Columbia Engineering International, Ltd. v. Dorman

602 S.W.2d 72, 1980 Tex. App. LEXIS 4307
CourtCourt of Appeals of Texas
DecidedApril 17, 1980
Docket8324
StatusPublished
Cited by13 cases

This text of 602 S.W.2d 72 (Columbia Engineering International, Ltd. v. Dorman) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Columbia Engineering International, Ltd. v. Dorman, 602 S.W.2d 72, 1980 Tex. App. LEXIS 4307 (Tex. Ct. App. 1980).

Opinions

DIES, Chief Justice.

Sometime prior to March 1974, the Kirby Lumber Corporation (hereafter Kirby) acquired a plant (Evans Co.) across Highway 92 (east side) from its mill in Silsbee with the intention to build in its place a particle board plant. The consulting engineer for the plant was Columbia Engineering International, Ltd. (hereafter Columbia). The general contractor was Casey Enterprises, Inc. (hereafter Casey). McBride Steel Erection Corp. (hereafter McBride) was a subcontractor fabricating steel. Minnis Erection Corporation (hereafter Minnis) was a subcontractor and dismissed from the case on summary judgment. United States Fidelity and Guaranty Co. (hereafter United) was intervenor.

Next to the east side fence of the newly acquired property Gulf States Utilities Company (hereafter Gulf States) owned and maintained a high voltage tower, and the lines extended across Kirby’s fence and over its property.

Part I

On March 4, 1974, James M. Dorman and Walter W. Blackshear — ironworkers, employees of McBride — were assisting in the unloading of prefabricated steel near this east fence. This steel was “hooked” on both ends from the truck on which it was delivered by cables from a “cherry picker” with a “telescopic” (movable) crane or boom. The operator of the crane, Flowers — also a McBride employee — would then swing the steel off the truck and lower it to the ground. Dorman and Blackshear “guided” the steel, one at each end, holding the apparatus attached to the cable. On this date (March 4, 1974), the crane came into contact with Gulf States’ power line causing 15,000 volts of electricity to flow through the cable and the bodies of Dorman and Blackshear, both of whom were horribly and permanently injured.

A suit resulted in which Dorman and Blackshear were plaintiffs below.

Shortly, prior to trial, Dorman and Black-shear settled their cases with Kirby, Gulf States, Casey, Minnis, and United for four hundred thousand dollars ($400,000). Suits for contribution and indemnity flowed between the settling defendants and Columbia. After a lengthy trial, a jury found Columbia one hundred percent negligent and awarded Dorman and Blackshear substantial damages. Additionally, the trial court decreed that Columbia should respond to their cross-actions for indemnity and ordered Columbia to make them whole for the four hundred thousand dollars ($400,000) they had paid in settlement prior to trial to Dorman and Blackshear. It is from this judgment Columbia has perfected this appeal. For clarity, the parties will be referred to in this opinion generally by name.

Columbia’s first point is that “[t]he trial court erred in admitting into evidence the testimony of . . . Dorman, that he assumed that [Columbia’s] Engineer, . or someone from Columbia indicated to him and Blackshear, to place the steel beams [74]*74against the fence where the accident occurred, over [Columbia’s] objection that such evidence was hearsay, speculative, and not based upon fact.”

Herb Moss was Columbia’s main supervisor and engineer on the work site. On March 4, 1974, Dorman and Blackshear began unloading the steel dunnage further from the fence referred to herein and further from the power line. Dorman then testified his foreman (Milton Nanny, Sr.) came to him and ordered him to move the steel closer to the fence (and therefore the power line). Dorman at first refused, but Nanny, Sr., insisted saying, “Because Mr. Moss says there is going to be a little building come out here and it’s going to be in the way.” This evidence did not derive its probative force from the competency and credibility of Dorman and was, therefore, inadmissible as hearsay. See the many authorities cited in 24 Tex.Jur.2d Evidence § 557 at 51 (1961); also see 24 Tex.Jur.2d Evidence § 560 at 57 (1961).

