CNC Foundations, Inc. v. Turnbull-Wahlert, Construction, Inc.

CourtDistrict Court, E.D. Kentucky
DecidedMay 28, 2021
Docket2:20-cv-00118
StatusUnknown

This text of CNC Foundations, Inc. v. Turnbull-Wahlert, Construction, Inc. (CNC Foundations, Inc. v. Turnbull-Wahlert, Construction, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
CNC Foundations, Inc. v. Turnbull-Wahlert, Construction, Inc., (E.D. Ky. 2021).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF KENTUCKY NORTHERN DIVISION AT COVINGTON

CIVIL ACTION NO. 20-118-DLB

CNC FOUNDATIONS, INC. PLAINTIFF

v. MEMORANDUM OPINION AND ORDER

TURNBULL-WAHLERT, CONSTRUCTION, Inc., et al. DEFENDANTS

* * * * * * * * * * * * * * * * This matter is before the Court on three separate Motions to Dismiss filed by CNC Foundations, Inc., doing business as Helitech, in response to various counterclaims, (Docs. # 19, 23, and 26). Helitech’s first Motion to Dismiss as to KY Covington JRG, LLC, (Doc. # 19), was mooted by KY Covington JRG’s filing of an Amended Counterclaim, (Doc. # 24). Defendant Turnbull-Wahlert, Construction, Inc. and KY Covington JRG both filed Responses. (Docs. # 25 and 31, respectively). Thereafter, Helitech filed Replies. (Docs. # 30 and 32). Therefore, the Motions have been fully briefed and are ripe for the Court’s review. For the reasons stated herein, Plaintiff’s Motion to Dismiss Defendant Turnbull-Wahlert, Construction, Inc.’s Counterclaim, (Doc. # 23), is granted and Plaintiff’s Motion to Dismiss KY Covington JRG’s Amended Counterclaim, (Doc. # 26), is denied. I. FACTUAL AND PROCEDURAL BACKGROUND Plaintiff CNC Foundations, Inc. (“Helitech”) filed suit for breach of contract against Turnbull-Wahlert, Construction, Inc. (“TWC”), KY Covington JRG, LLC (“JRG”), and others alleging that Defendants had failed to pay Plaintiff for its work in the construction of the John R. Green Lofts Project (“the Project”) in Covington. (Doc. # 1 ¶ 7, 27, 33, 38, 52, 56). In response, Defendants TWC and JRG filed counterclaims related to the same Project. (Docs. # 16 and 24). Defendant TWC asserted counterclaims for (1) breach of contract, (2) negligence, (3) contractual indemnity, and (4) professional negligence. (Doc. # 16 at 23-26). Defendant JRG asserted a single counterclaim for negligence. (Doc. # 24 at 17). Helitech’s Motions to Dismiss ask the Court to dismiss TWC’s counterclaims

for negligence and professional negligence and JRG’s negligence counterclaim. (Docs. # 23 at 3 and 26 at 6-7). JRG is the developer and lessee of the property on which the at issue Project was located. (Docs. # 16 at 14 and 24 at 12). JRG and TWC entered into an agreement which provided that TWC would act as the design-builder for the Project. (Docs. # 16 at 17 and 24 at 12). TWC awarded Helitech the subcontract to perform foundations and earthwork improvements for the Project. (Docs. # 16 at 15 and 24 at 13). After entering into the original subcontract, Helitech agreed to perform additional work, including “pre- drilling,” 1 as part of its installation plan. (Docs. # 16 at 19 and 24 at 14). It is alleged that

Helitech failed to perform this pre-drilling before installing Vibratory Stone Columns (“VSCs”), which in turn, damaged the JR Green Building, the existing structure on the property. (Docs. # 24 at 14-17 and 16 at 20). In its counterclaim, TWC claims that Helitech was negligent and professionally negligent by breaching the duty of care laid out in the subcontract. (Doc. # 16 at 24-26). Similarly, JRG claims that Helitech was negligent because it owed JRG a duty to not damage the existing JR Green Building in completing its contract. (Doc. # 24 at 17).

1 The purpose of pre-drilling, as explained by Helitech, was “[t]o reduce the lateral pressure from the vibratory operation when installing [vibratory stone columns] in those locations closest to the JR Green building.” (Doc. # 1 ¶ 13). TWC puts forth a similar explanation in its counterclaim, stating that “predrilling [] limit[s] transition of vibration.” (Doc. # 16 at 16). While the parties disagree on the scope and duties implied by the contracts, no further factual background is required at this stage. II. ANALYSIS A. Standard of Review Granting a motion to dismiss is appropriate if a plaintiff fails “to state a claim upon

which relief can be granted.” Fed. R. Civ. P. 12(b)(6). Further, “to survive a motion to dismiss, a complaint must contain sufficient factual matter, accepted as true, to ‘state a claim for relief that is plausible on its face.” Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009) (quoting Bell Atl. Corp. v. Twombly, 550 U.S. 544, 570 (2007)). In order to have “facial plausibility,” the plaintiff must “plead[] factual content that allows the court to draw the reasonable inference that the defendant is liable for the misconduct alleged.” (Id.) (quoting Twombly, 550 U.S. at 556). In evaluating a motion to dismiss, a court should “construe the complaint in the light most favorable to the plaintiff” and “accept all well- pleaded factual allegations as true.” Hill v. Snyder, 878 F.3d 193, 203 (6th Cir. 2017)

