Coastal Chem, Inc. v. Brown

35 S.W.3d 90, 2000 WL 1707244
CourtCourt of Appeals of Texas
DecidedJanuary 18, 2001
Docket14-99-00045-CV
StatusPublished
Cited by27 cases

This text of 35 S.W.3d 90 (Coastal Chem, Inc. v. Brown) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coastal Chem, Inc. v. Brown, 35 S.W.3d 90, 2000 WL 1707244 (Tex. Ct. App. 2001).

Opinion

OPINION

MAURICE E. AMIDEI, Justice.

Coastal Chem, Inc. (“Coastal”) appeals the judgment entered in favor of John Brown, a Division of Trafalgar House, Inc., and Davy McKee Corporation, now known as Kvaerner John Brown, a Division of Kvaerner U.S., Inc. (collectively, “John Brown”), in an action for breach of a construction contract. We affirm.

I. Factual Background

In 1990, Coastal and John Brown 1 entered into a contract for the construction of a Methyl Tertiary Butyl Ether (“MTBE”) plant for Coastal in Cheyenne, Wyoming. The contract consists of two parts. The first is the Master Contract under which John Brown agreed to provide services for engineering, design, procurement, construction of, and start-up assistance with, designated Coastal projects and operations. The second is the Assignment, which provided for the design, engineering, and construction of the MTBE plant.

The contract provides that John Brown would be entitled to an early-completion bonus if the plant were substantially complete eighteen months from August 27, 1990. On that early-completion target date (February 29, 1992), Coastal accepted the plant as substantially complete. After Coastal’s acceptance, several problems arose with the plant. Coastal claims these problems prevented the plant from being substantially complete on February 29,

1992. Instead, Coastal claims, the plant was substantially complete on January 6, 1993. The early-completion bonus, if earned, was payable when the plant was finally complete, an event which Coastal stipulated occurred on November 15, 1993. Coastal refused-to pay John Brown the early-completion bonus.

John Brown sued Coastal for breach of the construction contract for failure to pay (1) the early-completion bonus and (2) amounts owed for removing and replacing two boilers as change or extra work under the contract. John Brown also brought a claim for the breach of a second contract to share in insurance proceeds Coastal sought in connection with the repair of the plant’s steam active reforming technology (“STAR”) unit, which sustained damage in an attempted start-up of the plant. John Brown further asserted a claim for quantum meruit for services provided outside the scope of the contract in connection with the STAR unit. Coastal brought a counterclaim, asserting that John Brown failed to complete construction of the plant on time and, therefore, Coastal was entitled to a delay penalty under the contract. Coastal sought other damages for John Brown’s failure to complete certain assigned work and for Coastal’s costs of having to replace the two boilers.

Before trial, Coastal admitted to owing John Brown $1.3 million in insurance proceeds for the repair of the STAR unit received from the settlement of a lawsuit Coastal brought against the insurance carriers. Coastal and John Brown stipulated to, depending on the jury’s finding on the substantial completion date, a maximum bonus of $4,301,890 and a maximum penalty of $2,150,945.

The jury found that: (1) the plant was substantially complete on February 29, 1992; (2) the work John Brown performed on the boilers was change or extra work; (3) John Brown performed $2,004,173 in compensable work outside the scope of the contract on the STAR unit; (4) John Brown and Coastal agreed that John Brown would be reimbursed $1.3 million in insurance proceeds for John Brown’s work *94 on the STAR unit; and (5) John Brown failed to comply with the contract with respect to various components of assigned work.

The trial court entered final judgment in favor of John Brown in the amount of $4,301,890 as an early-eompletion bonus, $1,914,648 as extra work under the contract, and $2,004,173 as work performed outside the scope of the contract, plus prejudgment interest. The trial court also entered final judgment in favor of Coastal in the amount of $697,492 for John Brown’s failure to complete certain assigned work under the contract, plus prejudgment interest. Coastal’s award was to be credited against John Brown’s $1,914,648 recovery for extra work.

II. Analysis of Issues PRESENTED

A. Date of Substantial Completion

In its first issue, Coastal contends there is no evidence to support the jury’s finding that the plant was substantially complete as of February 29, 1992. When reviewing the legal sufficiency of the evidence, we consider only the evidence and inferences tending to support the trial court’s finding, and disregard all contrary evidence and inferences. See Southwestern Bell Mobile Sys. v. Franco, 971 S.W.2d 52, 54 (Tex.1998) (per curiam). We will sustain a no evidence point if there is no more than a scintilla of evidence to support the finding. See General Motors Corp. v. Sanchez, 997 S.W.2d 584, 588 (Tex.1999).

Coastal also claims that the evidence establishes as matter of law that the plant was not substantially complete until January 6, 1993. In addressing this issue, we must first examine the record for evidence supporting the jury’s finding, while ignoring all evidence to the contrary. See Sterner v. Marathon Oil Co., 767 S.W.2d 686, 690 (Tex.1989). Then, if there is no evidence to support the fact finder’s answer, we examine the entire record to determine if the contrary proposition is established as a matter of law. See id.

1. Meaning of “Substantially Complete” Under the Contract

Coastal contends “substantially complete” means that the plant actually had to function and be ready for safe start-up. John Brown, on the other hand, claims that “substantially complete” required only successful installation, not a fully-operational plant.

When construing a contract, we must give effect to the true intentions of the parties as expressed in the written instrument. See Lenape Resources Corp. v. Tennessee Gas Pipeline Co., 925 S.W.2d 565, 574 (Tex.1996). We must read the contract as a whole, rather than by isolating a certain phrase, sentence, or section of the contract. See State Farm Life Ins. Co. v. Beaston, 907 S.W.2d 430, 433 (Tex.1995). We are to give the language of the parties’ agreement its plain grammatical meaning unless doing so would defeat the parties’ intent. See DeWitt County Elec. Coop., Inc. v. Parks, 1 S.W.3d 96, 101 (Tex.1999).

With respect to substantial completion, Article 2.19 of Exhibit D to the Assignment states:

“SUBSTANTIALLY COMPLETE” shall mean that all ASSIGNED WORK has been completed consistent with the ASSIGNMENT DOCUMENTS, including Exhibit A.5, excluding only PUNCH LIST ITEMS.

Attachment A.5 to Exhibit A of the Assignment further provides:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

GB Tubulars, Inc. v. Union Gas Operating Co.
527 S.W.3d 563 (Court of Appeals of Texas, 2017)
Bluelinx Corp. v. Texas Construction Systems, Inc.
363 S.W.3d 623 (Court of Appeals of Texas, 2011)
Estate of Puckett v. Arvizu
364 S.W.3d 309 (Court of Appeals of Texas, 2010)
Ashford Partners, Ltd. v. ECO Resources, Inc.
379 S.W.3d 300 (Court of Appeals of Texas, 2010)
In Re Credit Suisse First Boston Mortgage Capital, L.L.C.
257 S.W.3d 486 (Court of Appeals of Texas, 2008)
Hirschfeld Steel Co. v. Kellogg Brown & Root, Inc.
201 S.W.3d 272 (Court of Appeals of Texas, 2006)
Oyster Creek Financial Corp. v. Richwood Investments II, Inc.
176 S.W.3d 307 (Court of Appeals of Texas, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
35 S.W.3d 90, 2000 WL 1707244, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coastal-chem-inc-v-brown-texapp-2001.