Coakley Landfill Group v. IT Corp.

2000 DNH 045
CourtDistrict Court, D. New Hampshire
DecidedFebruary 18, 2000
DocketCV-98-167-JM
StatusPublished

This text of 2000 DNH 045 (Coakley Landfill Group v. IT Corp.) is published on Counsel Stack Legal Research, covering District Court, D. New Hampshire primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Coakley Landfill Group v. IT Corp., 2000 DNH 045 (D.N.H. 2000).

Opinion

Coakley Landfill Group v. IT Corp. CV-98-167-JM 02/18/00 P UNITED STATES DISTRICT COURT FOR THE DISTRICT OF NEW HAMPSHIRE

The Coakley Landfill Group

v. Civil No. 98-167-JM Opinion No. 2000 DNH 045 IT Corporation

_________________________________ O R D E R

In the above-captioned diversity action, the Coakley

Landfill Group alleges that defendant IT Corporation breached its

contract to provide environmental remediation of the Coakley

Landfill and violated New Hampshire Revised Statutes Annotated

(RSA) 358-A. IT subsequently filed a third-party complaint

against members of the Coakley Group alleging breach of contract,

wrongful termination, and violation of RSA 358-A. Currently

before the court is IT's Motion for Partial Summary Judgment to

which the Coakley Group objects. For the reasons that follow,

the court grants IT's motion.

Background

In 1992, the United States and the State of New Hampshire

filed an action under §§ 106 and 107 of the Comprehensive Environmental Response Compensation and Liability Act (CERCLA)

against several municipalities and businesses allegedly

responsible for contamination of the Coakley Landfill. The group

of potentially responsible parties, who became known as the

Coakley Landfill Group, entered a consent decree, which required

them to implement the clean up of the site. The Group selected

IT as the remedial contractor to perform the work required by the

consent decree.

On July 26, 1996 the Group and IT entered into an agreement

describing the terms and conditions of the project. According to

this agreement, the Group would pay IT $4,808,766.40 to complete

the project.1 According to plaintiff, IT initially agreed to

have the landfill project completed by October 7, 1997. At IT's

request, this deadline was extended to October 31, 1997. As of

that date, IT had not completed construction of the project.

According to the agreement, the Group could terminate IT's

services if it was dissatisfied with the work performed by IT.

1The Group admits that this was the original contract price for the project but alleges that this price was subsequently adjusted to $4,625,196.40.

2 See Environmental Remediation Contractor Agreement, Article 19.2.

If the Group terminated the contract, the agreement provided

that:

the Contractor shall not be entitled to receive any further payment until the Work is finished. If, upon completion of the Work, the unpaid balance of the Contract Price exceeds all claims, costs, losses and damages sustained by the Group arising out of or resulting from completing the Work such excess will be paid to the Contractor.

Because of IT's alleged contract breaches, the Group

terminated the agreement in March of 1998 and filed a complaint

in state court, which was subsequently removed to this court.

Specifically, the Group alleges that IT repeatedly made

misrepresentations to the Group regarding IT's performance of

contractual obligations, failed to procure needed material for

the site, failed to employ competent personnel, and failed to

provide adequate oversight of the survey layout. According to

the Group, all of these alleged breaches resulted in IT's failure

to meet contractual deadlines. Up until the time that the Group

terminated IT, the Group had paid IT $1,130,544.07. In response

3 to the Group's suit, IT filed a third-party complaint2 against

individual members of the Coakley Group.

To complete the project, the Group hired another contractor,

H.E. Sargent, Inc. Sargent completed the project in August of

1998. Based on the Group's response to interrogatories over a

year ago, the cost to complete the project was $2,006,350.76.

See IT's Motion for Partial Summary Judgment, Exhibit C, Response

to Interrogatory No. 15.

Discussion

I. Standard of Review

The court may only grant a motion for summary judgment where

the "pleadings, depositions, answers to interrogatories, and

admissions on file, together with the affidavits, if any, show

that there is no genuine issue as to any material fact and that

the moving party is entitled to a judgment as a matter of law."

