Comfort Lake Association, Inc., Plaintiff--Appellant/cross v. Dresel Contracting, Inc. Fain Companies, Defendants--Appellees/cross

138 F.3d 351
CourtCourt of Appeals for the Eighth Circuit
DecidedApril 14, 1998
Docket96-3654, 96-3919 and 96-4220
StatusPublished
Cited by59 cases

This text of 138 F.3d 351 (Comfort Lake Association, Inc., Plaintiff--Appellant/cross v. Dresel Contracting, Inc. Fain Companies, Defendants--Appellees/cross) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Comfort Lake Association, Inc., Plaintiff--Appellant/cross v. Dresel Contracting, Inc. Fain Companies, Defendants--Appellees/cross, 138 F.3d 351 (8th Cir. 1998).

Opinion

LOKEN, Circuit Judge.

Comfort Lake Association, Inc. (“Comfort Lake”), filed this citizen suit seeking injunc-tive relief, civil penalties, and costs and attorney’s fees against Dresel Contracting, Inc., and Fain Companies (“Dresel and Fain”) for alleged violations of the Federal Water Pollution Control Act, 33 U.S.C. §§ 1251-1387, commonly known as the Clean Water Act. The district court 1 initially denied Dresel and Fain’s motion for summary judgment, rejecting their contention that the Minnesota Pollution Control Agency (“MPCA”) had commenced and was diligently prosecuting an administrative enforcement action that barred this citizen suit. See 33- U.S.C. § 1319(g)(6)(A)(ii). However, the court 2 later dismissed the action as mooted by MPCA’s subsequent enforcement actions and denied Comfort Lake an award of costs and attorney’s fees. Comfort Lake appeals; Dresel and Fain cross appeal the initial ruling. We conclude the claim for injunctive relief is moot, the claim for civil penalties is precluded by MPCA’s enforcement action, and the district court did not abuse its discretion in denying attorney’s fees. Accordingly, we affirm.

I. Background.

The timing of the various activities underlying this dispute is significant. In the Fall of 1994, MPCA issued Dresel and Fain a National Pollution Discharge Elimination System (“NPDES”) permit for construction of a Wal-Mart store in Forest' Lake, Minnesota. The permit required erosion and sediment control facilities because run-off of pollutants from the construction site threatened the water quality of nearby Comfort Lake and its tributaries. After investigating complaints, MPCA sent Dresel and Fain a warning letter on December 20, 1994, noting permit violations. Dresel and Fain responded in early January 1995, claiming to have properly addressed these problems.

On January 31, Comfort Lake, a non-profit association, dedicated to protecting the lake *354 and its tributaries, issued a notice of intent to sue Dresel and Fain over the same NPDES permit viplations noted in MPCA’s December 20 letter. Under the Clean Water Act, plaintiff must give such a notice of intent to sue to the Administrator, of the Environmental Protection Agency, the affected state agency, and the alleged violator at least sixty days before commencing a citizen suit. See 33 U.S.C. § 1365(b); Hallstrom v. Tillamook County, 493 U.S. 20, 110 S.Ct. 304, 107 L.Ed.2d 237 (1989). On April 3, Comfort Lake filed this citizen suit under 33 U.S.C. § 1365(a)(1).

Meanwhile, on February 13, MPCA again inspected the construction site, found continuing violations, and ■ issued a Notice of Violation to Dresel and Fain. They responded that the violations were remedied, but after another inspection,. MPCA issued a follow-up letter citing specific permit violations and demanding, within ten days, “a detailed schedule for correcting these deficiencies.” MPCA issued a second Notice of Violation on May 10, advising Dresel and Fain that the MPCA Board, would consider issuing an administrative cease and desist order at its May 23 meeting. On May 19, Dresel and Fain reported full compliance with the permit. MPCA promptly inspected, and a May 22 internal agency memorandum states that the violations had indeed been corrected. ‘

