Coakley Landfill Group v. IT Corp.

116 F. Supp. 2d 237, 2000 DNH 45, 2000 U.S. Dist. LEXIS 2649, 2000 WL 1480434
District Court, D. New Hampshire·Decided February 18, 2000·No. Civ. 98-167-JM·Published·Cited by 4 cases

Opinion

ORDER

MUIRHEAD, United States Magistrate Judge.

In the above-captioned diversity action, the Coakley Landfill Group alleges that defendant IT Corporation breached its contract to provide environmental remediation of the Coakley Landfill and violated New Hampshire Revised Statutes Annotated (RSA) 358-A. IT subsequently filed a third-party complaint against members of the Coakley Group alleging breach of contract, wrongful termination, and violation of RSA 358-A. Currently before the court is IT’s Motion for Partial Summary Judgment to which the Coakley Group objects. For the reasons that follow, the court grants IT’s motion.

Background

In 1992, the United States and the State of New Hampshire filed an action under §§ 106 and 107 of the Comprehensive Environmental Response Compensation and Liability Act (CERCLA) against several municipalities and businesses allegedly responsible for contamination of the Coakley Landfill. The group of potentially responsible parties, who became known as the Coakley Landfill Group, entered a consent decree, which required them to implement the clean up of the site. The Group selected IT as the remedial contractor to perform the work required by the consent decree.

On July 26, 1996 the Group and IT entered into an agreement describing the terms and conditions of the project. According to this agreement, the Group would pay IT $4,808,766.40 to complete the project. 1 According to plaintiff, IT initially agreed to have the landfill project completed by October 7, 1997. At IT’s request, *239 this deadline was extended to October 31, 1997. As of that date, IT had not completed construction of the project.

According to the agreement, the Group could terminate IT’s services if it was dissatisfied with the work performed by IT. See Environmental Remediation Contractor Agreement, Article 19.2. If the Group terminated the contract, the agreement provided that:

the Contractor shall not be entitled to receive any further payment until the Work is finished. If, upon completion of the Work, the unpaid balance of the Contract Price exceeds all claims, costs, losses and damages sustained by the Group arising out of or resulting from completing the Work such excess will be paid to the Contractor.

Because of IT’s alleged contract breaches, the Group terminated the agreement in March of 1998 and filed a complaint in state court, which was subsequently removed to this court. Specifically, the Group alleges that IT repeatedly made misrepresentations to the Group regarding IT’s performance of contractual obligations, failed to procure needed material for the site, failed to employ competent personnel, and failed to provide adequate oversight of the survey layout. According to the Group, all of these alleged breaches resulted in IT’s failure to meet contractual deadlines. Up until the time that the Group terminated IT, the Group had paid IT $1,130,544.07. In response to the Group’s suit, IT filed a third-party complaint 2 against individual members of the Coakley Group.

To complete the project, the Group hired another contractor, H.E. Sargent, Inc. Sargent completed the project in August of 1998. Based on the Group’s response to interrogatories over a year ago, the cost to complete the project was $2,006,350.76. See IT’s Motion for Partial Summary Judgment, Exhibit C, Response to Interrogatory No. 15.

Discussion

1. Standard of Review

The court may only grant a motion for summary judgment where the “pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Fed. R.Civ.P. 56(c). Accordingly, at this stage of the proceeding, the court does not weigh the evidence and determine the truth of the matter but instead determines whether there is a genuine issue of fact for trial. See Stone & Michaud Ins. v. Bank Five for Savings, 785 F.Supp. 1065, 1068 (D.N.H.1992) (quoting Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 249, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986)). The substantive law identifies which facts are material so that “only disputes over facts that might affect the outcome of the suit under the governing law will properly preclude the entry of summary judgment. Factual disputes that are irrelevant or unnecessary will not be counted.” Caputo v. Boston Edison Co., 924 F.2d 11, 12-13 (1st Cir.1991) (quoting Anderson, 477 U.S. at 248, 106 S.Ct. 2505).

The party seeking summary judgment bears the initial burden of establishing the lack of genuine issues of material fact. See Celotex Corp. v. Catrett, 477 U.S. 317, 323, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986); Quintero de Quintero v. Aponte-Roque, 974 F.2d 226, 227-28 (1st Cir.1992). As a result, the court must view the entire record in the light most favorable to the non-moving party, “ ‘indulging all reasonable inferences in that party’s favor.’ ” Mesnick v. General Elec. Co., 950 F.2d 816, 822 (1st Cir.1991) (quoting Griggs-Ryan v. Smith, 904 F.2d 112, 115 (1st Cir.1990)). Howev *240 er, once a defendant has submitted a properly supported motion for summary judgment, the plaintiff “may not rest upon mere allegation or denials of his pleading, but must set forth specific facts showing that there is a genuine issue for trial.” Anderson, 477 U.S. at 256, 106 S.Ct. 2505.

2. Article 19.2 of the Agreement

In its motion, IT contends that the Group breached Article 19.2 of the agreement between IT and the Group. In support of this claim IT alleges that (1) the adjusted contract price was $4,808,766.40, (2) IT has only been paid $1,130,549.07, (3) the project has been completed, and (4) the Group’s cost to complete the project was $2,006,350.76. Thus, IT alleges that the Group is bound, according to Article 19.2 of the agreement, to pay IT $1,671,-871.41 — -the difference between the contract price, the payment IT has already received, and the Group’s cost to complete the project.

a. Claimed Attorneys’ Fees.

The Group contends that summary judgment is not appropriate at this time because of attorneys’ fees which it seeks to recover.

Free access — add to your briefcase to read the full text and ask questions with AI

Coakley Landfill Group v. IT Corp., 116 F. Supp. 2d 237, 2000 DNH 45, 2000 U.S. Dist. LEXIS 2649, 2000 WL 1480434 (D.N.H. 2000).

116 F. Supp. 2d 237 (Coakley Landfill Group v. IT Corp.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related