2In its amended complaint IT joined Colder, the project engineer selected by the Group to prepare the remedial design work plan and oversee remediation activities and SeaHill Construction, the principal supplier of sands and soils for the project as third party defendants.

4 Fed. R. Civ. P. 56(c). Accordingly, at this stage of the

proceeding, the court does not weigh the evidence and determine

the truth of the matter but instead determines whether there is a

genuine issue of fact for trial. See Stone & Michaud Ins. Bank

Five for Savings, 785 F. Supp. 1065, 1068 (D.N.H. 1992) (quoting

Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 249 (1986)). The

substantive law identifies which facts are material so that "only

disputes over facts that might affect the outcome of the suit

under the governing law will properly preclude the entry of

summary judgment. Factual disputes that are irrelevant or

unnecessary will not be counted." Caputo v. Boston Edison Co.,

924 F.2d 11, 12-13 (1st Cir. 1991) (quoting Anderson, 477 U.S. at

248) .

The party seeking summary judgment bears the initial burden

of establishing the lack of genuine issues of material fact. See

Celotex Corp. v. Catrett, 477 U.S. 317, 323 (1986); Quintero de

Quintero v. Aponte-Rogue, 974 F.2d 226, 227-28 (1st Cir. 1992) .

As a result, the court must view the entire record in the light

most favorable to the non-moving party, "''indulging all

5 reasonable inferences in that party's favor.'" Mesnick v.

General Elec. Co., 950 F.2d 816, 822 (1st Cir. 1991) (quoting

Griqqs-Rvan v. Smith, 904 F.2d 112, 115 (1st Cir. 1990)).

However, once a defendant has submitted a properly supported

motion for summary judgment, the plaintiff "may not rest upon

mere allegation or denials of his pleading, but must set forth

specific facts showing that there is a genuine issue for trial."

Anderson, 477 U.S. at 256.

2. Article 19.2 of the Agreement

In its motion, IT contends that the Group breached Article

19.2 of the agreement between IT and the Group. In support of

this claim IT alleges that (1) the adjusted contract price was

$4,808,7 66.40, (2) IT has only been paid $1,130,549.07, (3) the

project has been completed, and (4) the Group's cost to complete

the project was $2,006,350.76. Thus, IT alleges that the Group

is bound, according to Article 19.2 of the agreement, to pay IT

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Procter & Gamble Co.
356 U.S. 677 (Supreme Court, 1958)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Colantuoni v. Alfred Calcagni & Sons, Inc.
44 F.3d 1 (First Circuit, 1994)
Michael A. Caputo v. Boston Edison Company
924 F.2d 11 (First Circuit, 1991)
Samuel Mesnick v. General Electric Company
950 F.2d 816 (First Circuit, 1991)
Charles M. Thibeault v. Square D Company
960 F.2d 239 (First Circuit, 1992)
Dinhora Quintero De Quintero v. Awilda Aponte-Roque
974 F.2d 226 (First Circuit, 1992)
Jack v. Trans World Airlines, Inc.
854 F. Supp. 654 (N.D. California, 1994)
Stone and Michaud Ins., Inc. v. Bank Five for Sav.
785 F. Supp. 1065 (D. New Hampshire, 1992)
Commercial Union Assurance Co. v. Brown Co.
419 A.2d 1111 (Supreme Court of New Hampshire, 1980)
Coakley Landfill Group v. IT Corp.
116 F. Supp. 2d 237 (D. New Hampshire, 2000)
Logic Associates, Inc. v. Time Share Corp.
474 A.2d 1006 (Supreme Court of New Hampshire, 1984)
Parkhurst v. Gibson
573 A.2d 454 (Supreme Court of New Hampshire, 1990)
Miller v. Miller
578 A.2d 872 (Supreme Court of New Hampshire, 1990)
State v. Ellison
599 A.2d 477 (Supreme Court of New Hampshire, 1991)
Flanagan v. Prudhomme
644 A.2d 51 (Supreme Court of New Hampshire, 1994)
Keshishian v. CMC Radiologists
698 A.2d 1228 (Supreme Court of New Hampshire, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
2000 DNH 045, Counsel Stack Legal Research, https://law.counselstack.com/opinion/coakley-landfill-group-v-it-corp-nhd-2000.