Commonwealth v. Bpi Construction Management, Inc.

Massachusetts Appeals Court·Decided June 20, 2025·No. 24-P-0754·Unpublished

Opinion

NOTICE: Summary decisions issued by the Appeals Court pursuant to M.A.C. Rule 23.0, as appearing in 97 Mass. App. Ct. 1017 (2020) (formerly known as rule 1:28, as amended by 73 Mass. App. Ct. 1001 [2009]), are primarily directed to the parties and, therefore, may not fully address the facts of the case or the panel's decisional rationale. Moreover, such decisions are not circulated to the entire court and, therefore, represent only the views of the panel that decided the case. A summary decision pursuant to rule 23.0 or rule 1:28 issued after February 25, 2008, may be cited for its persuasive value but, because of the limitations noted above, not as binding precedent. See Chace v. Curran, 71 Mass. App. Ct. 258, 260 n.4 (2008).

COMMONWEALTH OF MASSACHUSETTS

APPEALS COURT

24-P-754

COMMONWEALTH

vs.

BPI CONSTRUCTION MANAGEMENT, INC.

MEMORANDUM AND ORDER PURSUANT TO RULE 23.0

The defendant, BPI Construction Management, Inc. (BPI),

appeals from summary judgment entered against it in the Superior

Court on the Commonwealth's claims for violations of the

Massachusetts False Claims Act (MFCA), G. L. c. 12,

§ 5B (a) (1)-(2) (2012). The judgment total was $926,898.06,

including damages of $513,079.84, filing fees of $280.00,

punitive damages of $226,752.00, and attorney's fees of

$72,000.00. Because we discern no error in the motion judge's

denials of BPI's motions to dismiss the complaint under Mass.

R. Civ. P. 9 (b), 365 Mass 751 (1974), or to join additional

parties to the action, and we conclude that the Commonwealth was

entitled to summary judgment on liability and damages in the

amount calculated by the judge, we affirm the judgment and the order denying the defendant's motion for relief from the judgment.

Background. 1. Facts. The following facts are drawn from the summary judgment rulings and, except as noted, are not disputed.1 a. Westport project. In June 2017, general contractor M.

O'Connor Contracting, Inc. (O'Connor), awarded BPI, a construction company subject to the Prevailing Wage Law, G. L. c. 149, §§ 27, 27B, the carpentry subcontract for a public works contract in Westport. The terms of the subcontract required BPI to "comply with and be bound by all statutes, rules and regulations governing wage rates," and provided that the Westport project "is a public job and prevailing wage rates apply and weekly payroll reports are required." The schedule of prevailing wage rates at the Westport project for carpenters was $66.68 per hour.

BPI hired Superior Carpentry, Inc. (Superior), to provide the labor for BPI's portion of the Westport project. BPI's subcontract with Superior required Superior to "keep true and accurate payroll records for every such person under their employ and submit certified weekly payroll forms together with a

Statement of Compliance to [Westport] with the appropriate prevailing rate."

Superior hired carpenters for the Westport project through ICNG Contractor, Inc. (ICNG), and paid the carpenters at a rate below the prevailing wage. BPI did not review records, inquire, or take any other steps to verify that Superior was complying with the Prevailing Wage Law, however.2 Superior workers ultimately performed 4,756.5 hours of work on the Westport project under the subcontract with BPI.

To obtain payment, BPI was required to ensure that O'Connor was provided with weekly certified payroll reports (CPRs) documenting and certifying that all carpenters performing work under BPI's subcontract with Superior were being paid in compliance with the Prevailing Wage Law. During the Westport project, BPI used twenty-two completed CPRs from Superior to obtain payment. These CPRs falsely stated that the laborers were paid in compliance with the Prevailing Wage Law.

b. Middleborough project. In September 2017, A.P.

Whitaker & Sons, Inc. (Whitaker), awarded BPI the carpentry subcontract for a public works project in Middleborough. As with the Westport project, the contract for the Middleborough

project required that the workers employed under it be paid at the prevailing minimum wage rate, which was again $66.68 per hour. BPI subcontracted Superior to provide the labor and required Superior to keep true and accurate records and to pay prevailing wages. Superior again hired workers from ICNG. These laborers worked 2,237.5 hours on the Middleborough project.

Once again, the workers were not paid the prevailing wage, although Superior completed ten CPRs that falsely stated otherwise. BPI was required to, and did, use these CPRs to obtain payment from Middleborough, but it still did not supervise Superior's work and did not review records, make inquiries, or verify Superior's compliance with the Prevailing Wage Law.

2. Procedural history. In February 2018, the Fair Labor Division of the Massachusetts Attorney General's Office (AGO) received a complaint that the carpenters on the Westport project were not being paid the prevailing wage. The AGO investigated and, on December 13, 2021, filed this action against BPI (enforcement action). In response to the AGO's investigation, Superior admitted that it did not pay any worker the prevailing wage on either the Westport or the Middleborough projects. On December 21, 2021, Superior settled the Commonwealth's claims against it by agreeing to pay $256,539.92 in restitution (unpaid

wages), plus $284,000 in statutory penalties under the Massachusetts "wages and hour laws," see G. L. cc. 149, 151; MFCA.