Dresel and Fain completed store construction in November 1995 and applied for termination of the NPDES permit. MPCA terminated the permit on April 11, 1996. MPCA staff negotiated and then proposed to the agency Board a Stipulation Agreement requiring payment of $12,203 in civil penalties for all past violations of the permit, including $6,100 payable to the City of Forest Lake for “a diagnostic study of Comfort Lake.” On May 21, 1996, MPCA issued its thirty-four page Findings of Fact, Conclusions of Law and Order approving the Stipulation Agreement over Comfort Lake’s opposition. The Stipulation Agreement recites that it

covers all alleged NPDES/SDS Permit violations that occurred at the Wal-Mart construction site and that were known by MPCA as of the effective date of this Agreement. The alleged violations are considered past violations that have been satisfactorily resolved or corrected. This

Agreement contains no remedial or corrective action requirements because construction at the Wal-Mart site has been completed. The NPDES/SDS Permit has been terminated; thus, there is no likelihood that NPDES/SDS Permit violations will recur at the Wal-Mart site.

Dresel and Fain then renewed their motion for summary.judgment. The district court granted that motion, and in a separate order denied Comfort Lake an award of costs and. attorney’s fees. These appeals followed. Broadly stated, the issues are whether MPCA’s enforcement actions preclude Comfort Lake’s claims for injunctive relief and civil penalties, and whether the district court abused its discretion in denying an award of costs and attorney’s fees.

II. Is the Claim for Injunctive Relief IVIoot?

The doctrine that federal courts may not decide moot cases “derives from the requirement of Article III of the Constitution under which the exercise of judicial power depends upon the existence of a case or controversy.” Liner v. Jafco, Inc., 375 U.S. 301, 306 n. 3, 84 S.Ct. 391, 394 n. 3, 11 L.Ed.2d 347 (1964). A case may become moot at. any time. “[I]t is not enough that a dispute was very much alive when suit was filed____ The parties must continue to have a ‘personal stake in the outcome’ of the lawsuit.” Lew is v. Continental Bank Corp., 494 U.S. 472, 477-78, 110 S.Ct. 1249, 1253-54, 108 L.Ed.2d 400 (1990).

A claim for injunctive relief may become moot if challenged conduct permanently ceases. When the alleged violation underlying a Clean Water Act citizen suit ceases while the suit is pending, “[Ijongstand-ing principles of mootness ... prevent the maintenance of suit when there is no reasonable expectation that the wrong will be repeated.” Gwaltney of Smithfield v. Chesapeake Bay Found., Inc., 484 U.S. 49, 66, 108 S.Ct. 376, 386, 98 L.Ed.2d 306 (1987) (quotation omitted). The district court concluded that Comfort Lake’s claim for injunctive re *355 lief became moot when Dresel and Fain’s NPDES permit terminated and MPCA approved the Stipulation Agreement. We agree.

At the outset, we address the applicable mootness standard. Comfort Lake argues that Dresel and Fain must prove it is “absolutely clear

Free access — add to your briefcase to read the full text and ask questions with AI

Related

StarLink Logistics, Inc. v. ACC, LLC
101 F.4th 431 (Sixth Circuit, 2024)
Munt v. Schnell
D. Minnesota, 2020
Puget Soundkeeper Alliance v. Louis Dreyfus Commodities LLC
192 F. Supp. 3d 1165 (W.D. Washington, 2016)
State of Arizona v. Raytheon Company
761 F.3d 1005 (Ninth Circuit, 2014)
Ohio Valley Environmental Coalition, Inc. v. Alex Energy, Inc.
34 F. Supp. 3d 632 (S.D. West Virginia, 2014)
Club v. ICG Eastern, LLC
833 F. Supp. 2d 571 (N.D. West Virginia, 2011)
Ohio Valley Environmental Coalition, Inc. v. Hobet Mining, LLC
723 F. Supp. 2d 886 (S.D. West Virginia, 2010)
City of Duluth v. Fond Du Lac Band of Lake Superior Chippewa
708 F. Supp. 2d 890 (D. Minnesota, 2010)
Cambrians for Thoughtful Development v. Didion Milling, Inc.
571 F. Supp. 2d 972 (W.D. Wisconsin, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
138 F.3d 351, Counsel Stack Legal Research, https://law.counselstack.com/opinion/comfort-lake-association-inc-plaintiff-appellantcross-v-dresel-ca8-1998.