Commonwealth Utilities Corporation v. Goltens Trading & Engineering Pte Ltd., a Foreign Corporation, and In-Place MacHining Company, Inc., a Foreign Corporation, Defendant-Third-Party-Plaintiff-Appellant v. Man B & W Diesel Ag, Third-Party-Defendant-Appellee

313 F.3d 541, 2002 Daily Journal DAR 14130, 2002 Cal. Daily Op. Serv. 11989, 2002 U.S. App. LEXIS 25743
CourtCourt of Appeals for the Third Circuit
DecidedDecember 16, 2002
Docket01-16614
StatusPublished
Cited by1 cases

This text of 313 F.3d 541 (Commonwealth Utilities Corporation v. Goltens Trading & Engineering Pte Ltd., a Foreign Corporation, and In-Place MacHining Company, Inc., a Foreign Corporation, Defendant-Third-Party-Plaintiff-Appellant v. Man B & W Diesel Ag, Third-Party-Defendant-Appellee) is published on Counsel Stack Legal Research, covering Court of Appeals for the Third Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Commonwealth Utilities Corporation v. Goltens Trading & Engineering Pte Ltd., a Foreign Corporation, and In-Place MacHining Company, Inc., a Foreign Corporation, Defendant-Third-Party-Plaintiff-Appellant v. Man B & W Diesel Ag, Third-Party-Defendant-Appellee, 313 F.3d 541, 2002 Daily Journal DAR 14130, 2002 Cal. Daily Op. Serv. 11989, 2002 U.S. App. LEXIS 25743 (3d Cir. 2002).

Opinion

313 F.3d 541

COMMONWEALTH UTILITIES CORPORATION, Plaintiff,
v.
GOLTENS TRADING & ENGINEERING PTE LTD., a foreign corporation, Defendant, and
In-Place Machining Company, Inc., a foreign corporation, Defendant-third-party-plaintiff-Appellant,
v.
MAN B & W Diesel AG, Third-party-defendant-Appellee.

No. 01-16614.

United States Court of Appeals, Ninth Circuit.

Argued and Submitted November 6, 2002.

Filed December 16, 2002.

Thomas Roberts, Dooley Lannen Roberts & Fowler LLP, Tamuning, Guam; Elton John Bain, Kessner Duca Umebayashi Bain & Matsunaga, Honolulu, Hawaii, for the defendant-third-party-plaintiff-appellant.

Richard W. Pierce, White Pierce Mailman & Nutting, Saipan, Mariana, Pacific; Christopher H. Mansuy, De Orchis, Walker & Corsa, LLP, New York, NY, for third-party-defendant-appellee.

Appeal from the United States District Court for the District of the Northern Mariana Islands; Alex R. Munson, Chief Judge, Presiding. D.C. No. CV-97-00046-ARM.

Before SCHROEDER, Chief Judge, ALARCÓN and FISHER, Circuit Judges.

OPINION

ALARCÓN, Circuit Judge:

Third-Party-Plaintiff-Appellant, In-Place Machining Company, Inc. ("IPM"), appeals from the district court's order for summary judgment dismissing IPM's claim for contribution from Third-Party-Defendant-Appellee, MAN B & W Diesel AG ("MAN"). The dispute arises from the failure of a large diesel generator, owned and operated by Commonwealth Utilities Corporation ("CUC"), shortly after the generator had received parts and undergone repairs by Goltens Trading & Engineering PTE LTD. ("Goltens") and IPM. CUC filed claims against Goltens for breach of warranty and negligence, and IPM for negligent repair. IPM filed a third-party cross-claim for indemnity and contribution against MAN for MAN's allegedly negligent role as a consultant to, or supervisor of, the negligent repair. Goltens and IPM settled their dispute with CUC, and IPM dropped its cross-claim against MAN for indemnity. IPM persisted in its contribution cross-claim against MAN. The district court dismissed IPM's cross-claim on summary judgment, holding that IPM did not produce sufficient evidence to raise a triable issue of fact as to a breach of a legal duty by MAN in its relationship with CUC. IPM appeals the dismissal.

Because IPM has failed to produce facts necessary to sustain a claim in tort, we affirm the district court's grant of summary judgment.

