Clemens Construction Co. v. United States

153 Ct. Cl. 170
CourtUnited States Court of Claims
DecidedApril 7, 1961
DocketNo. 421-56
StatusPublished

This text of 153 Ct. Cl. 170 (Clemens Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Clemens Construction Co. v. United States, 153 Ct. Cl. 170 (cc 1961).

Opinion

Per Curiam

: This case was referred to Trial Commissioner Mastín G. White pursuant to Eule 45 with directions to make findings of fact and recommendations for conclusions of law. The commissioner has done so in a report filled January 6, 1960. Briefs were filed by both parties, exceptions to the commissioner’s findings were taken by the defendant and the case was submitted to the court on oral argument by counsel. Since the court is in agreement with the findings and recommendations of the trial commissioner, as hereinafter set forth, it hereby adopts the same as the basis for its judgment in this case. Plaintiff is therefore entitled to recover and judgment will be entered to that effect with the amount of recovery to be determined in further proceedings pursuant to Eule 38(c).

It is so ordered.

OPINION OP THE COMMISSIONER

This case involves a controversy that arose out of a contract covering the construction of a levee in Florida by the plaintiff for the Corps of Engineers, Department of the Army.

In accordance with Eule 38 (c), the trial was limited to the issues of law and fact relating to the right of the plaintiff to recover, and the determination of the amount of recovery and the amount of offsets, if any, was reserved for further proceedings.

Embankment Placed

The principal legal question in the case relates to the interpretation that should be given to a contract provision stating that:

Payment for construction of [the southern section of the] levee * * * will be made on the basis of quantities of embankment placed. Measurements of quantities to [173]*173be paid for will be made by computing the volume between the ground surface existing after stripping of levee base is completed, and the specified construction cross-section. * * *

The events leading up to the present litigation began on April 3,1951, when the Corps of Engineers issued specifications, drawings, and invitations for bids relative to the prospective construction of Levee L-40 in Florida. The work was to consist of constructing 26.2 miles of continuous levee, running generally from north to south, with materials excavated from a continuous borrow pit along the west side of, and parallel to, the levee. The borrow pit was to be separated from the levee by a 40-foot strip of land. It was indicated that, before the actual excavation of material from the borrow pit and its placement as part of the levee began, both the surface of the borrow pit and the base of the levee were to be cleared and stripped of all vegetation, stumps, and roots.

The levee was to comprise two sections: a northern section slightly more than 2 miles in length, and a southern section slightly more than 24 miles in length. Only the southern section is involved in the present litigation.

The levee was to traverse a low, fiat, wet area along the eastern edge of the Everglades. The ground in the particular area consisted, first, of a layer of peat, which is an organic, fibrous, compressible, and rather unstable soil. Prospective bidders were informed that wherever in the southern section the thickness of the peat exceeded 4 feet, the peat should be removed from the borrow pit down to the point where the average thickness of the peat remaining in the borrow pit would be 3 feet. The excess peat so removed was to be wasted (i.e., it was to be deposited alongside and to the west of the borrow pit, and was not to be used as material for placement in the levee). Beneath the peat, there was a mixture of sand, shell, and conglomerate rock. The peat remaining in the borrow pit after the stripping operation and the removal and wasting of the excess peat (if required) was to be used along with the underlying material as part of the levee.

[174]*174It was indicated that payment for the work performed in the northern section, and for the removal of the excess (or waste) peat from the borrow pit in the southern section, would be made on the basis of the quantity of material excavated from the borrow pit. In connection with this phase of the work, bidders were to quote as Item No. 1 a unit price of so much per cubic yard for “Excavation, unclassified.”

On the other hand, prospective bidders were informed that the work of constructing the levee in the southern section would be paid for in accordance with the provision quoted at the beginning of this part of the opinion. Bidders were to quote as Item No. 2 a unit price per cubic yard for “Embankment” in connection with the construction work in the southern section.

The plaintiff submitted the lowest bid on the levee job mentioned above, and a contract was entered into between the plaintiff and the defendant (represented by a contracting officer of the Corps of Engineers) on May 7, 1951. The plaintiff’s bid and the contract fixed $0,422 per cubic yard as the unit price for Item No. 1, “Excavation, unclassified,” and the same amount per cubic yard as the unit price for Item No. 2, “Embankment.”

The contract contained the provision previously quoted at the outset of this part of the opinion with respect to the basis of payment for the construction of the southern section of the levee.

In constructing the northern section of the levee, and in removing from the borrow pit and wasting excess peat in the southern section, the plaintiff excavated 1,039,599 cubic yards of material from the borrow pit. The Corps of Engineers paid the plaintiff for this work at the contract unit price of $0,422 per cubic yard for “Excavation, unclassified” (Item No. 1), or a total of $438,710.78. There is no controversy between the parties respecting this phase of the work or the sufficiency of this payment.

In the southern section, after the levee base and the surface of the borrow pit had been stripped and the excess peat in the borrow pit had been removed and wasted, the plaintiff excavated from the borrow pit 4,798,058 cubic yards of material. A total of approximately 4,618,058 cubic yards of [175]*175this material was placed by the plaintiff upon the prescribed levee site; and the remainder of the material (or approximately 180,000 cubic yards) was either spilled on the 40-foot strip of land separating the borrow pit from the levee site or was placed on the strip by the plaintiff to improve the working surface, and was not recovered by the plaintiff for placement as part of the levee.1 With the placement of the 4,618,058 cubic yards (approximately) of material upon the prescribed levee site, the peat comprising the ground surface of the levee base, as it existed upon the completion of the stripping operation, subsided beneath the weight of the added material and became inextricably mixed with it. The whole mass sank until it came to rest on the underlying sand, shell, and rock. This occurred during the construction of the levee, and before the embankment was measured for payment purposes.

Of the total of approximately 4,618,058 cubic yards of material which the plaintiff placed upon the prescribed levee site in the southern section, approximately 1,288,617 cubic yards of the material either subsided ('along with the ground surface of the levee base) below the line representing the elevation of the ground surface as it had existed after the stripping of the levee base and before the addition of the material from the borrow pit, or disappeared in the form of shrinkage as the wet material dried out after being incorporated in the levee embankment.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Peter Kiewit Sons' Co. v. United States
109 Ct. Cl. 390 (Court of Claims, 1947)
Orino v. United States
77 F. Supp. 938 (Court of Claims, 1948)
Williams v. United States
127 F. Supp. 617 (Court of Claims, 1955)

Cite This Page — Counsel Stack

Bluebook (online)
153 Ct. Cl. 170, Counsel Stack Legal Research, https://law.counselstack.com/opinion/clemens-construction-co-v-united-states-cc-1961.