(citing Ashcroft, 556 U.S. at 678; Twombly, 550 U.S. at 570). However, “mere conclusory statements, do not suffice” and legal conclusions “must be supported by factual allegations.” Ashcroft, 556 U.S. at 678-79. B. Helitech’s Motion to Dismiss TWC’s Counterclaims of Negligence and Professional Negligence Plaintiff Helitech argues that TWC cannot assert claims for breach of contract and negligence, unless the negligence arises from a duty independent of the duties imposed by the at issue contract. (Doc. # 23 at 7). By contrast, TWC argues that Kentucky law permits tort claims to proceed in this early stage of litigation as an alternative avenue of recovery. (Doc. # 25 at 1). Therefore, as to Helitech’s Motion to Dismiss TWC’s Counterclaims, there is only one operative issue—whether under Kentucky law, a claim for negligence may accompany a contract claim where the claimant has not alleged breach of a duty separate from the duty imposed by the contract. Kentucky Courts have recognized that “a party having viable contract and negligence claims may pursue both, [but] the initial inquiry is whether there is a negligence

claim independent of the contract claim.” Superior Steel, Inc. v. Ascent at Roebling’s Bridge, LLC, 540 S.W.3d 770, 791 (Ky. 2017); see also Kevin Tucker & Assocs., Inc. v. Scott & Ritter, Inc., 842 S.W.2d 873, 874 (Ky. Ct. App. 1992), overruled on other grounds by Degener v. Hall Contracting Corp., 27 S.W.3d 775 (Ky. 2000). “Liability for a [] negligence claim must be predicated on an extra-contractual duty.” RQSI Global Asset Allocation Master Fund, Ltd. v. Apercu Int’l PR LLC, 683 F. App’x 497, 502 (6th Cir. 2017) (citing Mims v. W.S. Agency, Inc., 226 S.W.3d 833, 836 (Ky. Ct. App. 2007)). Accordingly, a breach of duty arising under a contract “must be addressed under contract, and a tort action will not lie”; “[a] breach of duty arising independently of any contract duties between

the parties, however, may support a tort action.” Nami Res. Co., L.L.C. v. Asher Land & Mineral, Ltd., 554 S.W.3d 323, 336 (Ky. 2018) (emphasis in original) (quoting Superior Steel, 540 S.W.3d at 792). In other words, in order to allege negligence alongside a breach of contract claim, the negligence claim must arise from a duty separate from the underlying contract. TWC’s counterclaim includes claims of negligence and professional negligence. (Doc. # 16 at 24-26).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Presnell Construction Managers, Inc. v. EH Construction, LLC
134 S.W.3d 575 (Kentucky Supreme Court, 2004)
Pathways, Inc. v. Hammons
113 S.W.3d 85 (Kentucky Supreme Court, 2003)
Mims v. Western-Southern Agency, Inc.
226 S.W.3d 833 (Court of Appeals of Kentucky, 2007)
Isaacs v. Smith
5 S.W.3d 500 (Kentucky Supreme Court, 1999)
Degener v. Hall Contracting Corp.
27 S.W.3d 775 (Kentucky Supreme Court, 2000)
Kevin Tucker & Associates, Inc. v. Scott & Ritter, Inc.
842 S.W.2d 873 (Court of Appeals of Kentucky, 1992)
Henry Hill v. Rick Snyder
878 F.3d 193 (Sixth Circuit, 2017)
Boland-Maloney Lumber Co. v. Burnett
302 S.W.3d 680 (Court of Appeals of Kentucky, 2009)
Howard v. Spradlin
562 S.W.3d 281 (Court of Appeals of Kentucky, 2018)
Superior Steel, Inc. v. Ascent at Roebling's Bridge, LLC
540 S.W.3d 770 (Missouri Court of Appeals, 2017)
Nami Res. Co. v. Asher Land & Mineral, Ltd.
554 S.W.3d 323 (Missouri Court of Appeals, 2018)
Hayes v. D.C.I. Props.-D KY, LLC
563 S.W.3d 619 (Missouri Court of Appeals, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
CNC Foundations, Inc. v. Turnbull-Wahlert, Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/cnc-foundations-inc-v-turnbull-wahlert-construction-inc-kyed-2021.