However the trial court ruled: “[T]hat portion of the testimony is stricken,” and “The jury is admonished not to consider it for any purposes of what Nanny told him that Moss said.” “This therefore cures the error.” 1 C. McCormick & R. Ray, Texas Law of Evidence § 29 (Texas Practice 2d ed. 1956). This point is overruled.

We believe this appeal will be better understood if we next take up Columbia’s Points 6 through 11. These points contend the findings of negligence and proximate cause against Columbia are supported by no or insufficient evidence or are against the great weight and preponderance of the evidence.

We review these points under the guidance of Garza v. Alviar, 395 S.W.2d 821 (Tex.1965), and In re King’s Estate, 150 Tex. 662, 244 S.W.2d 660 (1951).

Dorman testified he saw Nanny, Sr. (his McBride supervisor) and Moss talking. He than saw Moss point to the dunnage (on which the steel was placed) and then “pointing ... to move it over towards the fence.” Nanny then came over the told Dorman to move it. He (Dorman) testified Moss gave “us the highball” which means he wanted the dunnage and steel placed next to the fence (and power line).

Herbert Moss began working for Columbia in June 1978 on loan from another company. He was a consulting engineer and “had to coordinate the work [at Kirby].” He inspected the work and then would certify to Kirby the amount of work that would be done by each contractor. It was on this basis Kirby paid the contractors. Friday before the accident, Nanny, Sr. (McBride foreman) asked Moss if he could unload the steel at the south end of the blending building. Moss answered, “I told him I had no objection to him unloading that steel there, but to watch that high power line above. . . . ” The blending building was sixty or seventy feet from the east fence (and hence about that much farther from the power line). However, Moss said Nanny was going to unload “[a] little southwest of the blending building, [w]hich would be by the fence”; to which Moss had no objection when asked by Nanny, Sr. He denied telling Nanny, Sr. “where to locate this steel at a fenceline on Monday,” but he “wasn’t surprised that they unloaded it over there.” He didn’t know Nanny, Sr., was doing this or he would have stopped it and, “Yes, sir, I had the authority to stop him. .” On examination by Kirby’s attorney, Moss admitted the hazard would have been the same whether the steel was unloaded at the Friday or Monday location. Kirby knew nothing of the unloading. Kirby was relying on Moss “as the construction supervisor.” Moss thought Columbia was a little unfair in not providing him with more help. He took no action to de-energize this power line. Columbia represented Kirby insofar as safety was concerned in dealing with the contractors. Had he been furnished more help by Columbia “probably” this wouldn’t have happened. He was asked, “Well, it was a joint thing between you and Nanny [where to unload the steel].” To this he answered, “Well, in a way.” He was asked, “do you think the steel was laid in an unsafe spot?” To which [75]*75he replied, “no doubt about it.” He admitted he had the power under the contract to direct the site of unloading.

Nanny, Sr., testified the day the accident happened he decided where the steel was to be stacked, “but prior to that Herb Moss and myself had talked about it, and he said that [he] agreed to it.”

McBride testified Columbia was to supervise the job.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Guentzel v. Toyota Motor Corp.
768 S.W.2d 890 (Court of Appeals of Texas, 1989)
Shenandoah Associates v. J & K Properties, Inc.
741 S.W.2d 470 (Court of Appeals of Texas, 1987)
UMC, INC. v. Coonrod Elec. Co., Inc.
667 S.W.2d 549 (Court of Appeals of Texas, 1983)
Badger v. Symon
661 S.W.2d 163 (Court of Appeals of Texas, 1983)
Cypress Creek Utility Service Co. v. Muller
640 S.W.2d 860 (Texas Supreme Court, 1982)
General Electric Co. v. Schmal
623 S.W.2d 482 (Court of Appeals of Texas, 1981)
Payne v. Gould, Inc.
503 F. Supp. 1060 (E.D. Texas, 1980)
Migues v. Nicolet Industries, Inc.
493 F. Supp. 61 (E.D. Texas, 1980)
Columbia Engineering International, Ltd. v. Dorman
602 S.W.2d 72 (Court of Appeals of Texas, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
602 S.W.2d 72, 1980 Tex. App. LEXIS 4307, Counsel Stack Legal Research, https://law.counselstack.com/opinion/columbia-engineering-international-ltd-v-dorman-texapp-1980.