* CUC owned several large electrical generating diesel engines designed by MAN and manufactured under license by Mitsubishi Heavy Industries. In April 1995, CUC hired IPM to repair a crankpin on engine number six. In early January 1996, CUC contracted with MAN for the scheduled-maintenance overhaul of engines four and five. Later in January 1996, engine number eight was substituted for engine number five in the maintenance overhaul contract between CUC and MAN. On January 23, 1996, before work on the scheduled overhaul began, engine eight failed, and the crankpin and journal of its number nine cylinder were damaged.

In early February 1996, MAN technician Gunter Molch ("Molch") performed a visual inspection of a fully assembled engine number eight. Molch submitted his findings from that inspection to CUC Power Plant Manager Frank Lizama ("Lizama") and to his home office in Germany. Molch's report listed the damage that was noted on his visual inspection of the fully assembled engine. He speculated regarding the damages that could be found on disassembly. He also made suggestions as to the repairs that might be required. He urged that all work be done by an authorized repair shop with some of the parts needing to go to MAN's shop in Germany for "reconditioning." Molch's report warned that severe damage to the crankpin should be expected. Molch reported that "crank web deflection was taken and the values found [were] still within [the] accepted limit." Nevertheless, he urged that the crankpin be tested for roundness, hardness, cracks, roughness, angular deviation, and deviation from parallelity. Molch stated that the decision as to the proper reconditioning method was contingent on the results of this further recommended testing. Molch did not create a definitive list of existent crankpin problems, nor did he propose solutions to any as yet undetermined problems.

A copy of Molch's report was attached to an internal memorandum regarding the procurement of the crankpin refurbishment, sent from CUC's acting power generation manager to a CUC procurement and supply advisor. This internal memorandum stated that the desired outside-contractor bid would be for refurbishing the number nine crankpin and to "check [its] hardness, roundness, roughness and presence of crack."

CUC did not follow Molch's advice. In March of 1996, CUC contracted with IPM to refurbish engine eight's malfunctioning number nine crankpin on site, as IPM had done the previous year with engine six, rather than send the crankpin to be repaired off-site at MAN Germany, as Molch had recommended in his report. CUC contracted with IPM in early March of 1996, to refurbish engine eight's number nine crankpin. IPM described its charges to CUC as including, "Hardness Checking, Crack Detection, and Crankpin Refurbishment."

From February to April of 1996, any work done by MAN on engine eight was not done pursuant to the previously executed engine maintenance-overhaul contract, but on an hourly basis. The purpose of this hourly contract, according to Frank Lizama, CUC's Power Plant Manager, was to use MAN technicians "to help us on technical matters with our MAN B & W engines." Two other CUC personnel stated in deposition testimony that they believed MAN to have been a "technical advisor" to CUC. At least one of those witnesses, however, believed all three contractors, Goltens, IPM, and MAN, to be such technical advisors.

MAN technician Ernst Miller ("Miller") informed his home office on March 5, 1996, that "I am commencing already with dismantling Engine Number 8 in preparation for honing, grinding of the crank pin motor." Miller's work was not done pursuant to MAN's contract with CUC to overhaul engine eight, but rather pursuant to the hourly contract to help CUC with "technical matters" concerning the engines. Miller disassembled engine eight, and sometime in April 1996, Miller and Molch measured the number nine crankpin for straightness. Miller testified that their measurements determined that the crank shaft was not bent beyond satisfactory tolerances. This determination was reported to CUC.

IPM performed the contracted on-site work on engine eight's number nine crankpin journal in May of 1996. IPM technician Allen Breitbach ("Breitbach"), testified at his deposition that he believed MAN's purpose in being at CUC's power plant was to work on another engine and to discuss what IPM was doing on engine eight. Breitbach believed that he had discussed MAN's manufacturer's tolerances for crankpin hardness with one of MAN's on-site technicians. Breitbach did not recall any discussion with MAN regarding the "specifications or tolerances on this particular crankpin." Further,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ahmann v. Minnesota Mutual Life Insurance
83 F. App'x 958 (Ninth Circuit, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
313 F.3d 541, 2002 Daily Journal DAR 14130, 2002 Cal. Daily Op. Serv. 11989, 2002 U.S. App. LEXIS 25743, Counsel Stack Legal Research, https://law.counselstack.com/opinion/commonwealth-utilities-corporation-v-goltens-trading-engineering-pte-ca3-2002.