Raymond Leger, Cross-Appellant v. Drilling Well Control, Inc., Dresser Offshore Services, Inc., Cross-Appellee

592 F.2d 1246, 1979 U.S. App. LEXIS 15527, 1980 A.M.C. 288
CourtCourt of Appeals for the Fifth Circuit
DecidedApril 10, 1979
Docket77-1310
StatusPublished
Cited by118 cases

This text of 592 F.2d 1246 (Raymond Leger, Cross-Appellant v. Drilling Well Control, Inc., Dresser Offshore Services, Inc., Cross-Appellee) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Raymond Leger, Cross-Appellant v. Drilling Well Control, Inc., Dresser Offshore Services, Inc., Cross-Appellee, 592 F.2d 1246, 1979 U.S. App. LEXIS 15527, 1980 A.M.C. 288 (5th Cir. 1979).

Opinion

FAY, Circuit Judge:

Appellee, Raymond Leger, was injured while working aboard a barge owned by appellant Dresser Offshore Services, Inc. [“Dresser”]. At the time of the accident, Leger was employed by Drilling Well Control, Inc. [“DWC”], a service company which specialized in the control of high pressure oil wells. Dresser was using the barge in a workover operation on an offshore oil well owned by Continental Oil Company [“Continental”]. DWC was called to the well site by Continental to correct technical difficulties which Continental and Dresser were encountering in the workover operation. On March 21, 1969, Leger and two other DWC employees arrived by workboat at the barge. They brought with them a pipe and bottle rack to be used in the workover operation. After the pipe and bottle rack were unloaded from the workboat, Leger first.asked John Bullard, the senior Continental representative aboard the vessel, for the use of the barge’s crane in helping to unload the pipe from the bottle rack. Bullard refused, indicating that the crane was too busy at that time. Leger then asked Hilliard Guidry, a Dresser employee, for the use of the crane. Guidry also refused. Leger then began to unload the pipe by hand, and he sustained the injury which is the subject of this suit.

Leger filed suit against his employer, DWC, under the Jones Act and general maritime law and against Continental and Dresser under general maritime law. On the morning of the trial Leger settled his claims against DWC and Continental for a total of $182,331.05. The Travelers Insurance Company, which provided liability insurance for DWC and Continental, settled Leger’s claim against DWC for $82,331.05 and Leger’s claim against Continental for $100,000.00. Dresser’s only issue on appeal is the effect of this settlement on the amount Leger was entitled to recover from Dresser. 1

Leger’s case against Dresser was tried twice. At the first trial, the jury found Leger’s damages to be $284,090.00. The trial court and Dresser’s counsel then learned that the release and indemnity agreement between Leger and Travelers Insurance Company provided that Travelers was to receive one-half of any funds actually collected by Leger from Dresser, whether the funds were collected as a result of judgment or settlement. The trial court granted Dresser’s motion for a new trial on the ground that the jury should have been informed that DWC and Continental were originally defendants, that Leger had settled his claims against them, and that Travelers was to receive one-half of all sums received by Leger from Dresser. The court considered it necessary that the jury be aware of the continuing interest in the law suit of the various witnesses from DWC and Continental.

The issue at the new trial was limited to liability, since the additional information to *1248 be submitted to the jury would have no bearing on the amount of damages. Thus, Leger's damages remained fixed at $284,-090.00. At the new trial the jury found the negligence of the parties as follows: Dresser — 45%; Continental — 20%; DWC — 0%; and Leger — 35% contributory negligence. Dresser filed a motion to alter the judgment, requesting that the court afford Dresser a credit against the judgment for the full dollar amount of the settlement ($182,331.05) between Leger, DWC, and Continental. The motion was denied, and the court, in accord with rules hereafter discussed, entered judgment against Dresser for $127,840.00. That amount reflects the total damages of $284,090.00 reduced by $99,430.17 representing the 35% contributory negligence of the plaintiff and by $56,-817.24 representing the 20% negligence attributed to Continental. No reduction in the judgment was made for DWC’s settlement since DWC was found not to be negligent. To put it another way, Dresser was charged by the judgment to pay only the portion of the total damages proportionate to its percentage of negligence (45% of $284,090.00).

