Committee for Re-Evaluation of the T-Line Loop v. San Francisco Municipal Transportation Agency

6 Cal. App. 5th 1237, 211 Cal. Rptr. 3d 902
CourtCalifornia Court of Appeal
DecidedNovember 29, 2016
DocketA147498
StatusPublished
Cited by11 cases

This text of 6 Cal. App. 5th 1237 (Committee for Re-Evaluation of the T-Line Loop v. San Francisco Municipal Transportation Agency) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Committee for Re-Evaluation of the T-Line Loop v. San Francisco Municipal Transportation Agency, 6 Cal. App. 5th 1237, 211 Cal. Rptr. 3d 902 (Cal. Ct. App. 2016).

Opinion

Opinion

MILLER, J.

In 2014, the San Francisco Municipal Transportation Agency (Muni) approved a contract to install the last 900 feet of light rail line needed to complete a partially constructed “T-Line Loop” (Loop) around a city block in the Dogpatch neighborhood of San Francisco. 1 The Loop—bounded by Third, Illinois, 18th and 19th Streets—will allow trains on the T-Third light rail line to turn around to meet service needs for special events and peak travel periods. Track for the Loop on Third Street was laid more than 10 years ago, and operates as part of the T-Third line; spur track was laid on most of 18th and 19th Streets between Third and Illinois when the T-Third line was constructed. In approving the 2014 contract, Muni authorized the construction of light rail line on Illinois Street and parts of 18th and 19th Streets to connect the existing spurs.

*1240 Plaintiffs filed suit to stop construction of the Loop, claiming that Muni failed to comply with CEQA. 2 When Muni’s board of directors approved the contract to complete the Loop, it relied in part on an environmental impact report that was certified in 1998 (the LEIR, discussed further below) in connection with plans to connect the southeastern portion of San Lrancisco to the rest of the city. It also relied on statements by the San Lrancisco Planning Department that no further assessments or environmental impact reports for the project were required under CEQA. On appeal, plaintiffs the Committee for Re-Evaluation of the T-Line Loop, William Schwartz and Richard Weiner (collectively, the Committee) claim that Muni, the Muni Board of Directors, Muni’s Director of Transportation, and the City and County of San Lrancisco (collectively, the City) abused its discretion under Public Resources Code section 21151 by failing to conduct a new CEQA analysis and instead relying on the 1998 environmental study, which, according to the Committee, did not analyze the Loop. The Committee also claims that even if the 1998 study did analyze the Loop, the City abused its discretion under Public Resources Code section 21166 by not requiring supplemental CEQA analysis examining conditions as they existed in 2014. We conclude that substantial evidence supports the City’s determination to proceed under Public Resources Code section 21166 rather than section 21151. We also conclude that substantial evidence supports the City’s determination that no further environmental impact report for the Loop was required. Consequently, we find no abuse of discretion, and we will affirm.

FACTUAL AND PROCEDURAL BACKGROUND

A. The Third Street Light Rail Project Is Approved

In the 1990’s, Muni’s predecessor agency proposed to connect the southeastern part of San Lrancisco to the rest of the city by means of the Third Street Light Rail Project (the Project), which would link the Visitación Valley, Little Hollywood and Bayview-Hunters Point neighborhoods with Chinatown, Downtown, and South of Market. 3 The Project was divided into two phases: the initial operating segment (Initial Operating Segment), from the southern border of the city, along Third Street, past the Caltrain Station at King Street to the Embarcadero; and the new central subway (New Central Subway), from the Caltrain station at King Street to Chinatown.

*1241 In 1998, the San Francisco Planning Department and the Federal Transit Administration published the Third Street Light Rail Project Final Environmental Impact Statement/Final Environmental Impact Report (FEIR) under CEQA and the National Environmental Policy Act of 1969 (NEPA). 4 The FEIR discussed both phases of the Project, but at different levels of detail. The FEIR stated that the two phases were related but distinct, and “subject to separate advancement decisions on separate schedules.” Preliminary engineering had been conducted for the Initial Operating Segment, but not the New Central Subway. Accordingly, the FEIR evaluated impacts and alternatives for the Initial Operating Segment, but provided only “planning-level information with less engineering detail about the impacts and alternatives” for the New Central Subway, which would be further analyzed in the future. 5

The FEIR describes the 5.4-mile-long Initial Operating Segment as composed of six smaller segments of light rail line running generally south to north, with segment 1 beginning near the southern border of San Francisco. Segment 4 runs along Third Street from Kirkwood Avenue north to 16th Street, and includes a “short-turn loop from Third [Street] following 18th, Illinois, and 19th Streets,” which would allow the extension of an existing line to serve Mission Bay and provide an area for two 2-car trains to lay over.

The San Francisco Planning Commission certified the FEIR as objective, complete, and in compliance with CEQA and the CEQA guidelines (CEQA Guidelines) in December 1998. 6

*1242 B. The Initial Operating Segment, Including Part of the Loop, Is Constructed

Anticipating construction of the Initial Operating Segment, in August 2000 the San Francisco Board of Supervisors (Supervisors) approved a resolution restricting turns and eliminating parking on Third Street. In April 2001, the Supervisors approved a resolution eliminating parking on 18th Street, 19th Street, and Illinois Street, where the Loop was to be constructed. 7 By 2003, construction of the Initial Operating Segment was completed, including segment 4 along Third Street and much of the Loop. Loop turnouts from Third Street were built, with track extending two-thirds of the way east from Third Street to Illinois Street on 18th and 19th Streets, but the Loop was not fully completed due to budget constraints. 8 Construction of the rest of the Loop was deferred because “the bulk of the increased service the Loop was intended to accommodate is not needed until the beginning of the operation of the Central Subway planned for 2019.” The Initial Operating Segment began service as the T-Third line in 2007.

C. Muni Receives a Federcd Grant to Complete the Loop

In 2013, the Federal Transit Administration awarded Muni a $10 million grant under the Transportation Investment Generating Economic Recovery (TIGER) program to fund the completion of the Loop as well as other roadway and surface improvements in the vicinity of Mission Bay.

*1243 In connection with applying for the grant, in 2012 Muni prepared a memorandum to the San Francisco Planning Department (Planning Department), seeking the Planning Department’s concurrence that CEQA Guidelines sections 15162 through 15164 did not require the preparation of a subsequent EIR, a supplement to the FEIR, or an addendum to the FEIR for the Loop to be completed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
6 Cal. App. 5th 1237, 211 Cal. Rptr. 3d 902, Counsel Stack Legal Research, https://law.counselstack.com/opinion/committee-for-re-evaluation-of-the-t-line-loop-v-san-francisco-municipal-calctapp-2016.