead, interest, extended major equipment costs, and bond costs." Negotiations regarding these unsettled issues continued.

On January 7, 1997, Complete General filed a complaint seeking to recover the unabsorbed home office overhead, idle equipment costs, extended equipment costs, and additional bond costs which it incurred due to ODOT's two extensions of Contract 56. Complete General's complaint also sought interest on all of its costs from the time of Contract 56's "substantial completion."

After Complete General filed its complaint, ODOT forwarded a settlement offer, referred to as "change order 40," to Complete General in which it offered to settle Complete General's claims for unabsorbed home office overhead, bond costs, and interest for a total of $196,410.34: $182,500 for unabsorbed overhead, $888.31 for bond costs, and $13,022.03 for interest. By a letter dated January 27, 1997, Complete General rejected change order 40, but agreed to accept the amount offered by ODOT as partial payment for the disputed claims. Accordingly, ODOT directly deposited $196,410.34 into Complete General's bank account.

On March 25, 1998, with the trial of Complete General's action scheduled to begin on April 13, 1998, ODOT filed a motion seeking leave to amend its answer to raise the defense of statute of limitations. On April 6, 1998, the trial court denied ODOT's motion for leave to amend its answer.

Beginning on April 13, 1998, Complete General's claims against ODOT were tried by the court. On November 18, 1998, the Court of Claims issued a decision and a judgment entry awarding Complete General $374,231.08. Specifically, the Court of Claims awarded Complete General $184,947 on its claim for unabsorbed home office overhead, $62,622.50 on its claim for idle equipment costs, $115,171.49 in interest on the overhead and idle equipment awards, and $11,490.09 in additional bond costs. However, the Court of Claims found for ODOT on Complete General's claim for extended equipment costs.

ODOT appeals from the decision of the Court of Claims assigning the following errors:

ASSIGNMENT OF ERROR NO. 1

THE TRIAL COURT ERRED BY NOT FINDING THE CONTRACTOR'S CLAIMS WERE BARRED BY THE TWO-YEAR STATUTE OF LIMITATIONS.

ASSIGNMENT OF ERROR NO. 2

THE TRIAL COURT ERRED AS A MATTER OF LAW IN AWARDING DAMAGES FOR UNABSORBED HOME OFFICE OVERHEAD PURSUANT TO THE EICHLEAY FORMULA.

ASSIGNMENT OF ERROR NO. 3

THE TRIAL COURT ERRED IN ITS APPLICATION OF THE EICHLEAY FORMULA BY INCORRECTLY COUNTING THE NUMBER OF COMPENSABLE DAYS, BY NOT SUBTRACTING OVERHEAD INCLUDED IN CHANGE ORDER WORK, AND BY NOT DEDUCTING CERTAIN COSTS FROM THE OVERHEAD POOL.

ASSIGNMENT OF ERROR NO. 4

THE TRIAL COURT'S RELIANCE ON PLAINTIFF-APPELLEE'S EXPERT IN CALCULATING DAMAGES UNDER EICHLEAY WAS AGAINST THE MANIFEST WEIGHT OF THE EVIDENCE.

ASSIGNMENT OF ERROR NO. 5

THE TRIAL COURT'S DECISION TO AWARD cg $62,622.50 IN IDLE EQUIPMENT COSTS BETWEEN MARCH 15, 1991 AND APRIL 29, 1992 WAS AGAINST THE MANIFEST WEIGHT OF THE EVIDENCE.

ASSIGNMENT OF ERROR NO. 6

THE TRIAL COURT COMMITTED PLAIN ERROR IN ITS CALCULATION OF THE BOND COSTS.

Complete General cross-appeals from the Court of Claims' decision and entry assigning the following errors:

1. THE TRIAL COURT ERRED IN LIMITING PLAINTIFF'S RECOVERY OF HOME OFFICE OVERHEAD TO 365 DAYS, CONTRARY TO DEFENDANT'S JUDICIAL ADMISSIONS.

2. THE TRIAL COURT MADE A MATHEMATICAL ERROR IN DETERMINING THE AMOUNT OF PLAINTIFF'S UNABSORBED OVERHEAD AWARD.

3. THE TRIAL COURT MISCALCULATED THE PREJUDGMENT INTEREST AWARD TO PLAINTIFF.

4.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Melka Marine, Inc. v. United States
187 F.3d 1370 (Federal Circuit, 1999)
Fireman's Fund Insurance v. BPS Co.
491 N.E.2d 365 (Ohio Court of Appeals, 1985)
C. E. Morris Co. v. Foley Construction Co.
376 N.E.2d 578 (Ohio Supreme Court, 1978)
Blakemore v. Blakemore
450 N.E.2d 1140 (Ohio Supreme Court, 1983)
Seasons Coal Co. v. City of Cleveland
461 N.E.2d 1273 (Ohio Supreme Court, 1984)
Royal Electric Construction Corp. v. Ohio State University
73 Ohio St. 3d 110 (Ohio Supreme Court, 1995)
State ex rel. Tubbs Jones v. Suster
701 N.E.2d 1002 (Ohio Supreme Court, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
Complete General v. Dept. of Trans., Unpublished Decision (5-25-2000), Counsel Stack Legal Research, https://law.counselstack.com/opinion/complete-general-v-dept-of-trans-unpublished-decision-5-25-2000-ohioctapp-2000.