Cogentrix Energy Power Management, LLC v. FERC

24 F.4th 677
CourtCourt of Appeals for the D.C. Circuit
DecidedJanuary 28, 2022
Docket20-1389
StatusPublished

This text of 24 F.4th 677 (Cogentrix Energy Power Management, LLC v. FERC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cogentrix Energy Power Management, LLC v. FERC, 24 F.4th 677 (D.C. Cir. 2022).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

Argued November 12, 2021 Decided January 28, 2022

No. 20-1389

COGENTRIX ENERGY POWER MANAGEMENT, LLC AND VISTRA CORP., PETITIONERS

v.

FEDERAL ENERGY REGULATORY COMMISSION, RESPONDENTS

NEW ENGLAND STATES COMMITTEE ON ELECTRICITY, INC., INTERVENOR

On Petition for Review of Orders of the Federal Energy Regulatory Commission

Christopher R. Jones argued the cause for petitioners. With him on the briefs were Miles H. Kiger and Jessica Harris Miller. Nicholas M. Gladd entered an appearance.

Matthew J. Glover, Attorney, Federal Energy Regulatory Commission, argued the cause for respondent. With him on the brief were Matthew R. Christiansen, General Counsel, Robert H. Solomon, Solicitor, and Beth G. Pacella, Deputy Solicitor. Anand R. Viswanathan, Attorney, entered an appearance. 2

Before: SRINIVASAN, Chief Judge, KATSAS, Circuit Judge, and RANDOLPH, Senior Circuit Judge.

Opinion for the Court filed by Senior Circuit Judge RANDOLPH.

RANDOLPH, Senior Circuit Judge: Cogentrix Energy Power Management, LLC and Vistra Corp. own electric generation facilities in New England. Their petition for judicial review is directed at the Federal Energy Regulatory Commission’s orders affecting their facilities. ISO New England Inc., 171 FERC ¶ 61,160 (2020) (“Initial Order”), on reh’g, 172 FERC ¶ 61,251 (2020) (“Rehearing Order”). Electric generation facilities in this area receive payment for their services through formula rates established by ISO New England Inc.’s open access transmission tariff (the “ISO New England tariff”).1 The Commission’s orders approved Schedule 17, an amendment to the ISO New England tariff. Schedule 17 established a new recovery mechanism for costs incurred by certain electric generation and transmission facilities to comply with mandatory reliability standards the Commission had approved.

The Commission ruled that Cogentrix and Vistra could use Schedule 17 to recover only costs incurred after they filed a cost-based rate with the Commission pursuant to Federal Power Act (“FPA”) § 205, 16 U.S.C. § 824d, and the Commission had approved the rate. The Commission reasoned that the filed rate doctrine and its corollary, the rule against retroactive ratemaking, limited recovery to prospective costs.

1 ISO New England is a regional transmission organization that coordinates electricity transmission in New England and whose tariff governs recovery of transmission rates. Emera Me. v. FERC, 854 F.3d 9, 16 (D.C. Cir. 2017). 3

I.

A.

Congress added electric grid reliability to the Commission’s regulatory responsibilities in the Electricity Modernization Act of 2005, Pub. L. No. 109-58, tit. XII, 119 Stat. 941 (2005).2 The Act created FPA § 215, 16 U.S.C. § 824o, which gives the Commission the power to “adopt and enforce mandatory technical reliability standards for facilities that make up the national energy grid.” New York v. FERC, 783 F.3d 946, 950 (2d Cir. 2015). Congress provided the Commission with this authority in order to enhance the reliability of the electric grid after a large-scale blackout in the northeastern United States in summer 2003. Id.

Section 215 does not give the Commission authority to write mandatory reliability standards. Instead, the Commission may certify a non-governmental organization as the “Electric Reliability Organization” to write and propose the standards. 16 U.S.C. § 824o(c), (d). The Commission may approve such standards if the Commission finds that the standards are “just, reasonable, not unduly discriminatory or preferential, and in the public interest.” Id. § 824o(d)(2). The North American Electric Reliability Corporation has been the certified Electric Reliability Organization since 2006. N. Am. Elec. Reliability Corp., 116 FERC ¶ 61,062 (2006); Fed. Energy Regul. Comm’n, Reliability Primer 34–35 (2020).

In 2013, the Commission approved a new set of critical infrastructure protection reliability standards the Corporation proposed. Version 5 Critical Infrastructure Protection

2 The Electricity Modernization Act is part of the Energy Policy Act of 2005, Pub. L. No. 109-58, 119 Stat. 594 (2005). 4

Reliability Standards, 145 FERC ¶ 61,160 (2013) (“Reliability Standards”), on clarification & reh’g, 146 FERC ¶ 61,188 (2014) (“Reliability Standards Clarification Order”). These new standards require system operators like ISO New England to designate the system’s generation and transmission facilities as low-, medium-, or high-impact, based on the facilities’ relative importance to the reliable operation of the electric grid. Reliability Standards, at PP. 2, 41. All facilities must comply with the low-impact reliability standards. Id. at P. 2. Facilities designated as medium- or high-impact must comply with additional reliability standards. Id. Medium- and high-impact facilities had to comply with the new standards by April 1, 2016. Reliability Standards Clarification Order, at P. 7.

B.

ISO New England started designating transmission and generation facilities as medium-impact facilities in 2013 and 2014, respectively. Those critical facilities3 began to incur costs to comply with the standards. Cogentrix, Vistra, and other critical facility owners commenced negotiations with ISO New England regarding compensation for those compliance costs. Those discussions resulted in Schedule 17.

Schedule 17 amends the ISO New England tariff to include a cost-based recovery mechanism for expenses that critical facility owners incur to comply with the new standards. A facility may recover costs under Schedule 17 “only to the extent” that it satisfies four conditions. Schedule 17 § 2.2(A), J.A. 61. First, the costs must be “incurred . . . during the period in which the subject facility is designated as [a] []Critical

3 Like the parties, we use “critical facilities” to refer to electric generation and transmission facilities that are designated by ISO New England as medium-impact facilities. 5

Facility” by ISO New England. Id. § 2.2(A)(i). Second, the critical facility owner must specify a cost recovery period and the costs must have been paid during that period. Id. § 2.2(A)(ii). Third, the costs must be “presented by the []Critical Facility Owner in a Section 205 filing and approved by the Commission.” Id. § 2.2(A)(iii). Fourth, the costs must “satisfy all other conditions for recovery, as set forth in this Schedule 17.” Id. § 2.2(A)(iv).

On January 6, 2020, ISO New England filed Schedule 17 with the Commission with a requested effective date of March 6, 2020.4 The Commission had concerns about the temporal scope of cost recovery permitted by Schedule 17 § 2.2(A)(i), so the Commission filed a deficiency letter. In the letter, the Commission asked ISO New England whether it “intends to allow the recovery of costs incurred prior to the requested effective date” of Schedule 17 and, if so, to “explain how this cost recovery mechanism would be consistent with the filed rate doctrine and the rule against retroactive ratemaking.” J.A. 132.

ISO New England responded that Schedule 17 § 2.2(A)(i) “does not address the recovery of [mandatory reliability costs] incurred prior to [Schedule 17’s] requested effective date of March 6, 2020.” Id. at 135.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
24 F.4th 677, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cogentrix-energy-power-management-llc-v-ferc-cadc-2022.