The rules employed by Judge Hunter to determine the amount of credit against the judgment were derived from the following principles:

(1) Where the concurrent fault of two or more persons combine to produce injury, the parties at fault are joint tortfeasors and, as such, are liable to the injured plaintiff. 2

(2) The Federal Rules of Civil Procedure have liberalized joinder 3 and impleader rules in maritime claims to facilitate the presence of all interested parties in one action. All potential joint tortfeasors may be made third party defendants, pursuant to Rule 14(c). Application of the Rule in this manner is the only possible interpretation of it consistent with its purpose and intent.

(3) Where there are two or more defendants (alleged joint tortfeasors), and the plaintiff settles with and grants a release as to one or more of them, reserving his rights against the remaining, the settling defendants are relieved of any further liability to the plaintiff. 4

(4) When two or more parties have contributed by their fault to cause injury to another, the liability for such damage is to be allocated among the parties proportionately to the comparative degree of their fault. 5

(5) A tortfeasor seeking to assert a reduction by the degree of fault of alleged joint tortfeasors must prove by a preponderance of the evidence that the settling defendant was, in fact, at fault. 6

(6) A settling party’s negligence is considered only when he has been made a party to the suit. In such a case, the judgment awarded to the claimant against the nonsettling defendant is credited with the dollar amount represented by the proportion of negligence, if any, attributed to the settling parties.

Leger v. Drilling Well Control, Inc., 69 F.R.D. 358, 362-63 (W.D.La.1975) (original footnotes omitted). While Dresser concedes the validity of the first five Leger principles, it argues with respect to the sixth that “where two of the original defendants have settled with the plaintiff for more than would have been their pro rata share of the total damages awarded to the plaintiff, the application of the doctrine of comparative fault constitutes an abuse of discretion in *1249 that it allows double recovery in favor of the plaintiff.” We do not agree.

Judge Hunter’s able opinion is in full accord with recent Supreme Court decisions in this area. The Supreme Court clarified in Cooper Stevedoring Co. v. Kopke, 417 U.S. 106, 94 S.Ct. 2174, 40 L.Ed.2d 694 (1974) that there no longer exists a blanket prohibition against contribution in non-collision cases. The Court left open the question of whether contribution should be “based on an equal division of damages or should be relatively apportioned in accordanee with the degree of fault of the parties.” Id. at 108 n.3, 94 S.Ct. at 2176 n.3. In United States v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Boston Ship Repair, LLC v. Starr Indemnity & Liability Co.
997 F. Supp. 2d 118 (D. Massachusetts, 2014)
Berg v. Footer
673 A.2d 1244 (District of Columbia Court of Appeals, 1996)
Coats v. Penrod Drilling Corp.
61 F.3d 1113 (Fifth Circuit, 1995)
Odeco Oil & Gas Co. v. Petroleum Helicopters, Inc.
857 F. Supp. 29 (E.D. Louisiana, 1994)
Boykin v. Bergesen D.Y. A/S
842 F. Supp. 874 (E.D. Virginia, 1994)
Amerada Hess v. Owens-Corning Fiberglass
627 So. 2d 367 (Supreme Court of Alabama, 1993)
Williams v. Fab-Con, Inc.
990 F.2d 228 (Fifth Circuit, 1993)
Boyett v. Keene Corp.
815 F. Supp. 204 (E.D. Texas, 1993)
McDermott, Inc. v. Iron
Fifth Circuit, 1992
Loeber v. United States
803 F. Supp. 1154 (E.D. Louisiana, 1992)
In Re Granada Partnership Securities Litigations
803 F. Supp. 1236 (S.D. Texas, 1992)
Stewart Title Guaranty Co. v. Sterling
822 S.W.2d 1 (Texas Supreme Court, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
592 F.2d 1246, 1979 U.S. App. LEXIS 15527, 1980 A.M.C. 288, Counsel Stack Legal Research, https://law.counselstack.com/opinion/raymond-leger-cross-appellant-v-drilling-well-control-inc-dresser-ca5-1979.