In January 2022, BPI moved unsuccessfully to dismiss the Commonwealth's complaint on the grounds that the Commonwealth failed to join indispensable parties (namely, Superior, O'Connor, and Whitaker). In denying BPI's motion, a Superior Court judge (first judge) concluded that the AGO had exclusive discretion to decide if and when to pursue an MFCA enforcement action.3 In May 2022, the first judge then denied BPI's motion to add Superior, O'Connor, and Whitaker as third-party defendants, concluding that an MFCA defendant is not entitled to indemnification or contribution.

In September 2022, the Commonwealth moved for partial summary judgment on BPI's liability under §§ 5B (a) (1) and 5B (a) (2), for using the thirty-two false CPRs (that Superior had prepared) to obtain payment from the towns of Westport and Middleborough.4 Citing to the undisputed evidence that (1) the

information Superior provided on the CPRs for the Westport and Middleborough projects was false and fraudulent; (2) BPI used those CPRs to obtain payment, with deliberate indifference or reckless disregard for their falsity; and (3) the false CPRs caused the general contractors to submit false claims to the towns, on December 15, 2022, a different Superior Court judge (second judge) allowed the Commonwealth's motion.

On February 13, 2023, BPI again moved to add Superior, O'Connor, and Whitaker as third-party defendants, this time asserting claims under G. L. c. 93A and, as to Superior only, claims for committing breaches of Superior's subcontract with BPI. The first judge denied the motion, concluding that it was simply a repackaging of BPI's earlier attempt to bring impermissible claims for indemnification and contribution.

The Commonwealth then moved for summary judgment for relief in July 2023.5 The second judge allowed this motion in part, ordering BPI to pay $513,079.84 in compensatory damages and $72,000.00 in attorney's fees under G. L. c. 12, § 5B (a) (2),

zero; and (2) BPI was therefore entitled to judgment in its favor on liability.

BPI also filed a second cross motion for summary judgment, 5 which the Commonwealth opposed. Approximately ten days later, before the summary judgment motions were heard, BPI moved for reconsideration of the December 2022 partial summary judgment entered on its MFCA liability. The Commonwealth opposed that motion, as well, and the motion was denied by the second judge.

Free access — add to your briefcase to read the full text and ask questions with AI

Commonwealth v. Bpi Construction Management, Inc., (Mass. Ct. App. 2025).

Commonwealth v. Bpi Construction Management, Inc. (Commonwealth v. Bpi Construction Management, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States v. Bornstein
423 U.S. 303 (Supreme Court, 1976)
Tritsch v. Boston Edison Co.
293 N.E.2d 264 (Massachusetts Supreme Judicial Court, 1973)
Friedman v. Jablonski
358 N.E.2d 994 (Massachusetts Supreme Judicial Court, 1976)
Wolfe v. Ford Motor Co.
434 N.E.2d 1008 (Massachusetts Supreme Judicial Court, 1982)
Barbosa v. HOPPER FEEDS. INC.
537 N.E.2d 99 (Massachusetts Supreme Judicial Court, 1989)
Shepard v. Attorney General
567 N.E.2d 187 (Massachusetts Supreme Judicial Court, 1991)
Madsen v. Erwin
481 N.E.2d 1160 (Massachusetts Supreme Judicial Court, 1985)
Commonwealth v. Domanski
123 N.E.2d 368 (Massachusetts Supreme Judicial Court, 1954)
Massachusetts v. Schering-Plough Corp.
779 F. Supp. 2d 224 (D. Massachusetts, 2011)
United States v. Dynamics Research Corp.
441 F. Supp. 2d 259 (D. Massachusetts, 2006)
US Ex Rel. Harris v. Bernad
275 F. Supp. 2d 1 (District of Columbia, 2003)
Raytheon Co. v. Continental Casualty Co.
123 F. Supp. 2d 22 (D. Massachusetts, 2000)
Auto Flat Car Crushers, Inc. v. Hanover Insurance Co.
17 N.E.3d 1066 (Massachusetts Supreme Judicial Court, 2014)
Commonwealth v. Newton N., a juvenile
89 N.E.3d 1159 (Massachusetts Supreme Judicial Court, 2018)
Thomas v. EDI Specialists, Inc.
773 N.E.2d 415 (Massachusetts Supreme Judicial Court, 2002)
Locator Services Group, Ltd. v. Treasurer & Receiver General
825 N.E.2d 78 (Massachusetts Supreme Judicial Court, 2005)
Quinn v. Walsh
732 N.E.2d 330 (Massachusetts Appeals Court, 2000)
Scannell v. Attorney General
872 N.E.2d 1136 (Massachusetts Appeals Court, 2007)
Chace v. Curran
881 N.E.2d 792 (Massachusetts Appeals Court, 2008)